Civils and stations

08.04.08

Mound Tunnel lowering & Waverley Bridge girder works

Network Rail's Transport Scotland funded £150million upgrade of Edinburgh Waverley Station's tracks and platforms was completed on schedule and within budget on 16th November 2007. The work provided half a mile of new and extended platforms including four new platforms numbered 1, 3, 10 and 20. The station was also provided with two new escalators and two new passenger lifts.

While this was going on, over two miles of new track was laid as part of the extensive remodelling and 37 new signals commissioned enhancing station capacity. During the Christmas and New Year blockade, which was safely and successfully delivered , the tracks running through the middle Mound Tunnel were lowered providing clearance for electrification works and around 100 bases and other electrification structures were installed in the tunnel and on the Waverley Bridge.


Track works

The track works completed during the blockade consisted of:

• Track bed lowered by 230mm (including “points 157”) and 180 metres of new track installed.
• 110 metres (approx.700 tonnes) of new chips installed on both lines X and Y.
• New crossing panel for 161 points installed and closure rails cut to suit.
• Renewed ballast from out with the Mound Tunnel for a distance of 140 metres.

Girder works

The works to the girder completed during the blockade consisted of:

• Installation of temporary works foundations.
• Trestles erected and jacked to design levels and monitored for settlement. When rate of settlement had reduced to a level that allows jacking loads to be maintained, cutting of the girder to a depth of 300mm commenced.
• South side of the girder (over roads 14 and 15) cut approximately 8 metres in length and to a depth of 300mm. Then bottom flange removed and replaced with the new 30mm thick steel flange plate.
• North side flange (over roads 16, mid road and 17) cut approximately 11 metres and to a depth of 300mm and removed before new 30mm thick steel flange plate was fitted.
• Approximately 730 steel plates, angles, splices and flanges, weighing approximately 31 tonnes, installed for strengthening of the girder and fitted using circa 7000 bolts.
• Final welding, bolt installation and inspection carried out before the removal of the jacking loads and monitoring equipment.
• Removal of trestles and temporary works foundations.
• Track / platform surveys were undertaken on completion of the works prior to bringing back into operational use.

Signalling

The signalling works consisted of disconnections and reconnection works.

OLE

OLE works within Mound Tunnel were as follows:

• 220 metres of Furrer and Frey rigid conductor bar installed within the Mound Tunnel.

Civils

Civil works carried out and completed were:

• Sandstone invert cut in Mound Tunnel – cut depth varied between 20mm and 80mm.
• Sandstone rib cut on both sides of the tunnel to approximately 140mm depth to accommodate clearance for “pantograph”.
• 170 metres of drainage installed in 6 foot between lines X and Y throughout tunnel.

Tell us what you think – have your say below, or email us directly at opinion@railtechnologymagazine.com

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Maritime Transport launch new rail services

17/07/2019Maritime Transport launch new rail services

Maritime Transport has launched two new rail services from DP World London Gateway to its rail terminals in Trafford Park and Wakefield. It ... more >
Campaign for Windsor Link Railway to be revived

17/07/2019Campaign for Windsor Link Railway to be revived

A campaign for a rail link between Windsor and Heathrow Airport is to be revived, after the scheme was turned down by the Department for Transpor... more >
Conwy Valley Line to partly reopen tomorrow

17/07/2019Conwy Valley Line to partly reopen tomorrow

The Conwy Valley line is set to reopen for passengers ahead of the National Eisteddfod in Llanrwst, Network Rail has announced. Llandud... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey’s commercial account director, Anna Delvecchio, for her insight into what the Rail Sector Deal means for the rail industry and its supply chain. Anna started her career as an apprentice at the age o... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

By Ewan Quayle, Rail Technology Magazine Reporter Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on R... more >