Cardiff resignalling project completion delay to 2017 confirmed

Cardiff Area Signalling Renewal (CASR), originally due for completion this year, has slipped by two years until January 2017, Network Rail has confirmed. 

The scheme to improve rail services on the Cardiff and Valleys network was split into five work phases: Vale of Glamorgan, Valley Lines, Barry, East of Cardiff, and Cardiff Central & West of Cardiff. 

Network Rail has so far been able to commission the first three. It was during the phase 4 works – East of Cardiff – when things started to go awry. Slippages in the delivery of critical path track works in summer 2014 led to significant changes in the future commissioning plan. 

As RTM reported last year, this forced Network Rail to forecast 2017 as a more likely completion date, which has now been confirmed. 

Cardiff Central cable diversion complete 2 edit

In summer 2014, two new junctions were to be created, Moorland Road Junction and Long Dyke Junction, both with ladder crossings. These were intended to reduce the need for trains to reverse at Cardiff West and give more flexibility for the platforms at Cardiff Central. An extensive programme of engineering trains was planned with a temporary virtual quarry established at Cardiff Marshalling sidings. 

But the programme of work quickly fell behind schedule, and the two crossovers are still to be installed. 

Christian Irwin, the senior project manager for CASR, who came on board after the problems at Long Dyke, told RTM: “We failed to deliver the scope of the works we needed to in 2014 and that involved some of the major track works we had to do at Long Dyke. We have now completed another 50% of them and just have the remaining crossovers to complete. 

“Over the late May bank holiday weekend we have got two large crossovers that we need to install over a three-day possession. That is the last piece of major outstanding work we need to do.” 

However, he told us that the problems at Long Dyke have had a major knock-on effect. 

“What that ultimately meant was that we couldn’t commission phase 4 when we planned to in October 2014 and this then meant we couldn’t commission phase 5 in Christmas last year,” said Irwin. “This has ultimately impacted on us because sheer demand for signalling testing resource for the whole of Network Rail across CP5 is phenomenal.” 

Irwin added that when he started on CASR he embarked on a whole re-planning process to find a gap in the Network Rail diary where he could negotiate the access with TOCs and FOCs to give the team a big disruptive possession needed to carry out the works, and get the required resources. 

 Cardiff Central Cables Before 2 edit

This meant phase 4 slipped back by about nine months and, given that the Christmas 2015 resources were already taken by all Network Rail’s other major projects, CASR had to push phase 5 back to Christmas 2016. 

“This was the first available slot of the magnitude we required,” said Irwin. “We can only do phase 5, which includes Cardiff West, over a Christmas/New Year period. That will be taking place for a period of about nine days from Christmas Eve 2016 through to 2 January 2017 – when platform 8 [the new platform at Cardiff Central] will come into operational service.” 

Network Rail’s most recent update on its high-profile projects notes that CASR’s anticipated final cost is £268m – up significantly from the original £220m. 

Irwin said the rise is a consequence of the re-planning. “We’ve declared publicly that there has been an increase of approximately £50m. We expect this to go up a little bit further, but I can’t commit to a price,” he told us – but they are “very nearly” ready to do so. RTM expects to be able to report the final price by July. 

More details and the full interview with Christian Irwin are in the April/May 2015 edition of RTM, which is now available for FREE using the new RTM App, available on iOS and Android. Search ‘RTM Magazine’ in the App Store / Google Play. 

Comments

Lutz   09/05/2015 at 13:48

It is disappointing that the work has been delayed, but the bright spot in this is that it would appear that the right level of hard-nosed program management is in place to complete the delivery to a realistic schedule.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Improvement work begins across three level crossings in Staffordshire

24/02/2020Improvement work begins across three level crossings in Staffordshire

Network Rail improvement work will begin this week on three level crossings in Staffordshire. Engineers will be replacing the older barrier ... more >
£2.5m government funding set to improve CrossCountry

24/02/2020£2.5m government funding set to improve CrossCountry

Announced today (Feb 24th) by the Rail Minister a £2.5m investment is set to benefit passengers across CrossCountry rail services. Fro... more >
Ep 8 Safely shaping a sustainable railway, Martin Frobisher

20/02/2020Ep 8 Safely shaping a sustainable railway, Martin Frobisher

Martin Frobisher, Group director, Safety, Technical & Engineering and Network Rail, joins us in the RTM Podcast room to discuss the renewable... more >
Southend Victoria line disruption following a landslip at Billericay

20/02/2020Southend Victoria line disruption following a landslip at Billericay

Railway tracks on the Southend Victoria line, between Billericay and Wickford, have been damaged following a landslip. Ballast, the stones that h... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

14/11/2019Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

Rail Technology Magazine’s Matt Roberts explains the significant role data can play within the future development of the rail industry. Standing as a cornerstone of the UK transport network, the rail industry is forever striving to innovate and maximise efficiency in all aspects of its work. Data is just one such way of achievi... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News