DfT refuses to provide extra funding for over-budget Croxley rail link

The Croxley rail link is going over-budget again, but will not receive any additional government funding, the DfT has stated.

The line, which will extend the London Underground’s Metropolitan Line to Watford Junction via Watford High Street, was originally due to be completed by May 2016, but its delivery was postponed to 2019, while delivery costs more than doubled from £116.8m to £284.8m.

TfL took over full responsibility for the project from Hertfordshire County Council, but it was still left short of £2.73m funding, while the council tried to compensate it with the offer of a package of wasteland it had bought for £1. The project was given the formal go-ahead last November once the funding was found.

However, in response to written questions from Bob Blackman, the Conservative MP for Harrow East, Andrew Jones, the transport minister, admitted “the costs of the scheme are currently higher than the agreed budget”. He said the higher costs were because of “prices received from the supply chain”.

Jones added that TfL was “considering how best to deal with” the cost of the scheme, but that it had “agreed to meet” any expenses over the £284.8m budget.

“The department will not be providing any additional funding for the scheme and expects TfL to complete it as agreed,” he concluded.

Jones also revealed that transport secretary Chris Grayling had “re-confirmed the importance that the government attaches to the scheme” at a meeting with London mayor Sadiq Khan on 5 December.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Jimbo   14/12/2016 at 16:13

Diamond Geezer has some interesting observations about this scheme in his blog, and is suggesting it will be cancelled - https://diamondgeezer.blogspot.co.uk/

Lutz   15/12/2016 at 09:17

I remember when the price tag on this scheme was quoted as being GBP 16M. Welcome news; glad to hear that the DfT is holding steady on this. TfL needs to take some of the fluff out of the scheme and then just the job done.

Andrew Gwilt   15/12/2016 at 10:36

Has Hertfordshire council got enough money to carry on with the Croxley Rail Link. Or has TfL or Mr Khan got enough money to resume the rail link to Watford Junction. The Mayor of London Mr Khan could persuade the government (DfT) and the Chancellor to bring in extra money to carry on with the new rail link and it should be completed in mid/late 2019 as planned.

Lutz   16/12/2016 at 22:27

@Andrew Gwilt The project is over budget, so either cost savings must be found from within the scope of the project, or extra costs be covered by TfL (as mentioned in the article); this is not a matter for the DfT to address.

Andrew Gwilt   19/12/2016 at 00:52

@Lutz Suppose you are correct.

Add your comment

rail technology magazine tv

more videos >

latest rail news

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Sept) on World Electric Veh... more >
Contract awarded by Network Rail to strengthen bridges

09/09/2020Contract awarded by Network Rail to strengthen bridges

Three contracts have been awarded by Network Rail to carry out strengthening work to three railway bridges across the Wessex route in the South o... more >
New electric train fleet revealed for Birmingham’s Cross-City Line

09/09/2020New electric train fleet revealed for Birmingham’s Cross-City Line

The electric train fleet set to transform travel on Birmingham’s Cross-City Line has been revealed to rail passengers in the West Midlands.... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across t... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Sept) on World Electric Veh... more >