Crossrail

26.02.18

Phasing issues put Crossrail construction £190m over expected cost

Construction costs on the Crossrail programme have come in 20% over the planned costs, amounting to around £190m of extra spending on the year to date.

The difference in cost has been attributed in part to the phasing of certain works, with construction on certain sections of the line completed in periods which were not initially planned.

TfL bosses revealed the issue in the latest board papers for their Finance Committee, which labelled delays at Whitechapel and Farringdon stations as factors which had driven up costs in the last year.

In addition, the capital’s transport body said it had been required to make system-wide changes in design and employ new high-level staff, causing an added rise in expenditure.

But Crossrail officials defended the extra spending, explaining that coming in over cost for this particular year would not push the project past its £14.8bn total budget.

This was confirmed by TfL in its report: “Crossrail construction costs are £190m (20%) ahead of budget, but the Elizabeth Line is still forecast to be delivered within its overall funding.

“Period variances are expected as the budget contains a number of assumptions about the timing and scope of work.”

A spokesperson for Crossrail told RTM that the numbers for expected costs were based on a business plan completed by the company in September 2016.

“The Elizabeth Line is being delivered within its available funding,” they added.

“The TfL finance report refers to Crossrail’s actual expenditure compared to forecast expenditure as estimated in the Crossrail Business Plan. Variances are expected as the business plan contains a number of forecast assumptions dating from September 2016, such as the timing and scope of work to be delivered in 2017-18.”

Both Woolwich and Bond Street stations have also come in behind scheduled opening times, with the £300m Bond Street revamp opening in November last year.

RTM reported in January that the Elizabeth Line could be under some time pressure after electrical testing works scheduled for November had been pushed back due to an explosion.

A voltage transformer meant to connect some of TfL’s equipment with Network Rail’s failed and exploded, meaning the testing – which was necessary to begin energisation on some sections of the line – could not be completed.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Lutz   26/02/2018 at 16:06

Has it not already been confirmed that Crossrail will come in over budget and late?

Noam Bleicher   27/02/2018 at 08:18

Yes it has Lutz. The whole article could be summarised in the sentence 'The project has gone over budget due to late delivery largely caused by a transformer explosion'. Let's bear in mind however that the overspend is a little over 1% of the total project and will have been forgotten in a few months once the service is operating.

Ian Watkins   27/02/2018 at 13:08

That doesn't seem to tie in with this in the article: But Crossrail officials defended the extra spending, explaining that coming in over cost for this particular year would not push the project past its £14.8bn total budget.

Lutz   27/02/2018 at 13:26

@Noam Bleicher:- The impact of the issues around the transformer may be small, but the total cost of the #Crossrail project is now being quoted at near to 50% more than the figure we have been quoted through-out the construction. The figure is adjusted for inflation, but that does not justify the 50% increase. This pertinent because we are now looking at funding for #CR2; That is a GBP 36 bn (GBP 34 bn if you look at non-TfL figures - possibly pending a discussion on cost-cutting) in 2015 currency base. More than half the funding has to come from the #London economy, yet the project has not been fully costed. We have also been seeing a decline in patronage on the national routes and in tube services in contradiction of the current estimates of future demand. So there is a growing risk that London will be burdened with two white elephants were revenues do not meet expectations and costs are much higher than originally claimed they would be.

Lutz   27/02/2018 at 13:33

Ian Watkins:- The budget was GBP 10 bn - the near 50% increase in the figure is not justified by inflation alone. There will be variances in the level of expenditure across a project time-line due tactical adjustments delivery of individual tasks, but we already know that the project will buts it's budget when we have been assured all along that it would not because of adequate financial capacity within the allocated budget.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Network Rail Thameslink programme harnesses innovation with its latest aerial project

22/10/2018Network Rail Thameslink programme harnesses innovation with its latest aerial project

The Thameslink programme at Network Rail’s latest project pledges to drive innovation and make commuters’ lives easier with cutting-e... more >
FCA probe: TfL could be fined for not telling LSE about Crossrail delay

19/10/2018FCA probe: TfL could be fined for not telling LSE about Crossrail delay

The UK’s financial watchdog is considering whether to launch a formal investigation into TfL over its reported failure to tell the London S... more >
Urgent government talks after Dutch company plugs £80m funding hole in Greater Anglia

19/10/2018Urgent government talks after Dutch company plugs £80m funding hole in Greater Anglia

Greater Anglia has received an £80m rescue package led by the Netherlands, leading to reports of urgent talks between the UK and Dutch gove... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

The East Coast franchise report tells us what we already knew: it was a bid set up to fail

18/09/2018The East Coast franchise report tells us what we already knew: it was a bid set up to fail

RTM's Jack Donnelly assesses what the Transport Committee's latest report on the VTEC franchise means for the industry as a whole “Even now, there is no concrete plan, nor timescales, for the interim operator of this franchise. From our inquiry, we cannot be sure, and cannot reassure passengers or public, that the arrangements ... more >
read more blog posts from 'the sleeper' >

comment

Northern Powerhouse Rail: The need for change

18/09/2018Northern Powerhouse Rail: The need for change

Northern Powerhouse Rail (NPR) will be transformational for the north – it will change the way people live, work, and play. It will rebalan... more >
Innovation through people and technology

18/09/2018Innovation through people and technology

Ian Prosser, HM chief inspector of railways and director of railway safety at the ORR, picks out the key industry challenges to focus on based on... more >
Why we all must mind the gap

18/09/2018Why we all must mind the gap

Clair Mowbray, chief executive of the National College for High Speed Rail (NCHSR), explains how we can all ensure the UK’s next generation... more >
3D printing: from virtual to real

11/09/20183D printing: from virtual to real

Like so many other technological advancements, 3D printing has moved from being the stuff of science fiction, through niche industrial applicatio... more >

rail industry focus

View all News

interviews

Going global: an interview with Network Rail’s Leevan Finney

29/08/2018Going global: an interview with Network Rail’s Leevan Finney

RTM’s Jack Donnelly sat down with one of the leading minds behind Network Rail’s most advanced and innovative rail maintenance techno... more >