Latest Rail News

04.09.15

Farnworth Tunnel work delayed until December

Work to re-bore Farnworth Tunnel – an important enabler of electrification between Manchester and Preston – has been delayed possibly until December, Network Rail has confirmed. 

The rail infrastructure owner said that engineers enlarging the 1834-built Tunnel have come across “exceptionally poor ground conditions” and have run into “large swathes of sand”. 

Network Rail said “rather than a firm material to bore through, sand pours down into the excavated area halting progress”. 

RTM only recently visited the Farnworth Tunnel site alongside the transport secretary after Fillie – the largest tunnel boring machine in the UK – started its journey to build the new 270m railway tunnel. Boring work was even ahead of schedule, and everyone was confident the 5 October completion date would be achieved. 

Martin Frobisher, route managing director for Network Rail, said: “This delay is intensely frustrating for our engineers and, more importantly, for passengers who are set to benefit from more frequent, faster, quieter services once this wider programme of work is complete. 

“We first hit an area of running sand on August 14 when our engineers saw it suddenly pouring from the working face. This has slowed progress and created big voids, the largest of which needed filling with around 35 tonnes of grout. Again on August 27, sand poured into the excavated area and our engineers had to remove 100 tonnes of material by hand. 

“The nature of civil engineering, especially deep below ground, is that you never fully know the exact ground conditions until you start tunnelling or excavating. Taking soil samples acts as a guide but is never 100% accurate because conditions vary greatly with the amount of water present.” 

Network Rail added that more than 1,500 soil samples have been taken, each one eight metres in depth, to try and get as accurate an idea as possible of the ground conditions to be encountered, but such testing “can only ever act as a guide”. 

Engineers are now pumping resin into the ground to firm it up before 9m-wide Fillie bores through it. 

Farnworth tunnel is 276m long and, as at 2 September, 45m had been excavated since tunnelling started on 1 August, leaving a further 231m to go. 

Alex Hynes, managing director for Northern Rail, said: “We are deeply disappointed that work to deliver the Farnworth Tunnel project will now not be completed by October 5, as originally planned. This will have a significant impact on the lives of our daily commuters.” 

Northern Rail and First TransPennine Express services will continue as planned until October 5. The train plan after this date is currently being determined.

Comments

Lutz   05/09/2015 at 14:40

A few negative bonuses across teh business will soon sort out these sort of issues.

Add your comment

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

Most Read

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >