London Underground and TfL

10.01.19

Rail industry urges policymakers to save Crossrail 2 in wake of major Crossrail delays

The Railway Industry Association (RIA) has urged Crossrail policymakers not to postpone Crossrail 2 after it emerged that there are “thousands of hours of construction work still to be done” on Crossrail.

Following discussions at a London Assembly Transport Committee meeting, the RIA says it has become clear that money earmarked for Crossrail 2 will be diverted to complete the controversial Crossrail project, which has been hit with multiple delays and spiralling costs.

At the assembly’s committee meeting yesterday, current chief executive Mark Wild said there were thousands of hours of construction still to be completed. Bond Street, for example, is months from completion and still requires floors, ceilings, escalators, and a permanent power supply.

The comments, along with previously confidential documents released by TfL, revealed the extent of the delays and financial troubles, and that government and London transport chiefs were informed of the first alert that Crossrail’s schedule was in serious trouble as far back as June 2016.

Also speaking at the committee meeting, former boss Sir Terry Morgan revealed that TfL had altered his reports on the scheme’s progress and had been manipulating when information that the flagship project would be delayed was released.

Darren Caplan, chief executive of the RIA, has now urged policymakers not to delay a decision on Crossrail 2 in the wake of these controversies.

“Whilst this delay in the opening of Crossrail is regrettable – and the rail industry must always learn lessons on delivering major projects to deadline and budget – we should remember that schemes like Crossrail and Crossrail 2 have a transformational impact on the UK, its economy and connectivity and therefore a delay to one should not affect decisions on the other,” he said.

“Both these schemes are urgently needed to meet growing demand for rail services. Crossrail 1 will deliver over 57,000 new homes, generate 55,000 jobs and add over £42bn to the UK economy, benefits that will far exceed the final cost of the project, and Crossrail 2 will similarly support 200,000 new homes, 60,000 new jobs during the project and a 10% increase in rail capacity.”

Caplan said that the government, industry, stakeholders, and the Greater London Authority must work together to find ways of finishing Crossrail and to fund and safeguard the Crossrail 2 route alongside major projects like HS2 and Northern Powerhouse Rail ahead of the government’s Spending Review later this year.

Crossrail was given a £1.4bn bailout in December, with the Greater London Authority paying the majority via a DfT loan a day after the £15.4bn project was due to open on its original schedule. Crossrail is now not expected until 2020.

Image credit - Dominic Lipinski

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Greater Anglia brings in extra support for busy periods

21/11/2019Greater Anglia brings in extra support for busy periods

Office staff at Greater Anglia are being trained to help customers when stations are busy due to big events or disruption. Customer Action T... more >
Greater Anglia announces delays cut by almost half

21/11/2019Greater Anglia announces delays cut by almost half

Between December 2018 and October 2019, delay minutes for its Class 317 commuter trains, which run through Cambridgeshire, Hertfordshire and Esse... more >
Metrolink contactless payment system hits millionth journey

20/11/2019Metrolink contactless payment system hits millionth journey

Transport for Greater Manchester announced today (20th Nov) that at the weekend Metrolink’s contactless payment system hit the million-jour... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

14/11/2019Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

Rail Technology Magazine’s Matt Roberts explains the significant role data can play within the future development of the rail industry. Standing as a cornerstone of the UK transport network, the rail industry is forever striving to innovate and maximise efficiency in all aspects of i... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

  • 15/11/2019A workforce which reflects society

    Loraine Martins MBE, Director of Diversity and Inclusion at Network Rail, joins us in the studio for the third episode of our RTM podcast, talking at...
  • 02/11/2019Monica Barbosa: Women In Rail

    Director of business development and communications at Xrail, Monica Barbosa, thinks women are missing out on exciting opportunities because the...
  • 01/11/2019The dangers of fatigues

    Working long hours, poor health, too little sleep, a demanding job and more can all make us tired and affect our mental and physical performance...
View all News

interviews

Greater Anglia brings in extra support for busy periods

21/11/2019Greater Anglia brings in extra support for busy periods

Office staff at Greater Anglia are being trained to help customers when stations are busy due to big events or disruption. Customer Action T... more >