Latest Rail News

05.06.15

Using a 'Lego wall' to avoid a disruptive all-line block

The engineers delivering the Cardiff Area Signalling Renewals Project used an innovative ‘Lego wall’ to provide a solid barrier between open lines and those lines being replaced, avoiding the need for a disruptive all-line block.

The idea came from someone’s “throw-away comment” about Lego, which prompted serious thinking about the concept of a ‘real virtual wall’ and research by Network Rail that proved it was viable.

 6WO3 waits to depart Longdyke with spent ballast whilst operatives wait by the wall

6WO3 waits to depart Longdyke with spent ballast, whilst operatives wait by the wall

RTM asked Network Rail’s Keith Morey (CDM integration manager) and Christian Irwin (senior project manager) to explain the idea and its genesis in more detail, following its successful implementation over the late May bank holiday. They told us:

“The Cardiff Area Signalling Renewals Project (CASR) had a massive task because of a lack of access when installing two new sets of points (9034 A & B) to form a crossover on the main lines and the rest of the 9033 crossover that was installed in Christmas 2014 on the reliefs to connect onto the main lines just outside Cardiff.

“These track works needed to be completed prior to the planned East of Cardiff Signalling commissioning, scheduled for the end of June 15. The railway involved is a four-track stretch of railway but in order to utilise the large Kirow 1,200 crane to install the points and new track panels, an all-line block was needed.

“With Network Rail being the principal contractor for the works, the planning with contractors (along with the safety of operatives) were clearly in the company’s area of responsibility, tied in with the delivery and productivity of the works and the commissioning.

“The project team looked at the amount of RRV works that could be controlled in part by slew restrictors and also by virtual wall technology, but to carry out the work with lines open would need the Kirow to unload, move and slew panels that had a much higher potential to foul the relief lines. Additionally, operatives would need to work around the site and so also needed something that could more easily be used to help keep them safe as though they were working in a full possession.

“It was clear getting an all-line possession wasn’t possible because of the number of trains that were required to run or to re-plan further with the scarce resource at Easter and Christmas would again impact the signalling programme, so to meet the commissioning timescales, an alternative was needed.

“By thinking outside the box, the project team came up with the idea of a real virtual wall, from a throw-away comment about Lego.

“Network Rail as principal contractor then looked at the viability of the idea of a real virtual wall and carried out further research. The project found that it was possible to have large size ‘blocks’ cast and so the possibility of a real virtual wall was born.

“Measurements were calculated and stability tested and all was found to be feasible. The first section was delivered, installed at the depot and tested, passing with flying colours.

“After that it was ‘all systems go’ and the wall was assembled in the 10-foot over the required distance for the stretch of track to be replaced. This was done using RRVs and trailers utilising short midweek night possessions. The installed stretched for approximate half a mile along the route. Gauge clearances were checked and levels tested to monitor for movement but all was sound – the project had the real virtual wall.

“This in turn allowed the CASR team to produce (in collaboration with Balfour Beatty Rail) a plan to deliver a whole crossover and link into the relief within a bank holiday weekend, utilising the two-line closure, the Kirow crane, numerous trains, RRVs with slew locks and dozers within the dig.

“Everything worked perfectly, following the carefully planned programme – everything was excavated to the required depth and within time. With all trains arriving in the right formation and on time, the planning showed its worth, with hand-back achieved 60 minutes early.

 The top of the wall can be seen as the RRV loads wagons with spoil and an ATW service rushes past

The top of the wall can be seen as the RRV loads wagons with spoil and an Arriva Trains Wales service rushes past

“Not only that, but the main services had still been able to run on the reliefs while the mains were being worked on, so the train operators – Arriva, First Great Western and CrossCountry – were happy, along with Freightliner, Colas, GBRF and DB Schenker, who were all able to run freight trains.

 Pouring new ballast on the new crossover

Pouring new ballast on the new crossover

“This solution has saved an all-line possession for 72 hours; it has cut customer disruption and cut congestion in Newport & Cardiff stations. Win-wins for not only the project, but the Route, the TOCs and FOCs, and the travelling public.

“Additionally, the blocks can be disassembled and then used elsewhere for future works to again create a safe environment and access efficiencies. The project is now looking at the possibility of installing block walls near two-line RRAPS so that machines could on- and off- track without needing an all-line block. All from a child’s Lego set.”

c. Richard Scott

The Kirow near the wall

Owen Batham from Elite Precast told RTM: "As the largest manufacturer of interlocking blocks in the UK, Elite Precast were delighted when we were asked to get involved in this exciting and innovative project. We are very proud to have helped to ensure both the safety of the workforce and the completion of the works ahead of schedule. Our high strength 'Lego' blocks have an almost endless range of uses and the vision of the Network Rail engineers in choosing our product means that we are able to add yet another to the list."

RTM's recent update on the wider CASR works can be found here.

(Photos: Keith Morey and Richard Scott)

 

Comments

Daniel   05/06/2015 at 12:39

It would have been interesting to see the cost of half a miles' worth of Lego Blocks, from production cost through to man hours utilised in erecting the boundary... So that we could compare with the cost of an all-line block.

Brian   05/06/2015 at 18:21

Are they going to get Lego men as contractors next?

David Stuart-Smith   06/06/2015 at 05:58

It would be important to have a clear understanding of just what level of impact the block wall could safely resist. It would be undesirable if a heavy bump on the worksite side of the wall resulted in a block toppling onto the in-service lines! It might also be useful to have cast-in lifting points in the top of each block for ease of handling.

Paul   08/06/2015 at 11:24

Lego star wars, Lego Police and now Lego Network rail... whatever next... very clever but simple idea..

Keith   12/06/2015 at 13:59

Daniel - Re your comment the cost was relative to the cost of charges for delays & reworking the programme as well as wall costs David - The blocks did have lifting points built in at manufacture so were easy to handle - the load & impact calcs are relative and were based not only on block strength but condition strength - Elite can assist with these if you need help

Add your comment

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >