HS2

14.09.18

HS2 land purchase costs triple in six years, ‘significant uncertainty’ remains

HS2 Ltd’s acquisition of properties has been criticised for soaring costs and slow payments in the National Audit Office’s (NAO’s) latest report on the scheme.

Only half of advance payments to claimants have been completed within the required three-month period from HS2 Ltd after receiving a claim request, the auditor said, prompting further concerns about the rate of acquisition of land for the £56bn project.

Under the compulsory purchase for Phase 1 – between London and the West Midlands – property owners must receive a payment of 90% of the estimated value of their land within three months of HS2 taking possession.

However, between March 2017 and August 2018 payments have been later than the three months or are forecast to be later in 52 out of 108 cases. For 35 of these, HS2 concluded that the main reason behind the delay is that claimants have not provided the required information in a timely manner.

Estimated costs for HS2 Ltd to buy land and property for Phase 1 have already “increased significantly” since the start of the programme, according to the spending watchdog. In 2012, HS2 Ltd’s estimate of the net cost — cost after resales — to acquire land and property that supported its first baseline cost and delivery plan was £1.1bn. By 2013, around the time the Hybrid Bill was deposited, this had increased to £1.6bn. The most recent estimate in 2017 was £3.3bn — almost triple the original estimate.

Factors behind the spike in costs included “significant additions” to the scope of the programme, such as additional junctions and route changes. “These changes have resulted in an increase in the amount and type of property required, and therefore the cost to acquire the property needed has increased by approximately £175m (2011 prices),” it added.

Despite the growing overhead for land acquisition, the NAO noted that HS2 Ltd expects that costs “will remain within available funding,” although the early stage of the programme means that there remains “significant uncertainty” about what the final costs will be.

“There is potential for further changes to the scope of the programme, and therefore the amount of land required, the number of property owners that will apply for compensation under discretionary schemes is uncertain, and the final settlement value of almost all properties, including some high-value properties, has not yet been decided,” the report found.

“Although HS2 Ltd has made efforts to improve its land and property function since 2015, there is work to be done to support claimants to receive timely compensation where they are due an advance payment.

“While HS2 Ltd’s estimate of the cost of land and property has increased significantly over time, cost estimates, particularly in this sort of major land acquisition programme, are inherently uncertain and subject to change as more information becomes known about both the design and operation of the railway, and the nature of the land and properties required.”

RTM has contacted HS2 Ltd for comment.

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Greater Anglia brings in extra support for busy periods

21/11/2019Greater Anglia brings in extra support for busy periods

Office staff at Greater Anglia are being trained to help customers when stations are busy due to big events or disruption. Customer Action T... more >
Greater Anglia announces delays cut by almost half

21/11/2019Greater Anglia announces delays cut by almost half

Between December 2018 and October 2019, delay minutes for its Class 317 commuter trains, which run through Cambridgeshire, Hertfordshire and Esse... more >
Metrolink contactless payment system hits millionth journey

20/11/2019Metrolink contactless payment system hits millionth journey

Transport for Greater Manchester announced today (20th Nov) that at the weekend Metrolink’s contactless payment system hit the million-jour... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

14/11/2019Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

Rail Technology Magazine’s Matt Roberts explains the significant role data can play within the future development of the rail industry. Standing as a cornerstone of the UK transport network, the rail industry is forever striving to innovate and maximise efficiency in all aspects of its work. Data is just one such way of achievi... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

  • 15/11/2019A workforce which reflects society

    Loraine Martins MBE, Director of Diversity and Inclusion at Network Rail, joins us in the studio for the third episode of our RTM podcast, talking at...
  • 02/11/2019Monica Barbosa: Women In Rail

    Director of business development and communications at Xrail, Monica Barbosa, thinks women are missing out on exciting opportunities because the...
  • 01/11/2019The dangers of fatigues

    Working long hours, poor health, too little sleep, a demanding job and more can all make us tired and affect our mental and physical performance...
View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >