Northern Line Extension enabling works completed ahead of schedule

The first phase of enabling works on the London Underground Northern Line Extension has been completed ahead of the planned 19 week schedule.

Amey engineers designed and installed eight articulation joints along a 55m section of the South West Storm Relief Sewer, which will allow it to flex during the excavation and construction of the extension’s 5.2m-diameter running tunnels.

The works also required the diversion of flow to provide safe and adequate access and egress for operatives, materials and equipment.

Kevin Fowlie, managing director of utilities at Amey, which acted as a subcontractor for the Ferrovial Agroman and Laing O'Rourke (FLO) joint venture holding the contract to build the extension, said: “Our approach to these works was based on a methodology used on another successful project previously carried out by Amey on the North East Storm Relief Sewer.

“Drawing on our experience in this way ensured that we were able to minimise delays and support the project's wider schedule and performance indicators.”

Jonathan Cooper, project manager at NLE Tunnels & Utilities, added that Amey and FLO had worked “incredibly hard” on the works. Phase two of the enabling works, including settlement remediation, is due to start in 2018.

The extension will include two new stations at Battersea Power Station and Nine Elms, due to be completed in 2020. It is intended to support 25,000 new jobs and 20,000 new homes.

However, concerns were raised about the state of the project after it emerged that redesigning Battersea Power Station would add an extra £240m to the costs.

Last year, the Independent Investment Programme Advisory Group warned Transport for London that the project “remains of high concern” because of the risk of delays.

(Image c. Loco_Steve from Flickr)

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here 

Comments

Andrew Gwilt   10/01/2017 at 15:22

The new Battersea tube station on the extended Northern Line will be located not far from Battersea Park and Clapham Junction as its a out-of-Interchange with walking distance between the 3 stations. Plus will the Northern Line be split with the current Northern Line operating between Battersea-Edgware via Charing Cross/Camden Town and a new renamed tube line say like "Morgan Line" to operate between Morden-High Barnet via Bank/Camden Town and Finchley Central-Mill Hill East.

Add your comment

rail technology magazine tv

more videos >

latest rail news

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Sept) on World Electric Veh... more >
Contract awarded by Network Rail to strengthen bridges

09/09/2020Contract awarded by Network Rail to strengthen bridges

Three contracts have been awarded by Network Rail to carry out strengthening work to three railway bridges across the Wessex route in the South o... more >
New electric train fleet revealed for Birmingham’s Cross-City Line

09/09/2020New electric train fleet revealed for Birmingham’s Cross-City Line

The electric train fleet set to transform travel on Birmingham’s Cross-City Line has been revealed to rail passengers in the West Midlands.... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across t... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Sept) on World Electric Veh... more >