The DfT has admitted that controlling the costs of the HS2 project will be “challenging” and that the cost estimates of delivering Phase 2b will not be certain until 2019.

The news came from the department’s permanent secretary, Phillip Rutnam, in written evidence to support an ongoing Public Accounts Committee (PAC) inquiry on the Great Western Railway.

Rutnam said that the cost estimates of Phase 2b, whose preferred route was announced late last year, will become more certain as HS2 Ltd awards contracts this year to progress the design of Phase 2b.

“On the timing to secure assurance on the delivery of the identified potential efficiencies, the 2015 Spending Review set a budget for HS2 of £55.7bn,” Rutnam wrote in his evidence report.

“HS2 is an ambitious engineering project which will take many years to complete, and like any programme of this scale, controlling costs will be challenging, yet the government is committed to delivering HS2 within this budget.

“We continue to scrutinise HS2 Ltd’s cost estimates closely and will report revised estimates in the Outline Business Case when it is published in 2019 to support the Phase 2b hybrid Bill that we plan to deposit in Parliament at the same time.”

The government first announced its preferred Phase 2b route, which will travel from Crewe to Manchester and from the West Midlands to Leeds, in November last year.

The DfT is currently consulting on seven substantial changes to the route, including a new connection to Sheffield’s existing train station. The public consultation on the Sheffield route is due to end in March, with the government to publish its formal response later this year.

“We expect HS2 Ltd will be able to take advantage of experience and learn lessons from the Phase 1 and Phase 2a processes,” Rutnam added.

“Moreover, cost estimates will become more certain as HS2 Ltd awards contracts in 2017 to progress the design of Phase 2b in readiness for the deposit of the Phase 2b Hybrid Bill.”

The permanent secretary argued that the contracts should provide an “appropriate level of maturity” around the cost estimates for Phase 2b by the time that its business case is published in 2019.

Separately during the PAC hearing, which took place in 14 December, Phillip Boswell MP also asked Rutnam about the government’s strategy and plans for the necessary skills to deliver rail enhancements.

Rutnam highlighted the government’s announcement of its Transport Infrastructure Skills Strategy (TISS) in January 2016 which aims to create 30,000 apprenticeships within the rail and road sectors by 2020. The strategy will be directed by the industry-led Strategic Apprenticeship Taskforce, which was announced last April and is chaired by Mike Brown, commissioner of Transport for London.

The permanent secretary further explained that the TISS will be supported by the Rail Sector Skills Delivery Plan announced by the rail industry in December, which will look to develop training standards and encourage recruitment and retention in the sector.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here 

Comments

Tothehills   18/01/2017 at 09:08

So before they even start serious works the DfT has decided to get its excuses in! Now there is cofidence! We need it but now they have shed great doubts that they have any control over this gold plated project.

Geordie   20/01/2017 at 13:21

It's just as well that the country is rolling in money to fund this marvellous, well thought out project that will benefit millions...

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

‘Local hero’ recognised for his work with homeless in Blackpool

17/09/2019‘Local hero’ recognised for his work with homeless in Blackpool

Chris Conway, a Network Rail signaller, was awarded for his contribution to tackling homelessness last night at an awards ceremony in Blackpool. ... more >
Isle of Wight rail line receives £26m investment

17/09/2019Isle of Wight rail line receives £26m investment

Government has unveiled a £26m investment package into the Isle of Wight railway line, to help modernise and improve the line and its ... more >
Doncaster station to celebrate engineering, speed and connectivity through art

17/09/2019Doncaster station to celebrate engineering, speed and connectivity through art

Rail users are in for a treat as plans for public art at Doncaster train station are revealed. The art will be a key part of the station’s ... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Connecting Network Rail with the supply chain

17/09/2019Connecting Network Rail with the supply chain

Continuing our mission to connect buyers with suppliers, This year TransCityRail North is adding a new element to the event. We are introducing an incomparable opportunity for you to meet with over 11 procurement directors from Network Rail at our exclusive 'Network Rail Meet the Buyers Hub'.  Situated at the heart of the event ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

  • 11/09/2019The next generation of rail infrastructure

    How the rail industry delivers the next generation of complex infrastructure will rely heavily on the people tasked with leading the projects, and the...
  • 11/09/2019Putting passengers first

    How does the rail industry design the railways for the next 40 years, and when it does, how do we make sure it’s all done with the passenger in mind?...
  • 10/09/2019Cleaning up the railways

    Jim Knox, director of Gard Chemicals, explains how the company is helping the rail industry ensure they have the best cleaning and maintenance...
View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >