McLoughlin explains GWML and TransPennine electrification delays

TransPennine electrification will definitely miss its 2019 completion date and will instead be delivered in the “early 2020s”, according to transport secretary Patrick McLoughlin.

Speaking to the transport select committee, McLoughlin was less specific on Great Western electrification, saying merely that he “hoped” it would be completed on time, and that he would be keeping up the “pressure” on Network Rail and the Office of Rail Regulation to ensure it is.

He said: “There are areas where progress has not been as fast as I would have liked.”

RTM has reported over recent months on delays to TransPennine electrification.

Asked about delays in general to electrification during CP5, McLoughlin said: “Is [electrification] the right mode to go for the future? I believe it is; I don’t think anyone is arguing against electrification. They are big schemes, and some are taking longer than we’d have liked. Some difficulties are being thrown up.”

In terms of the Great Western, he mentioned the fact that the route goes through “several World Heritage sites” and some “very difficult tunnels”, and acknowledged the widely-reported “cost increase” in the project. He noted that the scheme involved 15,000 foundations, 14,000 masts, 1,500 signal upgrades and 50 station improvements.

Permanent secretary at the Department for Transport, Philip Rutnam, refused to be drawn on other schemes that may be delayed, despite repeated questions from transport committee chair Louise Ellman MP. However, he did say that he would “much rather we didn’t face” this level of uncertainty over electrification timings.

pr

He said the slippages in TransPennine electrification were one of the reasons why the Invitation to Tender for the new Northern franchise insisted on 120 new-build diesel (or battery-powered) vehicles, not dependent on electric infrastructure.

Both said that Network Rail has concluded that more upgrades are needed to the TransPennine route to cope with the level of growth in passenger journeys. This, presumably, is a reference to a 12-week study recently completed by Network Rail and handed to the Department for Transport, but which remains so far unpublished.

McLoughlin said: “The upgrade of our transport infrastructure is highly desirable and necessary.”

He said “a lot of areas in the south” have benefited from electrification, but that the north has missed out. He suggested that some of the electrification on the East Coast was done "on the cheap", which is still causing problems today.

He noted that the first electric Liverpool to Manchester Airport train ran last week, as reported by RTM – but what he did not say was that those services, operated by Class 319s cascaded to Northern from Thameslink, were themselves a few months late in starting.

McLoughlin also referred to the cross-party northern electrification taskforce report, which put forward its long-term priorities across three tiers last week. McLoughlin promised that those priorities would be taken into account in the planning for Control Period 6, from 2019-2024.

(Images: Screenshots from Parliamentlive.tv)

Comments

There are no comments. Why not be the first?

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

HS2 publish annual equality, diversity and inclusion report

07/08/2020HS2 publish annual equality, diversity and inclusion report

Today (8 Aug) HS2 Ltd have released their annual report which details their equality, diversity and inclusion (EDI) work. The report also il... more >
Network Rail’s Southern Region completes installation of secure radio channels

07/08/2020Network Rail’s Southern Region completes installation of secure radio channels

A new digitally secure radio system has been successfully rolled out across Network Rail’s Southern region. As their Wessex route join... more >
Network Rail repairs lifeboat ramp during Cumbrian Coast line work

07/08/2020Network Rail repairs lifeboat ramp during Cumbrian Coast line work

Railway engineers have rebuilt a section of public walkway at St. Bees beach which is used to launch lifeboats to rescue those in distress at sea... more >
£195,000 for rail freight trial

06/08/2020£195,000 for rail freight trial

Funding has been allocated by the Scottish Government to Victa Railfreight to carry out a test to transport timber by rail in the North of Scotla... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News