Heavy delays to new trains forces TfL to bring in temporary replacements on London Overground

Modified electric trains have been launched by TfL on the London Overground as a temporary replacement for the delayed delivery of new Class 710 electric trains.

Earlier this month, the planned rollout of electric trains on the troubled Gospel Oak to Barking line was delayed indefinitely by manufacturer Bombardier – the latest in a long set of delays to trains that were originally due in spring last year.

Now TfL has announced that the London Overground line will, from this week, see a mixed fleet of trains with existing Class 378 trains being modified and drafted in.

The modified electric trains will operate alongside current diesel trains to ensure the line can remain open without the new trains, as well as offering more than double the capacity of the two-car diesel trains.

The London transport body called it an “temporary solution” after the long-awaited new electric Class 710 trains were delayed indefinitely, with Bombardier saying that it still needs to carry out software development and mileage testing before the trains are released for driver training.

Mayor of London and head of TfL Sadiq Khan said it would “continue to press Bombardier to do everything they can to deliver a fully operating train to relieve the uncertainty and disruption to customers,” with Khan adding that he had secured a month’s free travel to compensate passengers once the new trains are introduced.

The trains were supposed to be introduced in spring last year, but were delayed until the summer.

They were then promised in November, with a campaign user group claiming the service has been on a “knife-edge” due delays, cancellations and overcrowding, and TfL has since been unable to provide a date for when the electric trains would come into service.

TfL’s director of rail and sponsored services, Jon Fox, said: “We are very sorry for the continuing delay to the introduction of the new fleet of electric trains on the Gospel Oak to Barking line. We share our customers' frustration and continue to push Bombardier to do everything they can to allow us to bring the new trains into service as soon as possible.

“Given the ongoing delays we are modifying three electric trains normally used elsewhere on the network and will put them into use on the Gospel Oak to Barking line until the new electric trains are here.”

The Gospel Oak to Barking line’s existing diesel trains were due to be released for use elsewhere in the country, but TfL has already extended its lease on the trains twice since last summer due to the delays.

The diesel trains will now be released in March at which point if the new electric trains are still not available then TfL warned that the frequency of services on the line could be heavily reduced as a short-term measure.

A Bombardier spokesperson said: "We understand passengers’ frustration with the delay in the introduction of our new electric trains. We are completing the last few crucial software tests on the new British-built trains, to first enable driver training to commence and then, shortly after, passenger service on the Gospel Oak to Barking line."

Image credit - TfL image - a Class 710 London Overground Train

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Rail industry launches new interactive accessibly map for UK rail stations

17/04/2019Rail industry launches new interactive accessibly map for UK rail stations

A new interactive map which lets passengers find out about accessibility at stations has been launched by the Rail Delivery Group (RDG) to help b... more >
Helium balloons causing ‘increasing number of train delays’ at cost of £1m

17/04/2019Helium balloons causing ‘increasing number of train delays’ at cost of £1m

Helium-filled balloons are causing hundreds of train delays at a cost of £1m in taxpayer money every year, Network Rail has revealed. ... more >
Dawlish sea wall gets council planning approval with construction to begin in May

17/04/2019Dawlish sea wall gets council planning approval with construction to begin in May

Plans for an £80m sea wall to protect the Dawlish coastal rail line from extreme weather have been by approved by Teignbridge District Coun... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

08/04/2019West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

Malcolm Holmes, Chief Executive of the West Midlands Rail Executive, joins us to discuss the 30-year Rail Investment Strategy, and how he and his team are working closely with Midlands Connect to deliver on uplifting capacity and bettering services for people across the region ahead of TCR Midlands 2019. What do your roles as Ex... more >
read more blog posts from 'the sleeper' >

comment

Changing the London skyline with HS2

26/03/2019Changing the London skyline with HS2

Lisa Hogben, HS2 programme delivery manager for area south enabling works, explains how the arrival of HS2’s first tower cranes shows chang... more >
Picking up the pace with high-speed track handovers

26/03/2019Picking up the pace with high-speed track handovers

In 2018 Steve Featherstone, programme director of track at Network Rail, set his team a challenge to secure 100 high-speed track handovers in a y... more >
26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >

rail industry focus

View all News

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >