Latest Rail News

26.07.16

Northern Line Extension ‘remains a high concern’

The Northern Line Extension (NLE) on the London Underground remains at high risk of delay despite improvements, an independent report on Transport for London (TfL) has found.

The £500m contract to design and build the extension was awarded to Ferrovial Agroman Laing O’Rourke (FLO) in 2014, but in the first half of 2015, it became apparent that the NLE was likely to suffer severe delays and go over budget.

These could include building a new ‘station box’ at Battersea Power Station at an additional cost of £240m.

The Independent Investment Programme Advisory Group (IIPAG) carried out an interim review in April 2015 and recommended establishing a project management team with appropriate resources and carrying out a review of what lessons could be learned from the problems with the project.

In its annual report, published ahead of a meeting of the TfL finance and policy committee, IIPAG noted that the project has now reached “a more stable state”.

Site works at Battersea Power Station have commenced and TfL has successfully rescheduled and reconfigured them to minimise their impact on the overall programme.

However, TfL has not yet given IIPAG a copy of a documented plan for the management of its relationship with the station developer, as requested.

It has also carried out a review exercise to establish the cause of the problems, but not the independent review recommended, although IIPAG said there is scope for an independent review in the future.

It says that the review is “essential” for all other TfL projects designed to simulate development as part of the Mayoral Transport Strategy.

The report notes: “The NLE project remains of high concern to IIPAG and IIPAG will continue to seek regular briefings from the sponsor, project director and the project delivery team.”

In response, TfL said its team has regularly briefed IIPAG on the recent developments and “notes that the project remains of high concern to the group. Further briefings will be provided as appropriate”.

More generally, IIPAG said that TfL’s project and programme boards have sometimes failed to establish a sufficiently clear direction for projects and allowed changes in scope without funding them.

It noted that TfL has improved its performance at keeping projects within budget instead of seeking extra funding, but that more progress could be made in this area.

It also found that TfL lacks an overall strategy for the best deployment of non-permanent labour and a good understanding of the total costs of its workforce.

TfL replied that it has been developing a strategic workforce planning capability for the last 18 months, as well as a multi-vendor Engineering Recruitment Framework for the most cost-effective management of skilled non-permanent labour.

The latest edition of RTM features an article on the latest developments with the NEL programme, which includes fitting out two stations and 3km of twin tunnel and their shafts and junctions.

(Image c. Steve from Flickr)

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

 

Comments

Gabriel Oaks   26/07/2016 at 12:27

Surely this isn't the same TfL that wants to take-over Southern based on claims of TOC incapability.......

James Palma   26/07/2016 at 20:05

This is typical TFL. I know i deal with projects there all the time. They are arrogant, dont listen and do what they want, regardless of consequences.

Add your comment

 

related

Rail industry Focus

  • 02/11/2019Monica Barbosa: Women In Rail

    Director of business development and communications at Xrail, Monica Barbosa, thinks women are missing out on exciting opportunities because the lack of gender diversity in the rail industry.
  • 01/11/2019The dangers of fatigues

    Working long hours, poor health, too little sleep, a demanding job and more can all make us tired and affect our mental and physical performance – and when we’re fatigued we make more...
View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

NPR, TRU & Fleetwood Mac

18/10/2019NPR, TRU & Fleetwood Mac

Switch up your playlist with the first #WeAreRTM podcast, gain exclusive insight into the leaders running the rail industry their opinions on recent headlines, visions for the future and meet the personalities behind the job titles. It's no... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

24/06/2019Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

Ahead of his appearance, Malcolm Holmes spoke with Rail Technology Magazine about what key leaders in the industry were doing to improve rail in the Midlands. He said: “It’s very... more >