Rail Industry Focus

15.11.16

Oxford station on track for Marylebone

Source: RTM Oct/Nov 16

Network Rail’s senior programme manager, Jonathan Davies, and its project manager, Rob Mashford, speak to RTM about the ongoing works in and around Oxford station ahead of Chiltern Railways running services on the new Oxford-Marylebone line from December.

Works are progressing well and on time in and around Oxford station, including efforts to build two new bay platforms and a train accommodation building on the site, RTM has been told. 

Network Rail’s senior programme manager, Jonathan Davies, and its project manager, Rob Mashford, told us that the station – which is just one element of a major programme in the Oxford area to modernise the Great Western route – is currently undergoing what the infrastructure owner calls its ‘phase 0’ works.

 These works, needed to allow the new Chiltern service to run directly to London Marylebone by the end of the year, include building two new extended bay platforms, numbered in May as platforms 1 and 2, to accommodate the new and longer electric IEP trains.

“Platform 2 is partially open at the moment, but we’ll have it open for six-car traffic in mid-December,” Davies explained. “We’ve extended the platforms, we’ve put in a new train accommodation building and we’ll demolish the existing one, which is going to allow for longer trains to get into those bay platforms.” 

The accommodation building, which will house operational and catering staff, is a modular structure erected mostly off-site and brought into the station area in cubicles. It was recently bolted together and workers are currently fitting out electrics, air conditioning and other final fixes before staff move into the facility in late October. According to Mashford, the reason behind the re-do is that the new bay platforms will get extended and positioned through where the former accommodation building is.

 These ‘phase 0’ works will eventually culminate in the closure of the Aristotle Lane crossing, a dangerous crossing Davies said was “very high” on Network Rail’s safety index. “We want to get that closed as soon as possible so that we make the line safer for people using it,” he noted. Aristotle Lane Bridge will also soon be closed so engineers can raise the bridge deck to facilitate electrification of the line up to Oxford. 

Phase 1 track and resignalling 

Around the station, work also progresses simultaneously on ‘phase 1’ track and resignalling works, which kicked off in mid-September and are due to finish around summer 2018. 

“We’ve been particularly working north of Oxford at a place called Tackley, where we’ve been doing some works to crossovers,” said Davies. “This is the start of our remodelling and resignalling work over the next couple of years on the Oxford Corridor. We’ve been resignalling from the Heyford area in the north of Oxford all the way down to Didcot, and particularly doing a lot of track remodelling in and around the station.” 

Mashford added that the main track work is from Hinksey, south of the station, through to Wolvercote. “But as part of the scheme we’re also resignalling the whole of the route which is basically from Appleford, in the Didcot area, all the way up to Heyford, which is the boundary with the next route. The whole area gets resignalled onto the new Thames Valley signalling centre.” 

As well as boosting performance by renewing life-expired track, the technology being used in Oxford has been moved “to the 21st century” with the use of axle counters, which Davies and Mashford had previously put in at Reading and saw first-hand the “leap in reliability performance” in the area as a result. 

Station redesign?

Asked about the council-run Oxford station redesign competition, which chose a handful of winning concepts in March this year, Davies and Mashford said that was run “with no real practical remit”. 

“There’s quite a lot of significant funding that needs to be put in place to actually produce the building of any of those architectural concepts,” Davies explained. “And we’re not, certainly from our side, seeing that money being put together.” 

But despite no funding being made available for a redesign, the station won’t be forgotten after works are delivered this December. “There’s further works that we may well do post-2019,” Davies revealed, noting that this could include “an additional platform face at platform 5” as well as improvements to Botley Road Bridge, a major intersection into the station which many local pressure groups consider “dreadful” due to its exceptionally low height.

FOR MORE INFORMATION

W: www.networkrail.co.uk/great-western-route-modernisation/oxford

Tell us what you think – have your say below or email [email protected] 

Comments

Huguenot   15/11/2016 at 11:50

Well, not quite. "... two new extended bay platforms, numbered in May as platforms 1 and 2, to accommodate the new and longer electric IEP trains." Bay platforms 1 & 2 will be for Chiltern (and eventually EWR) services. Whilst a 5-car IEP would fit, IEPs won't be using them.

Add your comment

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

View all News

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio ... more >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >