01.03.12
Freight ready
Source: Rail Technology Magazine Feb/March 2012
The GNGE route linking Peterborough and Doncaster via Spalding, Lincoln and Gainsborough is undergoing a largescale upgrade to make it suitable for modern freight containers and relieve pressure on the ECML. RTM found out more from senior sponsor David Anderson of Network Rail.
The current upgrade work on the GNGE route has its genesis in discussions that began almost a decade ago on increasing capacity on the East Coast Main Line between Peterborough and Doncaster. Options included four-tracking the ECML itself and putting in dynamic loops, but the conclusion reached on the best way to provide availability in future timetables for long-distance, high-speed, highvalue passenger trains was to provide an alternative route via the GNGE line.
David Anderson, senior sponsor for the upgrade and responsible for many ECML projects during CP4, told RTM: “That’s the real purpose and real driver for this work; it is, if you like, an ECML business case.
“Having been under-utilised during the late 80s and early 90s, it became the predominant route for traffic, and so consequently there was some less investment on the joint line, the GNGE line. To some degree, what we’re doing is returning that line to the capability where it can fulfil its former role of carrying a great deal of freight – a role it’s fulfilled in the past.
“The track condition isn’t suitable for modern wagons and modern freight trains, so we’re doing a lot of track work to return the track to RA10 traffic. The freight industry has changed: there’s far less aggregate traffic moving around and far more container traffic. So for it to retain its freight crown, we’re doing a lot of work to provide W9 and W10 loading gauge as well, which allows the line to be used as an alternative route for freight ahead of the ECML. That involves a combination of a considerable amount of track work and a considerable amount of bridges work and culvert strengthening, and so on.”
Bridge and track works
Track renewal works contracted to Balfour Beatty have already started, while bridge contracts have also been let. One of the contractors is May Gurney, which won a £6.5m contract to replace 12 rail under-bridges. Design work began in December 2011 and the work will be complete by the end of 2013, the company said.
Anderson explained: “We’ve been undertaking track renewals on the south end of the route – the Werrington/Peterborough area – doing about 750 yards a weekend, although this past weekend we’ve achieved about 950 yards. Our objective now is to try to get up to 1,000 yards per weekend, which we think is possible given the possession availability and also the technology on the route – it’s quite a simple route in terms of signalling and so on. We’ve got generous possessions.”
Network Rail has possessions virtually every weekend until the end of March 2014, except when the route is used occasionally for diverted traffic.
Faster journey times
Freight operators obviously want as short a journey time as possible between Peterborough and Doncaster, and Network Rail has said that the average journey time from the 2009 and 2011 timetables will be maintained for them via the GNGE.
Anderson said: “The really good news is that in providing an alternative route via the GNGE, journey times become not just an average, but they become consistent and repeatable. We’re looking at just over the two-hour mark in either direction for Peterborough to Doncaster, which is obviously repeatable.”
East Midlands Trains and Northern run services currently, and Anderson says that although the line is being upgraded primarily for freight utilisation, “there’s no reason why passenger services couldn’t use the line in the short term”.
He added: “Those passenger services would benefit from the removal of the permanent speed restrictions and they would benefit from a high line speed profile as well.”
A good diversion
The upgrade works also mean the GNGE route will be a much more attractive option as a diversionary route for ECML traffic where necessary, with about 45 minutes cut off the current Peterborough to Doncaster journey time, assuming no stops.
There will also be resignalling work and automation of most of the 141 level crossings on the route.
He said: “In terms of it becoming a diversionary route for the ECML during weekend work- FOR MORE INFORMATION ing and so on, it becomes far more viable.”
Tell us what you think – have your say below, or email us directly at [email protected]