15.06.16

NR review could further delay Sheffield to Rotherham tram-train

The Sheffield to Rotherham tram-train pilot scheme could be delayed further because of a Network Rail review, transport minister Andrew Jones MP has confirmed.

In response to a question from MP Greg Mulholland, Jones said that Network Rail had initiated a review of the programme of works needed to adapt the infrastructure between Meadowhall South and Rotherham Parkgate for the tram-train.

The concerns are based on issues with the approval of new bespoke electrification equipment for the pilot project, the UK’s first tram-train.

Jones said that the DfT and South Yorkshire Passenger Transport Executive, who are co-funding the programme, were “clearly disappointed” by more delays in the project.

“The department understands that Network Rail has encountered significant issues with the approval of new bespoke electrification equipment needed to operate the tram train vehicles,” said Jones. “The joint funders are clearly disappointed by this further delay.”

Tram-train was due to start running in 2015, but this was delayed to spring 2016 and then January 2017 after delays due to problems adapting the heavy rail network.

Simon Coulthard, Network Rail’s head of the project, admitted last year that it was facing delays because of traction problems.

Jones said the project should be delivered by “early spring 2017”, but added that “until the outcome of the Network Rail review is known”, no further details could be provided.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Mark_Long   15/06/2016 at 14:17

It is a shame that UK, the place where railway was born and the modern industry has begun, can not even finish a few hundred of meters of railway track on time in the 21st century.

Neil Palmer   16/06/2016 at 03:14

Mark - Exactly ! Total incompetence from the beginning on this Tram-Train project. At this rate HS2 will reach Glasgow & Edinburgh before a single tram-train reaches Rotherham. Everyone involved in the project, from the DfT on down, should hang their heads in shame.

Roger Capel, Sheffield   17/06/2016 at 15:37

In an effort to hide their own limitations, NR have made a complete pig's ear out of this. As I have heard so many times around our city, why the hell didn't they bring in Deutsche Bahn, with a couple of decades tram-train experience, in from the beginning or at least put key staff on plane / train to Karlsruhe? We have our own way of working in the UK. Yeah, and it don't work! Network Fail again!

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >