Khan told in July of ‘high risk’ to Crossrail launch date as TfL reveals project’s ‘failed governance’

Documents released by TfL show that the former Crossrail chairman Sir Terry Morgan warned Sadiq Khan in July that schedule plans were at “high risk” and have been called a “serious indictment of Crossrail’s failed governance.”

Over 100 documents have been released relating to Crossrail, including board meetings dating back to 2013. They “clearly demonstrate” that the London mayor and TfL have been fully transparent about what they knew and when regarding the nine-month delay to Crossrail, according to TfL.

They show that Crossrail reported growing costs and schedule pressures to both TfL and Khan throughout 2018 and that, at a meeting on 26 July, Crossrail briefed TfL executives and the London mayor that the official opening date, 9 December 2018, was at “high risk.”

But the documents show that Crossrail, which yesterday announced a further delay and a £1.4bn refinancing bailout from the DfT, did not make a formal decision to delay the project until 30 August.

The Crossrail documents are the latest update in a long-standing spat between Sadiq Khan, Sir Terry and the London Assembly Transport Committee over the nine-month delay to the Elizabeth Line project and when Khan was made aware of it.

Before the chair of Crossrail resigned last week, Morgan insisted that Khan had withheld the information and said he was “in absolutely no doubt” that he was told in July about the need to delay the project.

The London Assembly Transport Committee accused Khan of “deliberately misleading” the public and the committee and of withholding the information until it was made public in August.

Khan has denied these claims, but the committee said that the mayor has still failed to provide all the information requested. Its chair Caroline Pidgeon MBE said: “Once again, with this response from the mayor, we are left wanting.”

TfL added that if Crossrail had concluded at the end of July that the delivery date could not be met, then it would have been legally obliged to notify TfL and the DfT, but no such notice was issued until 30 August.

In his evidence to the transport committee, Sir Terry said: “We have always had to separate fact from concerns. The fact is that we did not have a formal position to take until 29 August.

“We did brief informally about concerns that we had at the board meeting and indeed in briefings with the mayor, but the mayor did not have any information of the sort that we provided on 30 August any day earlier than that date.”

The London mayor commented: “I’m pleased that these documents confirm that I have been fully transparent about what I knew when, and am hopeful the funding deal with government will now allow us to get the Elizabeth Line open as quickly as possible so that Londoners feel all the benefits.”

Khan said he remained “deeply angry and frustrated at the delays and cost overrun,” which is why he asked TfL to commission an independent review.

Image credit  -Jonathan Brady/PA Archive/PA Images

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

22/03/2019Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

A new £208m Belfast Transport Hub with major rail and bus connections has been granted planning permission by the Department of Infrastruct... more >
New to-the-minute measures for train punctuality introduced to tackle delays

22/03/2019New to-the-minute measures for train punctuality introduced to tackle delays

New measures of train punctuality are to be released by train operators and Network Rail next month in a bid to improve performance. The Rai... more >
FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

22/03/2019FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

FirstGroup has finalised a £100m order for Hitachi AT300 electric trainsets in a partnership between the two companies to create a new Lond... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

The West Midlands 30-year strategy

19/03/2019The West Midlands 30-year strategy

Malcolm Holmes, executive director of West Midlands Rail Executive (WMRE), outlines the West Midlands Rail Investment Strategy 2018-2047. The West Midlands Rail Executive was formed three years ago to give local authorities a direct influence over the award of the region’s main rail ... more >
read more blog posts from 'the sleeper' >

comment

26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >
East West Rail: the next steps

19/03/2019East West Rail: the next steps

In January, five route options for the central section of East West Rail were published as part of a public consultation on the next phase of the... more >
Rail's role in transit-orientated developments

19/03/2019Rail's role in transit-orientated developments

Jonathan Bray, director at the Urban Transport Group (UTG), argues that transit-oriented developments are the future – and that rail has a ... more >

rail industry focus

View all News

interviews

Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

22/03/2019Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

A new £208m Belfast Transport Hub with major rail and bus connections has been granted planning permission by the Department of Infrastruct... more >