Interviews

16.01.14

London Overground’s five-car extension: ‘A three-year programme delivered in 18 months’

Source: Rail Technology Magazine Dec/Jan 2014

Huw Edwards, head of programme delivery at London Overground, speaks to RTM about its ongoing capacity improvement programme (LOCIP), including the introduction of five-car services and associated upgrades to depots, sidings and signalling across the network.

London Overground is an undisputed success story for the rail industry, showing how good project management, attractive rolling stock and clever branding can unleash huge amounts of latent demand.

But passenger numbers have been growing faster than the service’s ability to cope, necessitating upgrades to ensure it is ready for the future and a growing London, and to try to deal with overcrowding.

In 2007, at the end of the previous Silverlink DfT franchise, passenger numbers stood at around 33 million a year. But in 2013, under London Overground – run as a concession let by TfL to LOROL, a joint venture of MTR and DB/Arriva until 2016 – that figure rose to 135 million.

Huw Edwards, London Overground’s head of programme delivery, told RTM that the growth has been due to suppressed demand, but also regeneration in north-east London especially, such as in Hoxton and Haggerston.

The short to medium term solution is a fleet extension for the Class 378 Capitalstars, from four-car to five, for all London Overground routes except Gospel Oak to Barking (the electrification of which will allow the introduction of higher-capacity trains at a later date).

Edwards called the extension “readily deliverable” – and the £88m order for 57 new carriages was placed with Bombardier in Derby under an option built into the original 2007 rolling stock contract, following approval from the TfL board in February 2013.

But preparing the network for the longer trains has been a bigger job, requiring platform extensions, depot and sidings modifications and signalling works.

Longer platforms

Of the £321m London Overground Capacity Improvement Programme, roughly £174m is capital expenditure on the fixed infrastructure (the rest is the cost of the new rolling stock and alterations to the existing fleet, plus operations and maintenance over ten years).

Platform extension works on the East London Line started at Highbury & Islington, Canonbury and Surrey Quays in December 2013, with another nine due to be extended between February and June 2014. At some stations, a full platform extension to allow ten doors to open has not been possible; Wapping and Rotherhithe will have to remain at eight door opening, with passengers in the back car told to walk to the next doors, while Canada Water will get a compromise nine-door solution. Edwards said: “Canada Water is a very big interchange for us; we want to do as much as we can. We’ve found an affordable solution which takes us to nine door. To go to ten door would be a massive solution involving part-demolition of the bus station and a major civil engineering project. Yes, potentially there is a business case for that – but that solution isn’t deliverable in the timeframe the mayor wants.”

At Whitechapel, selective door opening will apply until Crossrail is complete. Cleshar is the contractor for these works. “When Crossrail concludes at Whitechapel, a set of temporary overbridges and secondary means of escapes will disappear and the platform lengths for the ELL become that much longer,” Edwards said. “That means we will go to five-car door opening in two or three years’ time at Whitechapel.”

Considering that London Overground seems willing to implement selective door opening when necessary, RTM asked Edwards whether TfL ever considered saving money by selecting that option rather than platform extensions at other stations.

He said: “We took the view that we don’t see passenger numbers getting any less, and therefore where it is relatively straightforward to build, we would – and it is, in the majority of areas. In the south east in particular, platform extensions are going in left, right and centre, and many of them are much bigger ours, the 12-car extensions for example. The answer is, yes we did look in the initial stages whether we’d use selective door opening at a larger number of locations, but we made a business decision to deliver 10 doors wherever we feasibly could.”

The North London Line extensions and disused platform reopenings are simpler; 17 of these will take place between February 2014 and February 2015. Dyer and Butler is to undertake these works.

On the West London Line, platforms on the Clapham Junction to Willesden Junction route will be extended by Network Rail under their eight-car works for Southern, by March 2014.

Train storage, maintenance and signalling

Sidings and depot facilities have also had to be altered to cater for the longer trains.

A major part of the project is Silwood Triangle, where 10 trains will be stabled. It was chosen because London Overground already owned the land, and because it is close to the New Cross Gate depot. The site, in north Lewisham, needed full planning consent – but Edwards told us that achieving this was better than plumping for a sub-optimal site just to get around the difficulties associated with the planning process.

Work at the site began in April 2013, and should be finished by April 2014. It includes revisions to track alignment, new track and walkways, infrastructure for the signalling, and new staff welfare buildings, fencing, car parks and access roads.

Edwards said making use of the Silwood site was a “good win” for London Overground, adding: “There was a discussion about utilising Network Rail sidings down towards the Norwood Junction or West Croydon, but we’ve gone for sidings near our central core – it’s a turnout off our infrastructure that London Overground owns and maintains. It’s a piece of scruffy scrub land which was light industry and scrapyards, very much brownfield, which we’ve redeveloped in a big way.”

Cleshar is the contractor for the majority of the works in the Silwood Triangle.

There are also ongoing depot reconfiguration and station works at New Cross Gate, being delivered by Spencer: extension of the train maintenance shed northwards; extension of the wheel lathe/heavy cleaning shed northwards; changes to the interior layout of the sheds to accommodate the longer trains; alterations to the bays used to store and maintain the trains to stable 13 five-carriage trains instead of 21 four-carriage trains; and modifications to other equipment within the depot so the longer trains can be maintained and to allow the trains to be converted from four to five carriages on site. These works will be complete by October 2014.

The headshunt at New Cross Gate station is also being extended.

Separately, the Willesden Junction train maintenance depot is being extended towards the station, and London Overground is also deciding on a new stabling/cleaning facility to accommodate 12 five-car trains in north London.

These works require extensive signalling changes at the depots and stabling facilities, and linewide alterations including the moving of starting signals and stop markers, the relocation of axle counters, and modifications to the Train Protection Warning System (TPWS) and Automatic Warning System (AWS). The signal changes will have a “slight impact” on train timetabling, meaning there will be consequent changes to the Train Describer (TD), Customer Information Screens (CIS) and Automatic Route Facility (ARF).

 WI87506 (resized)

New carriages

The first longer train enters service on the East London Line in late 2014. In total, 29 trains are being extended on the ELL, one a week for just over half a year.

Edwards said: “The insertion of the fifth car will happen at New Cross Gate, unlike when we went from three-car to four-car a few years ago, when it was done at Derby. To reduce outage time, we’re going to take the unit out of operational service for a week, insert the fifth car, fully commission, fully test, and send it back out into operation.”

Of course, all the fixed infrastructure works have to be ready for that first extended train.

London Overground will also need new drivers, because although it’s an extension rather than expansion, Edwards said changing stabling arrangements means changing driver rosters and a need for more drivers.

The main marketing campaign promoting the five-car extension to passengers will begin in summer 2014.

Commenting on the tight timescales of this project, Edwards told us: “When compared to a traditional DfT or Network Rail programme of work, the pace of delivery here is significantly faster. We’ll bring in the first fifth car at the end of 2014, when we didn’t gain board approval to do the work until February 2013. I often say it’s a three-year programme of work delivered in 18 months.”

That means taking risk-based decisions along the way, such as buying the switches and crossings seven months before detailed design was actually completed. “They become a fixed point,” Edwards said, “so we said ‘right, we’ve ordered the S&C, everything has to fit around them’. That’s how London Overground has developed, making risk-based management decisions and design decisions along the journey based on the information known at the time. We’ve been successful in doing that.”

The future

Edwards acknowledged that over a 20- or 30-year timeframe, the five-car extension alone will not be nearly enough to offer the capacity required, although Crossrail will help from 2018.

But the Class 378s can’t be configured to run in six-car formation, so Edwards said the next opportunity for serious capacity improvement after this extension would be at fleet renewal time in the mid-2020s.

Until then, LOROL could run additional train services – going from 16tph on the East London Line core to 18tph, for example. Going beyond that would require ATO (automatic train operation), Edwards suggested, copying the example of the Thameslink core, Crossrail, and London Underground.

He told RTM: “If we stretched and sweated the fleet, we believe we could be running an 18tph service between Shoreditch and New Cross Gate. But the reality is, that’s not where demand is – the demand is south. The demand is for bringing passengers up from the Crystal Palace, West Croydon areas into the central core. So therefore [we are in a] tricky position; that’s where the demand is, that’s where the business case is – unfortunately that’s not where the paths are…so the next discussion to be had with the industry is ‘can we sweat two additional paths south of New Cross Gate’.” 

Comments

Ricp   18/02/2014 at 16:40

This report of the interview is not quite right, or Huw Edwards has got a little confused. The LOROL Stakeholder Group was shown a proposal for two extra trains per hour from Crystal Palace towards New Cross Gate giving 10 tph during each peak, presumably to turn at Dalston. The present timetable unfortunately gives certain routes 5 + 10 minute frequencies, rather than a more even 7+ 8 minutes, which will generate more even loadings per train. The timetable needs tweaking, as there will be extra demand to Canada Water. With the reduction in services to London Bridge during the rebuilding, which presumably will be 4 x 8 or 10 car trains during each peak hour; this is roughly the capacity of the 8 Overground trains per hour. Thus what was a 4, 6 or 8 car train every 10 minutes will in future be the equivalent of a 5 car train every 4 minutes, a very intense service compared with 40 odd years ago when the service was a 4EPB, or 2x 4EPB every 30 minutes. I know, I recall using it!

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

First Class 700 arrives in the UK for testing

31/07/2015First Class 700 arrives in the UK for testing

The first Siemens-built Class 700 Desiro City train for Thameslink has arrived in the UK for testing today (31 July). It arrived in the earl... more >
Nexus criticised for ‘ineffective’ power supply risk management

31/07/2015Nexus criticised for ‘ineffective’ power supply risk management

The Rail Accident Investigation Branch (RAIB) has criticised Nexus and DB Regio Tyne & Wear (DBTW) for “ineffectively” managing r... more >
Abellio to refresh Class 321 trains in £4m upgrade

31/07/2015Abellio to refresh Class 321 trains in £4m upgrade

Abellio Greater Anglia will refurbish 40 of its Class 321 trains as part of a £4m investment in additional service improvements across its ... more >

editor's comment

01/07/2015New Priorities

Is Sir Peter Hendy the right man to get Network Rail’s control period back where it needs to be? It was an open secret that the Department for Transport wanted new blood at the top of Network Rail, and it is hardly a surprise to see a pause in Midland Main Line electrification either – there is only so much money, only so many engineers and only so much plant to get this ‘rolling programme’ of electrification don... read more >

featured articles

View all News

last word

Opening doors into the rail industry

Opening doors into the rail industry

RTM catches up with one of its former business development executives, Jonathan Berry, who is nearly a year into his management graduate scheme with Transport for London. David Stevenson reports.... more > more last word articles >

'the sleepers' daily blog

Electrification issues: Who knew what and when?

31/07/2015Electrification issues: Who knew what and when?

The date for when Network Rail started to see costs for some enhancement and electrification schemes exceed the amounts listed in the budget for CP5 seem to be getting earlier and earlier on a week-by-week basis.  Last week, RTM reported that Mark Carne sent a letter to shadow rail minister Lilian Greenwood MP making it clear that &l... more >
read more blog posts from 'the sleeper' >

Web call out 1

rail industry events

Fifth international rail human factors conference

14 Sep 2015

The Fifth International Rail Human Factors Conference will be held in London on the 14th to 17th September 2015. The conference is the only event...

read more >

ASPECT 2015

15 Sep 2015

ASPECT 2015 is an international conference covering all aspects of railway signalling, control and communications. There has been an excellent re...

read more >

The RBF National Annual Dinner 2015

02 Oct 2015

The RBF are delighted to be hosting once again a night of celebration, entertainment, dancing and fundraising at the Grand Central Hotel in Glasg...

read more >

Elmia Nordic Rail 2015

06 Oct 2015

Nordic Rail is the only dedicated railway exhibition in Scandinavia. It's a fair for companies, organizations and individuals with a professional...

read more >

Dinner at the Roundhouse

15 Oct 2015

Having just celebrated its fourth year, Dinner at the Roundhouse is well-established as the UK rail industry’s favourite networking ev...

read more >
view all events

events calendar

back

July 2015

forward
mon tue wed thu fri sat sun
29 30 1

Next Generation Rail: Knowledge without Borders

01/07/2015 - 03/07/2015

RRUKA, in collaboration with Young Railway Professionals (YRP) and RSSB’s FutureRailway programme, is organising the 3rd edition of the Next Generation Rail Conference.

2

Next Generation Rail: Knowledge without Borders

01/07/2015 - 03/07/2015

RRUKA, in collaboration with Young Railway Professionals (YRP) and RSSB’s FutureRailway programme, is organising the 3rd edition of the Next Generation Rail Conference.

3

Next Generation Rail: Knowledge without Borders

01/07/2015 - 03/07/2015

RRUKA, in collaboration with Young Railway Professionals (YRP) and RSSB’s FutureRailway programme, is organising the 3rd edition of the Next Generation Rail Conference.

4 5
6 7 8

UK Rail Station Regeneration and Development

08/07/2015

Investment in railway stations to improve connectivity can be an economic catalyst for unlocking new jobs, housing, and attracting inward investment. This is all in addition to delivering necessary improvements to meet passengers’ expectations and demand.

9 10 11 12
13 14 15

RailNewcastle Conference 2015

15/07/2015 - 17/07/2015

This rail-focused international conference offers opportunities for Scholars, Bachelor, Master, PhD Students, Early Career Researchers and Professionals involved in rail-related research projects and courses.

16

RailNewcastle Conference 2015

15/07/2015 - 17/07/2015

This rail-focused international conference offers opportunities for Scholars, Bachelor, Master, PhD Students, Early Career Researchers and Professionals involved in rail-related research projects and courses.

17

RailNewcastle Conference 2015

15/07/2015 - 17/07/2015

This rail-focused international conference offers opportunities for Scholars, Bachelor, Master, PhD Students, Early Career Researchers and Professionals involved in rail-related research projects and courses.

18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2
3 4 5 6 7 8 9

comment

Managing fatigue

01/07/2015Managing fatigue

In his second article on fatigue for RTM, Chris Langer, human factors advisor at CIRAS, the Confidential Incident Reporting & Analysis System... more >
Why rail companies may be ignoring the benefits of SMEs

01/07/2015Why rail companies may be ignoring the benefits of SMEs

Suzanne O’Keane, rail and transport community manager at Achilles, examines why rail companies may be reluctant to increase the number of s... more >
Meeting the land referencing challenge of HS2

01/07/2015Meeting the land referencing challenge of HS2

Before the first construction work starts, let alone the first train runs, a phenomenal amount of work is required to ensure the development of a... more >
Are we looking at a new age of elegant, visually appealing rail buildings and trackside structures?

01/07/2015Are we looking at a new age of elegant, visually appealing rail buildings and trackside structures?

The new roof structure at Manchester Victoria station is a fantastic example of what is possible with modern steel manufacturing techniques; it j... more >

rail industry focus

View all News

interviews

World-leading asset management on London Underground

01/07/2015World-leading asset management on London Underground

London Underground is only the second metro in the world to receive the new ISO 55001 accreditation endorsing its asset management systems. RTM h... more >