Subject: Network Rail, ORR and DfT bosses to be ‘held to account’ in CP5 inquiry

In light of the ORR letter to NR dated 6 August 2015, re: Possible breach of condition 1 of NR’s network licence with regard to its delivery of its enhancement programmes.

The letter states that there are 13 identified weaknesses in the way NR delivers its projects, caused by systemic failure.

I have been involved with implementing Systems Engineering – Requirements Management and Systems Integration and can only say that in my experience NR are sending out unclear signals as to the value of implementing a robust Systems Engineering management structure throughout all of its projects. If NR cannot get its act together and ensure that Systems Engineering is mandated then the existing problems will continue.

In my experience, I think that the NR L2 Engineering Management for Projects NR/L2/INI/020009 Issue 6 does not make it clear to PMs and CEMs that it is their responsibility to ensure that the project technical and operational requirements are comprehensively reviewed (front-end definition) to set a robust baseline (Glass Case), and then ensure that the design and installation teams are providing accurate verification and validation evidence throughout the GRIP stages in accordance with BS EN 50126.

Systems Engineering has not just been ‘'dreamed up’ to put increased costs and workload on PM staff, as many think. However, its concepts and potential benefits are still relatively unknown within the rail industry. It stops the 'we always do it this way' attitude by making people think consciously and challenge what they and others are doing.

So, NR; I say that it is time for you to ‘practice what you preach’ by ensuring that Systems Engineering is mandated for all new projects so that proper project costing and scope can be discussed and agreed early on with your contractors to the benefit of all parties.

 

Source: 100Andthirty

Subject: Midland Main Line electrification unpaused

This is good news. It underlines that electrification is a good thing. However, I believe it also underlines the importance of not squeezing very large infrastructure programmes into five year CP settlements. Whilst good for ongoing maintenance and renewal works, five-year plans really don't work with enhancement programmes. These need two things to happen: 1) appropriate programmes for the scale, risk and invasiveness of the programme; and 2) much better programme management and integration between NR Infrastructure Projects, NR ops, TOCs and everyone else contributing to the outputs of the programmes.

 

Source: Jb

Subject: Much-delayed Ordsall Chord legal challenge dismissed by judge

While looking forward to provision of this link, I feel the wrong decision has been taken as Mr Whitby's 'Option 15' appeared much more sympathetic to the existing historic environment.

If and when NR's proposal is built, it will leave a scar on the locality and I believe we and future generations will live to regret not taking more care of this piece of local heritage.

 

Source: Lutz

Subject: Waterloo upgrades ‘vital’ and needed now – London TravelWatch

Perhaps just as important, if not more so, is the work required to improve the reliability and capacity of the signalling system at the top end of the SWML.

There are constantly delays attributed to signalling problems anywhere between Wimbledon and Waterloo, but the planned replacement of the system was scheduled for the early 2020s. Given the lack of skilled resources in this discipline, it is questionable whether NR will be able to keep to this timetable.

Instead, the signalling changes will be a patch-work of infill/modify just as is proposed for this work. What is the likelihood of this upgrade running smoothly, and what will the reliability of the line in the vicinity of Waterloo up to the completion of the signalling renewal? Very unlikely I think.

Comments

Kevin   04/11/2015 at 13:59

I personally would like to see the GRIP process reworked and rationalised. GRIP 1-3 (initialisation, scoping and selection) would become stage A GRIP 4-6 (High Level/ Detailed Design, costing and Implementation) would become Stage B (Testing / Commissioning, Snagging and Handover) would become Stage C. Instead NR is going the other way and splitting the GRIP stages further into GRIP 3A GRIP 3B etc further complicating the processes involved and dragging them out. Its almost as if the more processes they have the more meetings they can hold to discuss them and the more time they can waste.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Firearms officers patrol trains for the first time

26/05/2017Firearms officers patrol trains for the first time

For the first time in rail history, specialist firearms officers will patrol trains across the UK network to ensure that the travelling public ar... more >
Carillion plans job losses as NR renewal cutbacks start to bite

26/05/2017Carillion plans job losses as NR renewal cutbacks start to bite

The RMT has this week vowed to fight “vigorously” against planned cuts to renewals work for Network Rail (NR) being carried out by co... more >
New Merseyrail fleet a platform for future innovations

26/05/2017New Merseyrail fleet a platform for future innovations

David Powell, programme director of rolling stock at Merseytravel, talks about the procurement of the new fleet of metro trains for the Merseyrai... more >
Freight leaders call for immediate infrastructure investment after election

25/05/2017Freight leaders call for immediate infrastructure investment after election

A key organisation representing rail freight in the UK has today urged the main political parties to back up manifesto promises for freight with ... more >

editor's comment

08/05/2017All set for Railtex

As the rail industry prepares for the biggest UK rail show of the year, Railtex 2017, we have produced a specially expanded edition of RTM for you.  Our exclusive show guide, which starts on page 67, provides you with everything you need to know about the things to see, hear and do at the three-day show. A look through our preview pages will give you a good idea of which stands to visit, as well as meetings to set up.  Th... read more >

last word

Collaborative working is the key to the future of rail infrastructure

Collaborative working is the key to the future of rail infrastructure

David Hawkins, operations director at the Institute for Collaborative Working (ICW), on why ISO 44001 is a new evolution in collaborative working. The launch of BS 11000 in 2010 heralded a step change in thinking for the UK rail industry le... more > more last word articles >

interviews

Intertrain: ready for the future

23/02/2017Intertrain: ready for the future

RTM recently attended Intertrain’s ‘Driving for Success’ event in Doncaster, where leaders from major players such as Carillion... more >

the sleeper's daily blog

Opinion poll: HS3 must take priority over Crossrail 2

19/05/2017Opinion poll: HS3 must take priority over Crossrail 2

Fresh from their victories in the metro mayor elections earlier this month, new leaders of Greater Manchester and Liverpool City Region Andy Burnham and Steve Rotheram were quick to make transport a top priority for their cities last week. In a post on Twitter, both called on the government to prioritise plans for an HS3 link connecting t... more >
read more blog posts from 'the sleeper' >

comment

Upskilling our workforce: how we need to think

19/05/2017Upskilling our workforce: how we need to think

Simon Rennie (pictured centre), general manager of the National Training Academy for Rail, on the importance of upskilling the current workforce ... more >
Inclusive design of ticket sales counters

17/05/2017Inclusive design of ticket sales counters

Boaz Yariv, senior architect, and Dr Elizabeth de Mello, senior ergonomics specialist at Network Rail, present the main features of the new inclu... more >
Small stations: simple changes for quick wins

17/05/2017Small stations: simple changes for quick wins

Richard Freeston-Clough of London TravelWatch explains how investing in small stations in the capital can deliver many benefits and also have a p... more >
Why are S&C layouts failing?

17/05/2017Why are S&C layouts failing?

Dr Sin Sin Hsu, programme engineering manager IP Track Development at Network Rail, analyses why switch and crossing (S&C) layouts fail prema... more >

rail industry focus

View all News