Amended HS2 works add half a billion pounds to the project’s cost

Changes to HS2 works to accommodate landowner requirements, design alterations and the extension of the Chiltern tunnel are set to add half a billion pounds to the project’s cost.

According to figures released today (12 October) and signed off by HS2 Ltd boss Simon Kirby, amendments made to accommodate requests from landowners and occupiers are expected to cost over £160m (in Q2 2011 prices, with contingency included).

These amendments relate to several districts, parishes and London boroughs, as well the city of Birmingham, and include the purchase of land, minerals and permanent rights and compensation. It also covers extra costs tied to railways (earthworks, tunnels and bridges, electrical and signalling), buildings, road and streets and bridges over HS2.

Changes to tunnels and bridges alone are adding almost £90m to projected costs.

Modifications related to the design of the works authorised by the Bill [HS2 Hybrid Bill] will cost an extra £160m, almost half of which related to the purchase of land, minerals and permanent rights and compensation.

But amendments relating to the extension of the Chiltern tunnel in the parishes of Amersham, Little Missenden and Great Missenden in Buckinghamshire are responsible for nearly half of the entire bill of surplus costs at a projection of almost £260m.

The overwhelming majority of this is a result of changes to tunnels and bridges.

Last week, RTM revealed the details of each of the seven civil engineering contracts currently up for grabs as part of HS2’s first phase. Works for the Chiltern tunnel spanned two of these contracts, with the first including both the tunnel and the Colne Valley viaduct.

This contract, valued between £800m and £1.3bn, included a 22km section, through the 15.8km long Chiltern tunnel.

Also today, the government released details of these additional and replacement plans and sections. The three-volume documents show extra details along the centre line of new and amended works, as well as the level of those works in relation to existing land and features.

The first volume related to Kilburn to Lower Boddington, while the second is for Ladbroke to Handsacre & Curdworth to Curzon Street. The third and smallest volume is for SO33 plans and route-wide and SO57 sections.

Please be aware that these documents are very large.

(Top image c. HS2 Ltd Birmingham & Fazeley canal viaduct)

Comments

Geordie   15/10/2015 at 13:37

The tip of the iceberg, and a sign of bigger things to come. I look forward to the extra money required for all the tunneling needed in North West London and Manchester, as well as the construction of stations there. Hold onto your hats folks, it's going to be eye-watering!

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >