Latest Rail News

28.04.16

Ambiguous Hendy Review puts rolling stock and local plans at risk

A lack of transparency in Sir Peter Hendy’s revised enhancement delivery plan (EDP) has made it harder to plan for the future and could impact the introduction or cascade of rolling stock across the network, it has been claimed.

In a paper presented to the Greater Manchester Combined Authority (GMCA), it was stated that “one of the major shortcomings of the report was the lack of transparency with regards to the underpinning methodology behind the revised dates across the entire rescheduled programme”.

The report authors, Sir Richard Leese, leader of Manchester City Council and GMCA’s rail lead, and Jon Lamonte, CEO of TfGM, added that only having indicative dates, or none at all, make it very challenging for the purposes of planning.

The report authors also criticised Sir Peter’s report for its “ambiguous language” and “non-specific target dates”. RTM recently reported that the Office of Rail and Road (ORR) said that changes to Network Rail’s regulated outputs in its revised England and Wales EDP could have “been clearer”, but were approved to get the industry “back to business as usual”.

Firm dates

Sir Richard and Lamonte added that “firm dates” are essential for the purposes of planning integrated infrastructure schemes, procurement of rolling stock and cascades, and planned access to the railway and other infrastructure for construction.

But they said: “Some EDPs have dates removed from obligations with no indication of timescales to commit development or delivery dates; this raises serious concerns for us and our stakeholders, puts local investment plans at risk and does not promote confidence in the delivery plan.”

The authors welcomed the decision to ‘un-pause’ the TransPennine Upgrade programme, and the fact that no schemes were cancelled altogether. However, they were concerned about some of the delays within the TransPennine programme.

The report states it is understood schemes can slip due to unforeseen events. For instance, the Ordsall Chord project has been subject to a legal challenge. But it adds: “It must be better to give target dates and then identify a clear list of potential project risks that could cause delay, than just simply leave dates out altogether, even if those dates have to have a degree of contingency in them.”

GMCA members were told that the lack of visibility of risks identified and mitigation taken gives “little confidence” that additional delays, or those previous issues, will not be repeated later in the programme.

It was noted that more clarity on the reasons behind the delays and what steps have been taken to address these issues on an individual project basis would greatly assist in understanding the necessity behind delays on some of the critical infrastructure projects in the north west region.

Great Western delays and rolling stock

Concerns were also raised about the continued delay of the Great Western electrification project, which is expected to deliver a major cascade of diesel trains to both Northern and ScotRail to meet planned service and capacity improvements in the future.

Back in January, Sir Peter revealed the revised completion dates of each element of the delayed Great Western Main Line electrification programme, which has seen its costs swell massively.

The GMCA report adds that the introduction of new rolling stock and the cascade of vehicles to other areas of the network are potentially threatened by the widespread slippages in the Hendy Review.

“Extra capacity and faster journey times are desperately needed in the northwest after years of underinvestment, and our passengers have a right to expect all of what they were promised, not projects that have now been revised downwards and delivered late,” said the report authors, adding: “It is particularly unpalatable that the Enhancement Delivery Plan was released on the same day that Arriva Rail North publically agreed firm orders for new electric and diesel units which were predicated upon assumed electrification schemes and rolling stock cascades as specified by DfT in the franchise ITT, which may now no longer be fulfilled as originally planned in the light of Sir Peter’s rephrasing.”

Sir Richard and Lamonte added that it is not clear how the impacts of the Hendy Review were considered in relation to the national franchising programme.

Prior to the publication of  the Hendy Review, the heads of two of Network Rail’s most important suppliers said the “uncertainty” thrown up by the reviews into the company’s capabilities and future must end.

With regards to revised programmes in the north, such as TransPennine electrification, TfGM, as a member of Rail North, said it would very much like to see a full breakdown of the programme with the causation of the delays that have led to the redefined completion dates clearly outlined.

“With a better understanding of how the slippage has happened, we will be better placed to assist in optimising the phasing of the revised programme and managing stakeholder and customer expectations throughout the delivery,” said Lamonte. “We would request much more transparency from Network Rail in this matter.”

It was also suggested that a supplementary annex be appended to the current Hendy Review or the public be sighted on it if such a report already exists within Network Rail.  

The report authors concluded that while it is “undoubtedly positive” that Sir Peter has undertaken his review, the report “does raise concern about the overall ability of the national railway network to fulfil obligations and meet the expectations of our passengers”.

(Image: c. Stefan Rousseau PA)

Comments

Henry Law   29/04/2016 at 21:41

With locomotives and unpowered vehicles in push-pull mode, with backwards compatibility, flexibiliity is maintained.

David   30/04/2016 at 11:25

Multiple Units are far superior and more versatile. Bearing in mind the wasted space and poorer acceleration characteristics of a locomotive.

Chris M   01/05/2016 at 02:31

David, your statement is rather simplistic, It depends on the technical capability of the particular designs and the route characteristics - the class 68 hauled trains run by Chiltern for example leave their 100mph diesel multiple units standing. And the space taken up by a loco doesn't matter unless the terminus tracks are very restricted in length.

Lutz   01/05/2016 at 15:50

The cracks in the plan start to come to light; it has been clear for sometime that the Hendy report was not the end of the story, and that the problems within the NR delivery units are so bad that further revisions will be required until the teams concerned have been made fit to do the job.

Andrew Gwilt   03/05/2016 at 00:29

I think this is about North of England (Northern Powerhouse). Unless its about the whole part of England and also Wales and Scotland.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Rail industry launches new interactive accessibly map for UK rail stations

17/04/2019Rail industry launches new interactive accessibly map for UK rail stations

A new interactive map which lets passengers find out about accessibility at stations has been launched by the Rail Delivery Group (RDG) to help b... more >
Helium balloons causing ‘increasing number of train delays’ at cost of £1m

17/04/2019Helium balloons causing ‘increasing number of train delays’ at cost of £1m

Helium-filled balloons are causing hundreds of train delays at a cost of £1m in taxpayer money every year, Network Rail has revealed. ... more >
Dawlish sea wall gets council planning approval with construction to begin in May

17/04/2019Dawlish sea wall gets council planning approval with construction to begin in May

Plans for an £80m sea wall to protect the Dawlish coastal rail line from extreme weather have been by approved by Teignbridge District Coun... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >
Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

22/01/2019Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

In the jigsaw puzzle of regional transport decision-making, there must be collaboration and compromise. Midlands Connect media lead James Bovill ... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

08/04/2019West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

Malcolm Holmes, Chief Executive of the West Midlands Rail Executive, joins us to discuss the 30-year Rail Investment Strategy, and how he and his... more >
read more blog posts from 'the sleeper' >

comment

Changing the London skyline with HS2

26/03/2019Changing the London skyline with HS2

Lisa Hogben, HS2 programme delivery manager for area south enabling works, explains how the arrival of HS2’s first tower cranes shows chang... more >
Picking up the pace with high-speed track handovers

26/03/2019Picking up the pace with high-speed track handovers

In 2018 Steve Featherstone, programme director of track at Network Rail, set his team a challenge to secure 100 high-speed track handovers in a y... more >
26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >