Metro closure to allow modernisation works

Nexus, which operates the Tyne & Wear Metro, is to close major lines for 27 consecutive days as part of the £385m modernisation programme.13:0

The line between Haymarket, the airport and Four Lane Ends will be closed from August 4-27.

Replacement buses, an airport shuttle and extra Metro services around the coast will provide alternative journeys during the closure. The summer was chosen for this work as it has the lowest number of Metro passengers and falls during the school holidays.

6km of track will be replaced between Jesmond and South Gosforth, with stations to be refurbished and cable routes replaced to Newcastle Airport.

Director general of Nexus, Bernard Garner, said: “August will see one of the biggest and most complex pieces of modernisation work in Metro’s history. I apologise to Metro users who will experience the disruption it will cause.

“The major line closure means there will be no trains on the busiest part of the Metro system for 27 days. We have picked the quietest possible time of the year to do the work, with the schools off and generally fewer passengers using the system during August.

“This is a once in a generation piece of modernisation work which can only be done during an extended closure period. It will mean we can deliver a high quality Metro service for the next 50 years.

“We will ensure there is a fast and reliable replacement bus service running when the line is shut. We advise passengers to plan their journeys in advance before travelling.”

Nexus rail director, Raymond Johnstone, said: “It is vital that we replace the track between Jesmond and South Gosforth. The tracks on this busy stretch of line date back to the late 1960s. To ensure Metro’s reliability for passengers it is essential we replace this ageing part of the network.

“Passengers will notice a smoother ride when the work is done, while the wider modernisation projects add up to a more dependable service.

“The scale of the works we are undertaking means that a 27 day closure is the only realistic option. We will be working around the clock during this period, all the way from Haymarket to Newcastle Airport. The line between Haymarket and South Gosforth will see the bulk of the modernisation work.”

Tell us what you think – have your say below, or email us directly at [email protected]

Comments

There are no comments. Why not be the first?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Sept) on World Electric Veh... more >
Contract awarded by Network Rail to strengthen bridges

09/09/2020Contract awarded by Network Rail to strengthen bridges

Three contracts have been awarded by Network Rail to carry out strengthening work to three railway bridges across the Wessex route in the South o... more >
New electric train fleet revealed for Birmingham’s Cross-City Line

09/09/2020New electric train fleet revealed for Birmingham’s Cross-City Line

The electric train fleet set to transform travel on Birmingham’s Cross-City Line has been revealed to rail passengers in the West Midlands.... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >