Latest Rail News

04.04.19

MPs ‘not convinced’ two-year delay and £3bn overspend will be enough as committee slams Crossrail’s ‘disastrous’ governance

MPs have said they are “increasingly alarmed at the continual shortcomings” of Crossrail and the DfT as its nearly £3bn overspend and substantial delays still “may not be enough.”

The Public Accounts Committee (PAC) has slammed Crossrail and the DfT’s lack of accountability over the flagship project and management “characterised by a catalogue of failures,” and said they are “still unable to fully explain how the programme has been allowed to unravel.”

The Crossrail project was due to open in December 2018 and was “supposed to set the standard for delivery of transport programmes around the world.”

But a new revised opening schedule has not yet been agreed, and the MPs said they are “not convinced” that new services will run in 2020 as is currently hoped, “nor that the additional £2.8bn of funding provided will be enough.”

The cost of Crossrail has risen from £14bn to around £17bn after TfL was forced to borrow over £1bn to bail out the project. It was then hit with several substantial delays as well as the resignation of its chair.

The committee’s latest report gives a scathing review of Crossrail Limited’s management of the project, with key warning signs missed or ignored and passengers still in the dark about the root causes of the programme “unravelling so quickly and so disastrously.”

The PAC criticised Crossrail for failing to properly report the progress and risks of the programme, and slammed the DfT’s project management and oversight.

The report stated: “We are becoming increasingly alarmed at the continual shortcomings our work has highlighted in the department’s project management and oversight of the railways and we will continue to look closely at progress with this programme.”

Meg Hillier, the chair of the committee, said: “Passengers were led to believe they would be able use new Crossrail services through central London from the end of last year. Instead, they have been badly let down by significant delays and cost overruns.

“Wishful thinking is no basis for spending public money and there remain serious risks to delivering this programme, with a revised schedule and costings for completing the work still to be agreed.”

She added: “It is unacceptable that Parliament and the public still do not know the root causes of the failures that beset this project. Nor will we accept the department and Crossrail Limited’s description of these serious problems as ‘systems failures.’

“Accountability in the use of public money is of fundamental importance.”

Image credit - Dominic Lipinski

Comments

There are no comments. Why not be the first?

Add your comment

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >