HS2

28.04.16

Council leaders criticise lack of clarity over TransPennine upgrade plans

Delays to the TransPennine electrification and route upgrade risk leaving the region with a “sub-optimal” service, and there are concerns about the current programme, Greater Manchester Combined Authority (GMCA) has warned.

In papers put before the GMCA before tomorrow’s board meeting, the authority says that while it welcomes the ‘unpausing’ of the TransPennine Upgrade Programme following Sir Peter Hendy’s review, it remains concerned that completion of the programme is now delayed until 2022.

The GMCA also said that there are no firm dates for some stages of the project, which could create problems with planning integrated infrastructure schemes and procurement of rolling stock, including causing delays to the promised new Arriva trains on the northern line.

Put together by Cllr Richard Leese, GMCA portfolio lead for rail, and Jon Lamonte, portfolio lead chief executive for Transport , the report adds that it is imperative the TransPennine upgrade scheme be delivered promptly.

“At the very least the target should be for the original scheduled delivery date without the project being reduced in scope in any way,” they say. “Delay of this scheme will leave a sub-optimal service solution for local journeys, with the correct matching of supply to different types of demand unable to be met.”

The report adds that Sir Peter Hendy’s review “contains ambiguous language and non-specific targets”.  GMCA also criticises the review for a lack of transparency around its methodology, meaning that there is a lack of visible scrutiny and mitigation of risks.

They also say that the highest priority projects for Greater Manchester railways are maintaining the committed delivery date for the Orsdall Chord development or even bringing it forward, as well as redeveloping Oxford Road and Piccadilly stations.

GMCA are also developing a rail industry plan, which they aim to have ready by September 2016.

(Image: Manchester Piccadilly, c. Dave Thompson from PA Images)

 

 

 

Comments

Chris M   01/05/2016 at 02:55

It's vague because the scope of the works has been thrown up in the air by the Northern Powerhouse political development and the slow rate of electrification progress elsewhere. The original idea was to just electrify what was already there, locking in speed restrictions and obsolete track formations. Now they have to figure out the scale of enhancements necessary to bring the Leeds - Manchester time down to 40 minutes, Ideally they need to know the NPR plan in fine detail to decide what is worth doing and what isn't. But no firm decisions on any NPR routes or infrastructure seem to have been taken yet.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Alstom set to purchase Bombardier Transportation

18/09/2020Alstom set to purchase Bombardier Transportation

Alstom’s move to takeover Bombardier Transportation has progressed following the announcement that Alstom has signed the sale and purchase ... more >
Flood-damaged Edinburgh-Glasgow line to reopen

18/09/2020Flood-damaged Edinburgh-Glasgow line to reopen

The Edinburgh-Glasgow, via Falkirk High, railway line will reopen for passengers on Monday (21st Sept.) Network Rail engineers have worked t... more >
East Coast Main Line: £216.2m contract to increase power supply

18/09/2020East Coast Main Line: £216.2m contract to increase power supply

Following a £216.2m contract awarded by the Rail Electrification Alliance, The East Coast Main Line Power Supply Upgrade can move forward i... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >