TfL shelves plans for Tube upgrades as financial woes revealed

Plans to upgrade major parts of London Underground will be put on hold and Crossrail 2 is now in doubt after TfL has disclosed the extent of its financial difficulties.

TfL has published its five-year business plan, revealing that the delayed opening of Crossrail will cost TFL £600m in lost fares.

The financial impact of the delay to the £15.4bn project has been exacerbated by a decline in passenger numbers and government cuts, leading to London’s transport bosses struggling to balance the books.

TfL has said its revenue for the next five years would be £2.1bn lower than forecast in 2016, compounded by the end of a £700m annual government grant.

Due to the financial troubles, the modernisation of signalling on the Piccadilly Line and the rebuilding of Camden Town station will be halted.

TfL has just agreed a £1.4bn bailout with the government for Crossrail, accompanied with a second push-back to its launch date, originally due 9 December, with the Elizabeth Line now not expected until at least 2020.

The rescue deal will see the Greater London Authority borrow up to £1.3m from the DfT and, following a review into the spiralling costs and delays, it’s been revealed that the project is now £2bn over its original budget.

The levy money that will be used to pay for the loan had, until this week, been earmarked from to provide funding for Crossrail 2.

The business plan expects fares to rise in London by more than inflation, and more jobs would also be lost at TfL as it seeks to cut back-office costs by 30% through merging functions and departments.

The transport body says it expects to break even by 2022-23, a year later than planned, due to the delays and lower demand for transport services.

Mike Brown, London’s transport commissioner, said: “This first year without a direct government grant for the day-to-day operating costs of running transport services has coincided with tough external economic conditions that has meant lower overall passenger numbers than previously forecast.

“That financial pressure has been compounded by the extremely disappointing news about the delay to the opening of the Elizabeth Line.”

He added: “A new Crossrail Ltd management team under Mark Wild's leadership is now working to establish a robust, deliverable schedule before committing to an opening date.  “

TfL states that major progress has been made as efficiency targets are ahead of target and the current operating deficit is set to be cut by more than £200m.

It blames a subdued economy for reduced journeys across the country, with Londoners now taking fewer trips per day compared to previous years, but declares that Sadiq Khan’s freeze of TfL fares will help “cushion London from the severity of impacts.”

The mayor of London said: “We are pushing ahead with our ambitious plans to make London a cleaner, safer, healthier city with more affordable and accessible public transport. This is despite an average reduction of £700m per year in TfL's funding from government, and the financial challenges of uncertainty in the economy and the delay to the Crossrail project.”

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

13/06/2019Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

The storm-battered Dawlish rail line could be “moved out to sea” and away from the “hazard” of the cliffs under new plans... more >
TfL awards contract for new DLR fleet to replace 30-year-old trains

12/06/2019TfL awards contract for new DLR fleet to replace 30-year-old trains

TfL has awarded a contract for 43 new trains to replace the oldest rolling stock on the Docklands Light Railway (DLR), with the first scheduled t... more >
Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey’s commercial account director, Anna Delvecchio, for her insight into what the Rail Sector Deal means for the rail industry and its supply chain. Anna started her career as an apprentice at the age o... more >
read more blog posts from 'the sleeper' >

comment

Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >
Malcolm Holmes on new stations for the Black Country

10/06/2019Malcolm Holmes on new stations for the Black Country

Malcolm Holmes, executive director of the West Midlands Rail Executive, described the new stations set to be built for the Black Country region o... more >
The skills bottleneck: Dealing with growing apprenticeship demand

10/06/2019The skills bottleneck: Dealing with growing apprenticeship demand

Richard Turner, head of apprenticeships at Network Rail, details the reasons for growing apprenticeship demand in the rail sector over the coming... more >
A train journey on the Midland Main Line 15 years from now…

10/06/2019A train journey on the Midland Main Line 15 years from now…

Chris Hobson, director of policy and external affairs at the East Midlands Chamber, talks in detail about what travelling through the region will... more >

rail industry focus

View all News

interviews

Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projec... more >