Inbox

02.11.15

Inbox – October-November 2015

Source: Martin Young

Subject: Network Rail, ORR and DfT bosses to be ‘held to account’ in CP5 inquiry

In light of the ORR letter to NR dated 6 August 2015, re: Possible breach of condition 1 of NR’s network licence with regard to its delivery of its enhancement programmes.

The letter states that there are 13 identified weaknesses in the way NR delivers its projects, caused by systemic failure.

I have been involved with implementing Systems Engineering – Requirements Management and Systems Integration and can only say that in my experience NR are sending out unclear signals as to the value of implementing a robust Systems Engineering management structure throughout all of its projects. If NR cannot get its act together and ensure that Systems Engineering is mandated then the existing problems will continue.

In my experience, I think that the NR L2 Engineering Management for Projects NR/L2/INI/020009 Issue 6 does not make it clear to PMs and CEMs that it is their responsibility to ensure that the project technical and operational requirements are comprehensively reviewed (front-end definition) to set a robust baseline (Glass Case), and then ensure that the design and installation teams are providing accurate verification and validation evidence throughout the GRIP stages in accordance with BS EN 50126.

Systems Engineering has not just been ‘'dreamed up’ to put increased costs and workload on PM staff, as many think. However, its concepts and potential benefits are still relatively unknown within the rail industry. It stops the 'we always do it this way' attitude by making people think consciously and challenge what they and others are doing.

So, NR; I say that it is time for you to ‘practice what you preach’ by ensuring that Systems Engineering is mandated for all new projects so that proper project costing and scope can be discussed and agreed early on with your contractors to the benefit of all parties.

 

Source: 100Andthirty

Subject: Midland Main Line electrification unpaused

This is good news. It underlines that electrification is a good thing. However, I believe it also underlines the importance of not squeezing very large infrastructure programmes into five year CP settlements. Whilst good for ongoing maintenance and renewal works, five-year plans really don't work with enhancement programmes. These need two things to happen: 1) appropriate programmes for the scale, risk and invasiveness of the programme; and 2) much better programme management and integration between NR Infrastructure Projects, NR ops, TOCs and everyone else contributing to the outputs of the programmes.

 

Source: Jb

Subject: Much-delayed Ordsall Chord legal challenge dismissed by judge

While looking forward to provision of this link, I feel the wrong decision has been taken as Mr Whitby's 'Option 15' appeared much more sympathetic to the existing historic environment.

If and when NR's proposal is built, it will leave a scar on the locality and I believe we and future generations will live to regret not taking more care of this piece of local heritage.

 

Source: Lutz

Subject: Waterloo upgrades ‘vital’ and needed now – London TravelWatch

Perhaps just as important, if not more so, is the work required to improve the reliability and capacity of the signalling system at the top end of the SWML.

There are constantly delays attributed to signalling problems anywhere between Wimbledon and Waterloo, but the planned replacement of the system was scheduled for the early 2020s. Given the lack of skilled resources in this discipline, it is questionable whether NR will be able to keep to this timetable.

Instead, the signalling changes will be a patch-work of infill/modify just as is proposed for this work. What is the likelihood of this upgrade running smoothly, and what will the reliability of the line in the vicinity of Waterloo up to the completion of the signalling renewal? Very unlikely I think.

Comments

Kevin   04/11/2015 at 13:59

I personally would like to see the GRIP process reworked and rationalised. GRIP 1-3 (initialisation, scoping and selection) would become stage A GRIP 4-6 (High Level/ Detailed Design, costing and Implementation) would become Stage B (Testing / Commissioning, Snagging and Handover) would become Stage C. Instead NR is going the other way and splitting the GRIP stages further into GRIP 3A GRIP 3B etc further complicating the processes involved and dragging them out. Its almost as if the more processes they have the more meetings they can hold to discuss them and the more time they can waste.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

22/03/2019Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

A new £208m Belfast Transport Hub with major rail and bus connections has been granted planning permission by the Department of Infrastruct... more >
New to-the-minute measures for train punctuality introduced to tackle delays

22/03/2019New to-the-minute measures for train punctuality introduced to tackle delays

New measures of train punctuality are to be released by train operators and Network Rail next month in a bid to improve performance. The Rai... more >
FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

22/03/2019FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

FirstGroup has finalised a £100m order for Hitachi AT300 electric trainsets in a partnership between the two companies to create a new Lond... more >
Government’s role in new passenger-centric railway ‘will have to change’, says Williams Review lead

21/03/2019Government’s role in new passenger-centric railway ‘will have to change’, says Williams Review lead

The man leading the Williams Rail Review has warned that the government’s role in the UK railways “will have to change” as the ... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >

the sleeper's daily blog

The West Midlands 30-year strategy

19/03/2019The West Midlands 30-year strategy

Malcolm Holmes, executive director of West Midlands Rail Executive (WMRE), outlines the West Midlands Rail Investment Strategy 2018-2047. The West Midlands Rail Executive was formed three years ago to give local authorities a direct influence over the award of the region’s main rail franchise. Working with the Department for Transpo... more >
read more blog posts from 'the sleeper' >

comment

26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >
East West Rail: the next steps

19/03/2019East West Rail: the next steps

In January, five route options for the central section of East West Rail were published as part of a public consultation on the next phase of the... more >
Rail's role in transit-orientated developments

19/03/2019Rail's role in transit-orientated developments

Jonathan Bray, director at the Urban Transport Group (UTG), argues that transit-oriented developments are the future – and that rail has a ... more >

rail industry focus

View all News