Following four days of successful improvement work on the Lewes to Seaford line in East Sussex, Network Rail have welcome passengers back on board.

The major upgrade programme, that took place between Nov 28 and Dec 1, included replacing the signalling system controlled by three signal boxes dating back to 1879.

The new technology is now controlled from a modern operating centre at Three Bridges, with a view to reduce delay time and provide a more reliable service for passengers.

The project also saw the removal of the removal of 18A points which were replaced with 40m of plain line track.

Thanks to the upgrade programme, three times as many trains and passengers can now use the diversionary route for London to Brighton services via Lewes, during disruption on the Brighton Main Line.

This weekend was also the final weekend of closure for the line between Barham and Havant, via Chichester, as major track replacements and station refurbishments comes to an end. The project has been ongoing since later October and has seen 2km of new track laid, providing a better ride for passengers.

The thousands of Southern Rail passengers who use the line for daily commuting returned yesterday (Dec 2) to a brighter and cleaner station following a partnership between Network Rail and Govia Thameslink Railway that carried out a series of station improvements at Seaford, Bishopstone, Newhaven Town, Southease and Glynde stations.

John Halsall, managing director for Network Rail Southern Region, said:

“I’d like to say thank you to the passengers who have been disrupted by this crucial work, which was needed to modernise the signalling system.

“I am extremely grateful that so many changed their plans for the four days to enable us to concentrate the work in this way. The alternative would have meant many more weekend closures for our engineers to achieve the same thing, so this has been much more effective for them as well as for us.

“The work means we can provide a more reliable service that passengers deserve and can depend on.”

 

Photo: Newhaven Harbour

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Northern supports song writing workshops in the community

10/08/2020Northern supports song writing workshops in the community

As part of the Northern supported project Lyric and Line, singer-song writer Gareth Davies-Jones has been working with three groups with addition... more >
HS2 searching for high voltage power supply systems

10/08/2020HS2 searching for high voltage power supply systems

With the green light for construction given a few weeks ago, HS2 have today (10 Aug) began the search for expert contractors to deliver the high ... more >
HS2 installs new bridge over M42 in just two days

10/08/2020HS2 installs new bridge over M42 in just two days

A 65-metre bridge was installed in just two days and ahead of schedule as the motorway opened 22 hours earlier than planned. The works near ... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >