Rail Industry Focus

05.09.16

Taking back flood control

Source: RTM Aug/Sep 16

Network Rail’s commercial scheme sponsor, Joanna Grew, talks to RTM about the recent flood alleviation works carried out at Hinksey.

Over the last 14 years, flooding on the Didcot to Oxford railway line between Hinksey has led to 11 closures and severe disruption to passengers and businesses through the cancellation of services. But this looks all set to change. 

Network Rail has just completed the main work on the £18m Hinksey project, which centred round raising the track height by 400mm and installing two culverts under the railway to allow water to flow from one side to the other. 

The project, which went through a protracted planning application, involved closing the railway for 16 days and saw engineers install 44 culvert sections under the track. 

The civils element of the work took place in the first five days of the closure, said Joanna Grew, Network Rail’s commercial scheme sponsor: “We had to undertake quite a large excavation and then install the flooding material and then the pre-cast concrete units were lifted in by a large crane. 

“The culverts are 3.6m by 1.8m metres, and we have two side by side going across the length of the railway connecting the two watercourses.” 

As well as installing the culverts under the line at the north section, near the Dairy Crest site, the team replaced the deck of Strouds underbridge to the south of Abingdon Road in order to raise the level of the track. 

“We were putting quite a lot of additional ballast under the tracks in order to give us the 650mm increase at its highest point,” said Grew. “We also had to replace all of the S&C in the area: there were nine point ends, and also a track point that needed replacing as well.” 

Kirow Lifting Down Main editFuture-proofed Grew added that the infrastructure owner believes the 11 closures of the past would have been mitigated against with the improvement measures taken. “If we have the most severe flooding we may still find that the area is affected in some circumstances,” she admitted, “but it would be for a much shorter duration and have a much lesser impact on the railway.” 

AECOM were the designers for Network Rail on the scheme, and also did the work related to the project’s flood risk assessment. 

Planning challenges 

One of the project’s challenges, Grew noted, was the planning application process, which saw the company’s plans thoroughly scrutinised by Oxford City Council, the Environmental Agency and the very vocal Oxford Flood Alliance. 

“When we raised the railway we were creating, effectively, a dam across the floodplain, which is why we needed to install the culvert which balances out the water on either side,” she said. “But it is very difficult to not make any changes anywhere, and Oxford City Council was very mindful of any impact it might have on residents. 

“We put a lot of work into the flood risk assessment to be able to satisfy the Environmental Agency and Oxford City Council.” 

She added that the Environmental Agency also had a Flood Alleviation Scheme in the pipeline for Oxford, which needed to be considered in Network Rail’s work. 

“They also have a need to move water from one side of the railway to another to create a channel that allows them to take water around the residential areas,” explained Grew. “We have worked with them very closely. In fact, it was about this time last year we signed an agreement with the Environmental Agency which allowed us to increase the size of the culverts to allow for passive provision of their requirements in the future. 

“We have actually put in bigger culverts than we need, but we will, temporarily, block the ends up with orifice plates which restrict them back down to the size that we need them to be.” 

Other challenges that faced the team included late ecological design changes, which meant undertaking some extra vegetation treatment; checking the site for potential archaeological remains; and coming across a raft of unexpected underground cables. 

“We faced lots of underground cables that we didn’t necessarily know were there,” she said. “In some cases they were found to be redundant, and were removed. Any live cables though needed to be safely moved out of the way. In some cases, we had to erect specific cable support structures in order to lift the cables out of the way so we could work around them.” 

PEM LEMs

Track renewal and remaining work 

After completing the civils aspect of the programme, the track work was handed over to Network Rail’s contractor, Colas Rail, to renew 200m of plain line track. 

“They had to replace quite a lot of plain line track in the whole stretch,” said Grew. “It is an area about 200m long, but there are four tracks in that area. We replaced all of that with brand new track. At the same time we raised it, so there was quite a lot of ballast that went down.” 

Network Rail handed the line back on time, but the team still has some work to complete. 

“We still have to connect the culverts up at either end with the watercourses,” noted Grew. “In the possession, we did all of the area underneath of the railway but we hadn’t ever planned to do the entire stretch – there was just too much to do in that time. 

“The two ends need connecting up, which means installing dams at either end because they connect in to the watercourses, and installing the remaining culverts.” 

This work, she added, would be done before the autumn, but wasn’t reliant on extended possessions.

Tell us what you think – have your say below or email opinion@railtechnologymagazine.com

 

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

View all News

editor's comment

17/01/2017Rising to the digital demand

The countdown is well and truly on for this year’s UK Rail Industry Awards (UKRIA), and the whole RTM team is looking forward to welcoming you to the fourth edition of this event on 9 February.  Held once again at Battersea Evolution, the prestigious awards ceremony promises to be an extraordinary evening, celebrating some of the major achievements of the industry in the last year. You can see the awards shortlist on pages 27-29, and read more details at ukria.com. If... read more >

last word

Making rail fares simpler

Making rail fares simpler

David Sidebottom, passenger director at Transport Focus, explains how a number of initiatives over the next 12 months aim to make rail fares simpler. By the end of 2017, we hope passengers will see fairer and simpler fares.  Two recent initiatives should help achieve this.  One initiative was a response to our four-year cam... more > more last word articles >

interviews

Investing in the future of Scottish Rail

15/11/2016Investing in the future of Scottish Rail

Phil Verster, managing director of ScotRail Alliance, speaks to RTM’s Luana Salles about ... more >

'the sleepers' daily blog

Commuters close to taking government to court over Southern crisis

06/01/2017Commuters close to taking government to court over Southern crisis

A commuter organisation looking to take the DfT to court over its handling of the Southern rail crisis have said that their legal challenge is almost ready. The Association of British Commuters (ABC) hopes to submit its full application calling for a judicial review by the end of this month, after initially raising funds for the challenge... more >
read more blog posts from 'the sleeper' >

comment

Exhibitors prepare for France’s rail technology showcase

20/01/2017Exhibitors prepare for France’s rail technology showcase

Florence Gaidet from Mack Brooks gives RTM an update on what people can expect from SIFER 2017, France’s showcase for railway technology, p... more >
The data-driven railway

20/01/2017The data-driven railway

RTM speaks to James Dean, Network Rail’s director of route asset management (DRAM), LNW, about the work the infrastructure owner is carryin... more >
Achieving efficiency through standards

17/01/2017Achieving efficiency through standards

Vaibhav Puri, head of standards policy at the RSSB, attempts to bust the myths around standards, and argues that they will be vital to the tradin... more >
A digital railway for a modern Britain

17/01/2017A digital railway for a modern Britain

David Waboso CBE, managing director of Group Digital Railway, discusses using digital technology and how we must work together better as an indus... more >