Editor's Comment

01.11.15

What to do, when to do it

Source: RTM Oct/Nov 2015

The Hendy report had not been published as RTM went to press, though its doubtlessly radical contents were being foreshadowed everywhere.

The grilling given to Mark Carne, Philip Rutnam and Richard Price by the House of Commons Public Accounts Committee (PAC) exposed some frankly frightening escalations in project costs. These were backed up by the Office of Rail and Road’s recent financial and efficiency report for 2014-15, which includes this revealing sentence: “We have only completed Enhancements Cost Adjustment Mechanism reviews on some 50% of the current portfolio, but the efficient funding we have determined already adds up to about 80% of the total assumed in the determination.”

Those figures make clear the scale of the overspend/underestimate, and thus the likely scale of Sir Peter’s enhancements shake-up. Although the Midland Main Line and TransPennine electrification projects have indeed been ‘unpaused’, neither is really a CP5 project any more. Expect to see many other projects slip to CP6 and beyond.

Of course, Hendy is not the only game in town – other reviews into Network Rail are going on concurrently. Some improvements are no doubt necessary, but it would be hard to see the wisdom of embarking on a wide-scale, disruptive restructure or reform of the organisation at this critical point. Far better to do as Anthony Smith recommends on page 6, and give Hendy and the rest of the board some breathing room – so, a few years to turn things around. If more serious changes are required, they should be done during the transition from one control period to another.

The government clearly recognises the value of rail, and the need for capital infrastructure spending. But with increased focus on Network Rail, especially since its significant debts became a public balance sheet issue, more attention from the hawks at the Treasury is inevitable. The rail sector cannot afford to lose the confidence of the government in its ability to deliver upgrades that are good value for money.

Carne, speaking to the hostile MPs at the PAC, made the point that the people lauded for projects like Dawlish and Reading are the same ones being castigated over Great Western electrification’s costs and slipping timescales. It’s not as simple as ‘heads must roll’. Network Rail is capable of great things, and has often achieved them – though its cost estimations have proven not just optimistic but wildly inaccurate for some projects. Far too little attention was paid to issues like access, stakeholder management, ground conditions, standards, integration, and so on. 

Now we must wait for Sir Peter’s conclusions!

Adam Hewitt

Editor

Comments

Lutz   21/11/2015 at 13:00

Nine months should be more than sufficient to establish a program to address the issues, with substantive remedy demonstrable within the first 12 months. Then we can start to look at the break out of units for privatisation.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

The vision of England's Economic Heartland's Strategic Transport Forum

26/03/2019The vision of England's Economic Heartland's Strategic Transport Forum

Dave Hodgson, elected mayor of Bedford Borough Council and chair of England’s Economic Heartland’s Strategic Transport Forum, sets ou... more >
Changing the London skyline with HS2

26/03/2019Changing the London skyline with HS2

Lisa Hogben, HS2 programme delivery manager for area south enabling works, explains how the arrival of HS2’s first tower cranes shows chang... more >
Picking up the pace with high-speed track handovers

26/03/2019Picking up the pace with high-speed track handovers

In 2018 Steve Featherstone, programme director of track at Network Rail, set his team a challenge to secure 100 high-speed track handovers in a y... more >
GTR replaces UK’s oldest electric fleet with new £240m Class 717 trains

26/03/2019GTR replaces UK’s oldest electric fleet with new £240m Class 717 trains

A new £240m fleet of Class 717 trains has been entered into service by Govia Thameslink Railway (GTR) to replace the UK’s oldest elec... more >

comment

Changing the London skyline with HS2

26/03/2019Changing the London skyline with HS2

Lisa Hogben, HS2 programme delivery manager for area south enabling works, explains how the arrival of HS2’s first tower cranes shows chang... more >
Picking up the pace with high-speed track handovers

26/03/2019Picking up the pace with high-speed track handovers

In 2018 Steve Featherstone, programme director of track at Network Rail, set his team a challenge to secure 100 high-speed track handovers in a y... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >
26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >
Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

22/01/2019Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

In the jigsaw puzzle of regional transport decision-making, there must be collaboration and compromise. Midlands Connect media lead James Bovill ... more >

rail industry focus

View all News

'the sleepers' daily blog

The vision of England's Economic Heartland's Strategic Transport Forum

26/03/2019The vision of England's Economic Heartland's Strategic Transport Forum

Dave Hodgson, elected mayor of Bedford Borough Council and chair of England’s Economic Heartland’s Strategic Transport Forum, sets ou... more >
read more blog posts from 'the sleeper' >