HS2 land purchase costs triple in six years, ‘significant uncertainty’ remains

HS2 Ltd’s acquisition of properties has been criticised for soaring costs and slow payments in the National Audit Office’s (NAO’s) latest report on the scheme.

Only half of advance payments to claimants have been completed within the required three-month period from HS2 Ltd after receiving a claim request, the auditor said, prompting further concerns about the rate of acquisition of land for the £56bn project.

Under the compulsory purchase for Phase 1 – between London and the West Midlands – property owners must receive a payment of 90% of the estimated value of their land within three months of HS2 taking possession.

However, between March 2017 and August 2018 payments have been later than the three months or are forecast to be later in 52 out of 108 cases. For 35 of these, HS2 concluded that the main reason behind the delay is that claimants have not provided the required information in a timely manner.

Estimated costs for HS2 Ltd to buy land and property for Phase 1 have already “increased significantly” since the start of the programme, according to the spending watchdog. In 2012, HS2 Ltd’s estimate of the net cost — cost after resales — to acquire land and property that supported its first baseline cost and delivery plan was £1.1bn. By 2013, around the time the Hybrid Bill was deposited, this had increased to £1.6bn. The most recent estimate in 2017 was £3.3bn — almost triple the original estimate.

Factors behind the spike in costs included “significant additions” to the scope of the programme, such as additional junctions and route changes. “These changes have resulted in an increase in the amount and type of property required, and therefore the cost to acquire the property needed has increased by approximately £175m (2011 prices),” it added.

Despite the growing overhead for land acquisition, the NAO noted that HS2 Ltd expects that costs “will remain within available funding,” although the early stage of the programme means that there remains “significant uncertainty” about what the final costs will be.

“There is potential for further changes to the scope of the programme, and therefore the amount of land required, the number of property owners that will apply for compensation under discretionary schemes is uncertain, and the final settlement value of almost all properties, including some high-value properties, has not yet been decided,” the report found.

“Although HS2 Ltd has made efforts to improve its land and property function since 2015, there is work to be done to support claimants to receive timely compensation where they are due an advance payment.

“While HS2 Ltd’s estimate of the cost of land and property has increased significantly over time, cost estimates, particularly in this sort of major land acquisition programme, are inherently uncertain and subject to change as more information becomes known about both the design and operation of the railway, and the nature of the land and properties required.”

RTM has contacted HS2 Ltd for comment.

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

ORR report: ‘No one took charge’ in May timetable chaos, ‘everyone made mistakes’

20/09/2018ORR report: ‘No one took charge’ in May timetable chaos, ‘everyone made mistakes’

A scathing report into the May timetable chaos has blasted transport secretary Chris Grayling, Network Rail, and the DfT’s handling of the ... more >
Government rejects claims of transport spending ‘regional imbalance’

20/09/2018Government rejects claims of transport spending ‘regional imbalance’

The Transport Committee has urged the DfT to “be more specific about the economic rebalancing effects it intends to achieve&rdquo... more >
DfT quietly pulls the plug on CrossCountry franchise competition

20/09/2018DfT quietly pulls the plug on CrossCountry franchise competition

The government has decided to pull the plug on the CrossCountry franchise competition as a result of its rail review announcement today. Bec... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Going global: an interview with Network Rail’s Leevan Finney

29/08/2018Going global: an interview with Network Rail’s Leevan Finney

RTM’s Jack Donnelly sat down with one of the leading minds behind Network Rail’s most advanced and innovative rail maintenance techno... more >
Transforming travel in the north west

06/02/2018Transforming travel in the north west

RTM’s Josh Mines talks to Robin Davis, head of new trains at TransPennine Express (TPE), about the huge rolling stock change journey the co... more >
Thameslink: Nearing the end of the line

23/01/2018Thameslink: Nearing the end of the line

RTM’s Josh Mines catches up with Mark Somers, project director for Thameslink, on how the final stages of the programme are progressing and... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

The East Coast franchise report tells us what we already knew: it was a bid set up to fail

18/09/2018The East Coast franchise report tells us what we already knew: it was a bid set up to fail

RTM's Jack Donnelly assesses what the Transport Committee's latest report on the VTEC franchise means for the industry as a whole “Eve... more >
read more blog posts from 'the sleeper' >

comment

Northern Powerhouse Rail: The need for change

18/09/2018Northern Powerhouse Rail: The need for change

Northern Powerhouse Rail (NPR) will be transformational for the north – it will change the way people live, work, and play. It will rebalan... more >
Innovation through people and technology

18/09/2018Innovation through people and technology

Ian Prosser, HM chief inspector of railways and director of railway safety at the ORR, picks out the key industry challenges to focus on based on... more >
Why we all must mind the gap

18/09/2018Why we all must mind the gap

Clair Mowbray, chief executive of the National College for High Speed Rail (NCHSR), explains how we can all ensure the UK’s next generation... more >
3D printing: from virtual to real

11/09/20183D printing: from virtual to real

Like so many other technological advancements, 3D printing has moved from being the stuff of science fiction, through niche industrial applicatio... more >