HS2

03.03.16

Engineering solution found for Appleby landslip, but line remains closed

A massive landslip causing closures on the Settle to Carlisle line is a step closure to being solved after engineers developed a repair solution.

The 500,000 tonne landslip, caused by severe erosion of the embankment base near the River Eden, recent repeated storms and saturated ground, occurred on January 31 and has forced the Northern Rail line to close between Appleby and Carlisle, with a replacement bus service in place.

Network Rail announced today that the line will stay closed for many months, although they do not know exactly how long, while they carry out repairs at Eden Brows, near Armathwaite, Cumbria, involving major earthworks to stabilise the embankment and building a structure underneath the affected section of railway to support it.

Rhiannon Price, Network Rail’s project manager for the Eden Brows repairs, said: “We have carefully considered many repair options and we are satisfied the one we’re going with is the best.

“Our aim is to do a thorough job that leaves the Settle to Carlisle railway line in better shape than it was before this land slip. As well as tackling this problem we intend to bring forward other, less major jobs we have earmarked on the shut section of line.

“We are acutely mindful of the impact on communities served by this line, including businesses reliant on tourist trade. We are working to fix this slip as quickly as possible.”

Between 4.30pm and 7.00pm today, Network Rail and Northern Rail will host a public drop-in event in Appleby station waiting room for local people to ask questions about the closure.

Today and tomorrow Network Rail staff, supported by members of the Friends of Settle Carlisle Line group, will be on a two-day walk-about in the communities affected by this closure, including Appleby, Lazonby, Kirkoswald, Armathwaite and Langwathby.

The line between Appleby and Carlisle was closed on 9 February after Network Rail's aerial and ground surveillance detected that a 130-metre-by-70-metre section of the Eden gorge embankment was giving way.

Since then 80 engineers and geotechnical experts – half based in an office, half on site – have been working on the problem.

The line was originally due to reopen by the beginning of March, but repairs have been complicated by the size of the landslip, the remote location and the fact that the area of land it affects, which is more than 130m long and 70m wide, is still moving.

Comments

Michael Still   03/03/2016 at 21:38

It is important to reopen this line. Most importantly we want to travel on it in on our holidays in May.

Manh Truong   04/03/2016 at 08:09

FC Barcelona 5 - 1 Rayo Vallecano 03/04/2016 ,La Liga Round 27 Highlight Resalte https://youtu.be/gB1EhlQmx48

Manh Truong   04/03/2016 at 08:10

FC Barcelona 5 - 1 Rayo Vallecano 03/04/2016 ,La Liga Round 27 Highlight Resalte https://youtu.be/gB1EhlQmx48

Tony   04/03/2016 at 13:08

Michael, I am afraid there is no chance that this line will be open by May. However, you may still travel on this beautiful scenic route, other than between Appleby and Carlisle which is bus only. May I suggest that you use between Settle and Appleby, you will still see some fantastic scenery.

Stpaddy   04/03/2016 at 13:54

As this is now going to be an extended closure, couldn't the replacement bus service to Carlisle run from a suitable station north of Appleby - ideally Armathwaite , leaving more of the line open for passengers, and with faster journeys through to Carlisle? I realise temporary track or signalling changes may be required to facilitate this.

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >