Rail Industry Focus

01.11.15

Strengthening the Haymarket tunnels

Source: RTM Oct/Nov 2015

Angus MacGregor and David Gibson of BAM Ritchies give details of a project to strengthen two Network Rail tunnels in Edinburgh.

The Haymarket, a £200m joint venture development in Edinburgh between Interserve and Tiger Developments, is approaching the milestone of the pre-construction enabling works phase 1.

Taking two years of painstaking work, the strengthening of two Network Rail tunnels underneath the site will have taken over 100,000 man-hours to complete before above-ground work can begin.

img 2523

The reinforcement of the north and south tunnels, which carry all east-west traffic from Edinburgh Waverley, has been further compounded by the necessity that work is undertaken at night to avoid any disruption to train services. About 850 trains travel through the tunnels each day reaching much of Scotland, including Glasgow and Fife, suburban lines to the east as well as the East Coast Main Line through to London King’s Cross.

The complexity of the underground phase has been unprecedented, thanks to the requirement to strengthen the tunnels that date back to 1846.

By the time the work is completed towards the end of the year, BAM Ritchies – the specialist geotechnical division of BAM Nuttall Ltd – will have installed 4,000 stainless steel masonry stitch bars placed with pinpoint precision, along with masonry repairs, including spray concreting and brick replacement works. In addition, some 600,000 litres of cement grout is being injected into the tunnel linings through nearly 5,000 holes drilled into the Victorian brick linings.

img 2358

The stitch bars are 10mm diameter, up to 850mm long and secured in place by high-strength resin grout in 16mm diameter holes. The void/crack filling grout is 11 N/mm2 cement grout carefully injected so as to ensure no excess pressure on the linings.

All work is undertaken during short night-shift possessions in the north tunnel from midnight till 5am five nights per week and in the south tunnel from 1am to 9.30am for one night a week. Using drilling masts mounted onto road/rail plant, BAM Ritchies mobilises to working areas in the minimum possible time, so as to maximise the productive working time.

Services supporting the tunnel works are provided through access shafts bored directly from the proposed development site down into each tunnel. The shafts also convey grout and concrete, enabling large quantities of material to be placed during the short possession windows. A sophisticated and intricate tunnel monitoring system has been installed by BAM Ritchies to provide real-time data on the effects of the proposed works on the tunnel, both during the enabling and construction works.

img 2292

We at BAM Ritchies are very well experienced in complex rail projects, but every situation is unique, so we’ve had to develop a very specific approach for this work based on the skills and knowledge of our team. There are many constraints to working on this site, but we have made good progress so far thanks to the working relationship that we have with our client and Network Rail.

Current project manager, Gilson Gaston, added: “We are now into the final few months of the project and it is satisfying to see how much has been successfully achieved when one considers the very short shifts that we have been working.”

Gary Walker from Network Rail Asset Protection said: “Clearly our priority is to ensure that the works are carried out safely and with no disruption to rail passengers on this extremely busy section of the network. We have worked closely with Interserve and BAM throughout the design process lasting about 12 months and it is pleasing to see work being carried out as planned.”

img 2232

According to Tim Shepherd, senior project manager with Interserve, it has been an ambitious phase in the Haymarket development that tested the technical nous of the project team. He explained: “The engineering and logistical challenges were immense, working on the Victorian tunnels in the dead of night where access was severely limited. Working on a live site that connects the capital with the rest of the UK has been extremely demanding, but we have worked closely with Network Rail to ensure no disruption to rail services.”

The overall scheme was designed by award winning Richard Murphy Architects and CDA Architects. With extensive piling work above ground well underway, and finishing of underground enabling works, the development is on track for a completion timeframe of 2017 for its phase 1 H5 office building, Premier Inn and StayCity apart-hotel. Work on H5, H2 and H3 will begin in the second quarter of 2016 as scheduled.

Comments

There are no comments. Why not be the first?

Add your comment

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

View all News

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio ... more >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >