Major works planned for Airdrie-Bathgate rail link

The GBP300 million project to create a new rail link between Airdrie and Bathgate enters its next phase this autumn and winter, with a series of line closures planned to help deliver the new service.

The project, financed by Transport Scotland and delivered by Network Rail, is currently focussed on the eastern end of the new rail link, improving existing infrastructure on the Bathgate branch line between West Lothian and Edinburgh. Work to double track the existing route will require four Sunday closures in September and October plus a 16-day closure in October, during which bus services will replace First ScotRail trains.

The project also requires electrification of the central track through the Mound tunnel to Edinburgh Waverley station. This work will be carried out over a nine day period during the Christmas holidays (25 Dec ’07 to 2 Jan ’08) and will involve a series of timetable adjustments. Replacement bus services and temporary timetables will be publicised in advance by the train operating companies.

Ron McAulay, Network Rail Director, Scotland said:

"The Airdrie-Bathgate Rail Link is the biggest transport project currently being undertaken in Scotland. In order to bring about the social, economic and transport benefits of this project, some temporary disruption to services is unavoidable. We have been working closely with our rail industry partners to ensure that a robust timetable of replacement bus services will be put in place during the work – we are confident that passengers will not face severe disruption.

"The work being undertaken in the Mound tunnel during the Christmas holidays will see the track lowered slightly and over-head lines installed through the middle of the three tunnels.* This work has been carefully planned to take place during the quietest period for the railways in Scotland."

Steve Montgomery, First ScotRail's Operations and Safety Director, said:

"On completion, this project will bring a number of benefits to customers in terms of overall service performance. Whilst they are taking place, we advise passengers to check their journey information which will be available at stations and on our website and to leave a little more time that usual for travelling."

Line closures related to the Airdrie-Bathgate Rail Link take place on the following dates:

Bathgate to Edinburgh - services replaced by buses:

• Sunday 16 September
• Sunday 23 September
• Sunday 30 September
• Sunday 28 October
• Saturday 6 October to Sunday 21 October

Mound Tunnel works (full replacement timetable TBC)

• 25 December 2007 to 2 January 2008

Services affected will include:

• Edinburgh to Glasgow – reduced to half-hourly service
• Fife services – reduced services
• Edinburgh to Dundee/Aberdeen – reduced services

Community forums Community forums have been organised to discuss the current works with the local communities near the line. They will take place on the following dates:

• 10 September, 6pm-7.30pm: Uphall Primary School, Uphall
• 12 September, 6pm-7.30pm: Deans Community High School, Livingston
• 13 September, 6pm-7.30pm: Bathgate academy, Bathgate

Tell us what you think – have your say below, or email us directly at [email protected]

Comments

There are no comments. Why not be the first?

Add your comment

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

Most Read

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >