Latest Rail News

03.04.14

Earthwork improvements ‘unlikely’ to meet modern criteria

Network Rail’s ongoing earthwork improvement programme is “unlikely” to achieve “modern criteria” in the foreseeable future, a new report from the Rail Accident Investigation Branch (RAIB) has revealed.

In response to six landslips which occurred on Network Rail infrastructure between June 2012 and February 2013, RAIB undertook a ‘class investigation’ into earthwork issues related to land neighbouring the railway and to risk management during adverse weather.

RAIB did add that many of Network Rail’s inherited earthworks were constructed with steeper slopes –more susceptible to landslips – than would be achieved with modern design procedures. But it says: “Network Rail’s on-going earthwork improvement programme is unlikely to achieve modern criteria in the foreseeable future.”

However, the independent body found that in some circumstances, key information provided by specialist staff examining earthworks is not considered when the slope management strategy is determined during evaluation.

The report said: “There is a lack of clarity about who should be carrying out visual checks for risks which can develop on neighbouring land between examinations which take place at intervals of up to ten years. The mandated process for collecting information about neighbouring land is, in parts, difficult to implement and not usually followed.”

RAIB stated that technological developments could offer means of improving this data collection, but it did concede that the location and timing of landslips is difficult to predict although they are almost always triggered by relatively high rainfall.

The landslips, which the report focused on, occurred at Loch Treig (near Tulloch) on 28 June 2012, at Falls of Cruachan (on the line to Oban) on 18 July 2012, at Rosyth (near Edinburgh) on 18 July 2012, at St Bees (Cumbria) on 30 August 2012, at Bargoed (South Wales) on 30 January 2013 and at Hatfield Colliery (South Yorkshire) on 11 February 2013.

However, since then, there have been a number of major landslips caused by adverse weather conditions. For instance the weather-beaten line at Dawlish– which saw around 80m of sea wall destroyed by stormy seas and high tides – has been further handicapped by several severe landslips during the engineering improvement works.

As the RAIB investigation was taking place, Network Rail introduced a new process which takes account of ground saturation and (in addition to likelihood) the possible consequence of a landslip.

As a consequence of the accidents under investigation, the RAIB has made five recommendations addressed to Network Rail, relating to improving management of earthwork and drainage risk arising from neighbouring land; considering all information provided by examiners when undertaking evaluations; and enhancing the new adverse weather risk management process.

In response to the report, a Network Rail spokesperson said: “With extreme weather events becoming more and more frequent, a greater focus on these areas is key to our plans over the next five years, with hundreds of millions of pounds set aside specifically for investment and better management of our earthworks and embankments.

“We will take on board RAIB’s recommendations and take any actions deemed necessary.”

Tell us what you think – have your say below or email [email protected]

Comments

Ricp   06/04/2014 at 23:52

We have to accept that the majority of our railway was built over a 50 year period from 1835 to the 1880s, when the majority of our network was complete. Only the Great Central main line followed and a few urban routes to fill the gaps or add capacity, like the Tottenham and Forest Gate section of the Gospel Oak - Barking line. Railways were built by men with shovels an barrows, pulled up inclined planes by a RFV G6N LOnother man or a basic gravity system. Many embankments were made up with ash or some other spoil, these have become waterlogged and unstable. NR is now a State Corporation so the taxpayer will pick up a fair part of the tab.

Add your comment

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >