Rail Industry Focus

01.01.15

Points renewal programme revised at Wimbledon

Source: Rail Technology Magazine Dec/Jan 2015

Work has started on a £7m project to rebuild a crucial railway junction in Wimbledon. Shaun Hodges, Network Rail’s Wessex S&C project manager, discusses the successful early progress and revisions.

The South West Trains-Network Rail Alliance has started work on a £7m programme of track maintenance in the Wimbledon area, designed to improve the reliability and punctuality of trains on this part of the network.

More than 72 South West Trains services per hour pass through Wimbledon at peak times and, as a result, the state of the railway around the station has a critical impact on punctuality across the network. But some of the infrastructure in the area dates back to the 1970s.

Preparatory work for the £7m project – which was 14 months in the making – started in October, finishing with a two-day Christmas closure allowing the team to clear the site ready for work in the new year.

Shaun Hodges, Network Rail’s Wessex S&C project manager, told us that during the Christmas closure there was a great deal of signalling preparation with new location cases, new plug interface location boxes and new cables being run. In addition to this, point motors were laid out ready for the work to begin and the team set the site compound up.

Successful crossover installation

Once this work was complete, the engineering team was ready to take possession of the area west of Wimbledon station where they would begin replacing 12 sets of points.

“The core renewals started on the weekend of 3-4 January, and that is when we broke the track and put the first new crossover in,” said Hodges. “We put a long crossover in place at the west end of the station – point number 756 A/B.

“It all went according to plan, 100% exactly how we wanted it to go and we handed back about half-an-hour early.”

The project, being carried out by Network Rail and contractor Colas Rail, is taking place over six weekends from 3-4 January through to mid-February. But during the weekend possessions, South West Trains cannot call at, or run through, Wimbledon.

Thameslink services, however, will continue to run to Wimbledon from central London via Tooting during the affected weekends, but there will be no services from Wimbledon to Sutton via St Helier.

Asked how the team managed to ensure the initial works ran so smoothly, Hodges said: “We had operational contingencies agreed with the train operators, so we had a detailed plan of every service that could have been affected in the event of an over-run. We also had a mitigation plan in place and a huge bus plan, bigger than any I’ve developed before with my colleagues at South West Trains. We also had construction contingencies throughout the entire weekend to hand it back on time.”

Hodges, who worked on last year’s Southampton S&C renewals project, which included replacing 24 point ends with conventional back drives, added that ‘micro-managing’ was also essential.

“Most of the lessons I learnt from that project, I transferred into Wimbledon,” he said, “which included lots of micro-planning and not leaving anything to chance.

“We looked at everything that could’ve gone wrong. For instance, we had a mitigation plan right down to getting 24-hour chefs in hotels for people who were going back at various times of the day and night.”

Revised programme

Originally the Wimbledon renewals team was tasked with replacing 12 sets of points over the allocated six weekends, but that has now been revised due to ‘restrictions’ being put in place.

Hodges said: “It was going to be 12 units, but it is now going to be eight with a revised plan. We have had some restrictions put on us, for a number of reasons. Initially, we will be doing eight of the 12 points and the other four, hopefully, will be done later in 2015. But this is not dated at the moment.”

Asked what the restrictions were and why they had been imposed, Hodges could not comment.

However, Network Rail recently came under the spotlight after engineering over-runs at King’s Cross and Paddington during the Christmas period left thousands of commuters stranded, and the rail operator facing a potential multi-million pound fine.

Following the problems, Network Rail’s CEO Mark Carne said that the events highlighted the “unacceptable impact on the travelling public when plans go wrong”.

He has also proposed that there should “a broader, industry-wide review, into the timing of our major works programmes” and the “passenger contingency arrangements for such works”.

Next project phase

Hodges told us that work on the revised project will see the engineering team adding “another crossover each weekend for the next three weekends” finishing off with a “very long stressing, tamping and welding week in early February”.

“Then we have a series of about 50-60 midweek nights to finish off all the other stressing and welding and completing the job,” he said.

“At this point we will go under the radar and most people won’t know we’re there because we will be operating in the ‘white period’ between the last train at night and the first train in the morning.”

With regards to the welding works, Hodges noted that the team has approximately 320 welds to put in – as well as having time to stress the layout – before the hot weather arrives. “We want to get that done by the end of March,” he said.

RTM asked why a date had not yet been set for the remaining renewals, Hodges said: “The Wessex programme this year (calendar as opposed to financial) is the busiest that I can remember, and I’ve been doing this 25 years.

“I can’t remember a more intensive S&C renewal programme for Wessex.”

Despite the revision, and once the renewals programme is complete, the team is confident that it will boost reliability and punctuality for passengers travelling through Wimbledon and from many other stations and locations.

“Currently there are a number of quality issues and points failures in the area, all of which will be dealt with under the cover of the track renewal,” said Hodges. “I’m also hopeful that with a fully welded layout our lineside neighbours will notice some benefit in terms of noise pollution, as we’ll be taking out a number of joists, being reduced.”

Tell us what you think – have your say below or email [email protected]

Comments

There are no comments. Why not be the first?

Add your comment

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

View all News

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio ... more >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >