Inbox

21.10.15

GW electrification cost estimates treble since 2012 – could hit £2.8bn

Estimated costs associated with the Great Western electrification programme have nearly doubled since last year and now stand at up to £2.8bn, Network Rail boss, Mark Carne, confirmed today (21 October).

The cost estimate, which stood at around £1.6bn last year – and just £874m when Network Rail’s Strategic Business Plan for CP5 was published in 2012 – now range from £2.5bn to £2.8bn, although this is subject to further scrutiny and review.

Speaking at a Commons Public Accounts Committee inquiry this afternoon, Carne said he was providing a range in order to avoid giving a “frankly spurious accuracy around a single number”, given that Network Rail is only around a third of the way through the programme.

Meg Hillier MP, chair of the committee, denounced it as a “staggering” increase and questioned Network Rail’s confidence about these costs, but Carne assured he was trying to be as transparent as he could.

Carne blamed the cost spikes across the CP5 portfolio, underpinning the material cost changes in the Great Western programme, on three main facts: inadequate planning and scope definition of the project in its earlier phases; poor cost estimation, particularly around electrification projects; and less flexibility in the regulatory regime since the reclassification of Network Rail’s debt onto the public balance sheet.

He added that around 75% of total cost increases in the 2014-19 are associated with electrification programmes – the “lion’s share” of the problem Network Rail has on its hands at present.

Carne admitted that, looking back now, the way in which Network Rail set itself up for the electrification programme was not adequate.

But he said that cost estimation processes, while unsatisfactory, were done at a very early stage of design and scope of works.

Regardless, he fully accepted that the soaring costs were an extremely serious disappointment – albeit did not represent Network Rail’s performance in delivering other projects.

The Office of Rail and Road’s (ORR’s) boss, Richard Price, another witness at the evidence session today, said he stood by the fact that £1.6bn – the original estimate for the Great Western programme – was what it should take to deliver the project efficiently.

But Price said that a number of things had changed since that estimate, including a greater understanding about the conditions in which Network Rail is carrying out works.

However Hillier said that these risks, regardless of slumping productivity levels, should have been predictable by Network Rail, and accused both leaders of “falling asleep on the job” that they are paid to do properly.

Yet Price pointed to the fact that the ORR  had identified a series of risks embedded in the project right at the start of CP5 – and reminded the committee that the regulator had launched a formal investigation in March as to whether Network Rail was doing everything to address these risks.

Last week, the ORR concluded that Network Rail had not done everything it could and found systemic weaknesses in Network Rail’s handling of projects, but only enforced an improvements package as punishment.

Hillier also asked whether the nearly doubling price tag of the Great Western programme posed a risk to other projects, to which Carne responded that further details will be contained in Sir Peter Hendy’s review of CP5.

But he added that “obviously the overall cost of the portfolio of projects increased significantly”, which meant that eventually, something else had to give.

(Image from the committee hearing this afternoon is a screengrab from parliament.tv, Open Parliament Licence)

Comments

Lutz   21/10/2015 at 22:30

Have measures will do no one any good; a good clear-out is called for.

Bpward   23/10/2015 at 13:44

Stop Go Stop Go is not the way forward. Estimates should be based on clear scopes, approved designers and definite Timescales

Electrictrains   23/10/2015 at 16:26

Of course it was 'poor estimatation'. Far easier to blame shortcomings in your technical support function than actually recognise the major and continuing shortcomings in your programme management - and senior management. Because I'm sure that these hugely detailed estimates are just dreamed up in a vacuum.

Chesterfield   24/10/2015 at 21:26

What is obvious but no-one seems willing or able to put honestly on the table is that these jobs were done more cost-effectively in BR days. Estimates will inevitably turn out wrong if, to retain 'political correctness', the wrong yardstick is used. But if going forward with current cost rates, they are so high that no scheme will prove viable, so investment will stall. Its a reminder of the early days of British Railways, when the industry was saddled with enormous costs to meet political objectives, which were subsequently blamed on the rail managers of the day rather than where they really belonged.

Wimg   25/10/2015 at 18:52

"What is obvious but no-one seems willing or able to put honestly on the table is that these jobs were done more cost-effectively in BR days." Roger Ford in Modern Railways last October did , researched and explained in his own very direct fashion; GW electrification is 4 times as expensive as East Coast electrification 25 years ago, and the end is not yet in sight ..

Add your comment

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >
GTR spreads messages of support on Suicide Prevention Day

10/09/2020GTR spreads messages of support on Suicide Prevention Day

As today (10 Sept) mark the annual World Suicide Prevention Day, Govia Thameslink Railway (GTR), have revealed ‘Affirmation Art’ clus... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News