Chiltern line £76m track and signalling upgrade complete after nine-day closure

The railway line between Banbury, Bicester and Leamington Spa reopened yesterday (8 August) after nine days of closure to allow Network Rail engineers to complete a £76m upgrade to the Chiltern main line’s track and signalling.

Although much of the work had already taken place prior to the closure, workers have now finished replacing the signalling through Banbury with a more reliable system with modern LED signals, set to be controlled from the West Midlands Signalling Centre in Birmingham.

Martin Ball, area director for Network Rail, said: “This work was completed on time and with the least amount of disruption to passengers and is an important part of modernising the railway through the area to provide passengers with a more reliable, better railway.

“Our engineers worked quickly and safely to complete this work on time and on budget and we worked closely with the train operators involved to carefully plan these improvements to cause the least amount of disruption to passengers.”

So far in the project, 14,000m of new rail have been laid, 50,000 tonnes of ballast have been used, and a total of 24 new points, which allow trains to change tracks, have been installed.

In addition to the new track layout and signalling, a fourth platform was built to allow for greater capacity and flexibility at Banbury station. This also provides the needed infrastructure for a new depot south of Banbury, which will provide essential maintenance provision for the Chiltern Railways fleet once it is finished being built.

The work in the region is expected to improve the punctuality and reliability of operators using the Chiltern main line, including CrossCountry and Chiltern Railways.

Dave Penney, Chiltern Railways’ managing director, said the Banbury work was an “essential investment” for the long-term reliability of the area’s railway, and praised its timely delivery.

“Through a modernisation of the signalling system, Chiltern Railways services can remain some of the most punctual in the country,” he added. “The 18-month project is now complete and I would like to thank all of our customers who have shown patience and understanding during the improvements, particularly during the recent nine day line closure between Leamington Spa and Bicester.”

A few minutes down south, works at Hinskey, near Oxford, to reduce flooding incidents are also progressing well, with around £18m being spent to make the railway more resilient. Services between Oxford and Didcot Parkway will be affected until 14 August as a result.

(Top image c. Elliott Brown)

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Peter Hicks   09/08/2016 at 11:10

There's a live, real-time map of the newly resignalled area at http://www.opentraintimes.com/maps/signalling/oxford#T_BNBR

GW   09/08/2016 at 15:57

How can NR say it is a more reliable system? It has only just been installed and until it has been working for some time they won't know - as they have found out in the Swindon area.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

DfT names five winners of fresh £16m stations fund

28/07/2017DfT names five winners of fresh £16m stations fund

The DfT has today announced the successful bidders for a £16m package, part of the second phase of the New Stations Fund, which will serve ... more >
East Midlands Airport offers £2.5m fund to boost station connections

28/07/2017East Midlands Airport offers £2.5m fund to boost station connections

East Midlands Airport has today offered details of a £2.5m deal designed to improve station services as part of the next franchise in the r... more >
Hitachi Class 800s pass digital signalling testing

28/07/2017Hitachi Class 800s pass digital signalling testing

Hitachi’s new fleet of Intercity Express trains have this week passed testing to run the digital technology required by the DfT. The t... more >

editor's comment

03/07/2017Rapid progress needed

As RTM went to press, the National Infrastructure Commission outlined a list of the ‘top 12’ immediate priorities on which ministers must make rapid progress in the next year. Unsurprisingly, major rail schemes, including HS2, Crossrail 2 and HS3, featured highly in the projects that needed speedy development.  Lord Adonis stated that all of these have been agreed in principle, “but require decisive action to get ... read more >

last word

How do tram and rail passengers compare?

How do tram and rail passengers compare?

David Sidebottom, director at Transport Focus, analyses the drivers in performance of passenger satisfaction in tram compared to rail. Results published in our recent Tram Passenger Survey (... more > more last word articles >

'the sleepers' daily blog

Londoners given peek at abandoned Mail Rail Underground line

28/07/2017Londoners given peek at abandoned Mail Rail Underground line

Londoners will soon be able to enjoy a unique rail experience – by riding a train going along the disused Mail Rail line. The 6.5-mile track runs deep under the capital, criss-crossing Tube lines and formerly linking six sorting offices with mainline stations at Liverpool Street and Paddington. At most, the small, electric and drive... more >
read more blog posts from 'the sleeper' >

comment

How can the new government support rail freight?

20/07/2017How can the new government support rail freight?

Following the recent general election, Maggie Simpson, executive director at the Rail Freight Group, considers what action the government can tak... more >
Building a sustainable future for rail services in Wales

20/07/2017Building a sustainable future for rail services in Wales

Geoff Ogden, interim managing director at Transport for Wales (TfW), talks to RTM about how the organisation is putting sustainable development a... more >
A potential benchmark for engineering quality and architectural design

20/07/2017A potential benchmark for engineering quality and architectural design

Victoria Hills, chief executive officer at the Old Oak and Park Royal Development Corporation (OPDC), gives RTM an update on the work to create a... more >
Simple changes for energy efficiency

20/07/2017Simple changes for energy efficiency

Michelle Papayannakos, rail sustainability specialist at the RSSB, argues that improving the way energy is managed should be a high priority for ... more >

rail industry focus

View all News

interviews

A game changer for Wales and Borders

17/07/2017A game changer for Wales and Borders

Andy Thomas, managing director for Network Rail’s Wales route, describes how the infrastructure owner will work more collaboratively than e... more >