Network Rail unveils details of Tinsley chord for S. Yorkshire tram-train

The Sheffield to Rotherham tram-train project has entered its next phase, with Network Rail revealing its plans for the new section of track to connect the national rail and tram network.

The new Tinsley chord will link the railway and Supertram networks, passing under the Tinsley Viaduct. It will need 150 metres of new track with associated ground work, overhead line equipment to carry the power to the tram-trains and lineside equipment including a small new building to house electrical equipment.

Warrick Dent, area director for Network Rail, said: “This is an exciting stage of the project as we consult on plans which, if approved, will turn years of meticulous planning into Britain’s first operational tram-train service.”

He added: “Tram-trains are a common sight in Europe and we believe they could help to improve journey options for passengers around our towns and cities. Even though the tram-trains run elsewhere, we have had many complex issues to work through with our partners in the project to make sure that the vehicles can operate safely in Britain without causing unnecessary disruption to regular tram and rail passengers.

“We would encourage regular Stagecoach Supertram and Northern Rail passengers, local residents and landowners to view and comment upon the plans.”

Tinsley Chord map  v6

Tram-trains will provide a direct service between Sheffield city centre, Rotherham Central station and a new stop at Rotherham’s Parkgate retail park. They will use the existing Supertram route between Cathedral and Tinsley-Meadowhall South, and then move onto the rail network via the new chord to Parkgate.

New platforms will be built at Tinsley-Meadowhall South, and Rotherham Central Station’s platforms will be extended to facilitate the new service.

An application for a Transport Work Act Order (TWAO) will be submitted to the transport secretary in spring 2015. Dependent upon the TWAO process and decision, work to construct the chord is expected to start in spring 2016. Construction is expected to take approximately eight months.

The £60m tram-train pilot project was originally announced in May 2012 and was intended to begin operation from 2015, however it has since been beset by delays due to complications in adapting the heavy rail network for tram-train operation.

In December it was announced that as part of the Sheffield City Region Devolution Deal the government has committed to work with Network Rail to ensure the tram-train project is delivered in time for a January 2017 launch date.

Tram-train vehicles are currently being manufactured, and work to the tramway and depot to accommodate tram-trains is also underway. South Yorkshire Passenger Transport Executive is procuring seven new dual voltage vehicles (750V DC and 25kV AC) for the project from Vossloh España, using tram-trains that are part of the Citylink family. Each three-section Citylink vehicle is 37.2m long, 2.65m wide and they have low-floor doors. They will go into service in late 2016, initially just on the existing tram network.

Tell us what you think – have your say below, or email us directly at [email protected]

Comments

Pedr   06/02/2015 at 18:56

Please what is the radius of curvature? And at what speed will it be taken?

John Gilbert   06/03/2015 at 11:28

Fearfully sharp curves! Screeching around them will slow the service down unnecessarily, and it will do no good to the trams' running gear!!

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >
GTR spreads messages of support on Suicide Prevention Day

10/09/2020GTR spreads messages of support on Suicide Prevention Day

As today (10 Sept) mark the annual World Suicide Prevention Day, Govia Thameslink Railway (GTR), have revealed ‘Affirmation Art’ clus... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News