Crossrail to open by March 2021 as bosses confirm new timetable

The Elizabeth Line will open by March 2021 at the latest as a new six-month delivery window for the Crossrail’s crisis-hit central section is revealed by the project’s bosses.

The announcement confirms that Crossrail, already heavily delayed and overbudget, will be completed at least two years behind schedule, with the midpoint of the delivery window at the end of 2020.

But the new plan does not include the opening of Bond Street, one of the 10 new stations for the new line, which has been delayed due to “design and delivery challenges.”

Crossrail said in its statement that “many risks and uncertainties remain in the development and testing of the train and signalling systems”, but that following a detailed audit of what has gone wrong so far, the new plan would put the project back on track.

Mark Wild, chief executive, said: “I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. But this plan allows Crossrail Ltd and its contractors to put the project back on track to deliver the Elizabeth Line.

“Crossrail is an immensely complex project and there will be challenges ahead, particularly with the testing of the train and signalling systems, but the Elizabeth Line is going to be incredible for London and really will be worth the wait.”

c610 line wide systems december 2018 315769

Originally due to open in late 2018, the earliest new opening date identified is October 2020, and its bosses say Crossrail’s central section will be delivered by March 2021 at the latest.

Crossrail expects the remaining fit-out and systems installation in the stations and tunnels to be completed in 2019 and for the central section works to be completed within the funding package agreed in December 2018.

London mayor Sadiq Khan described the new timetable as “realistic and deliverable.”

Crossrail said 100,000 interdependent tasks still need to be completed, with the four major tasks remaining, including the building and testing of software to integrate the train operating system with three different signalling systems.

Station systems need to be installed and tested, as well as complete installation of the equipment in the tunnels. When this is done, the trains need to be trialled over thousands of miles on the completed railway to “shake out any problems.”

The central section will open between Paddington and Abbey Wood and link the West End, the City of London, Canary Wharf and southeast London, with initially 12 trains per hour during peak times.

541 c610 line wide systems december 2018 315760

Crossrail Ltd said it was working closely with Costain Skanska Joint Venture to ensure Bond Street opens as early as possible, and full services across the Elizabeth Line from Reading and Heathrow in the west to Abbey Wood and Shenfield in the east will commence.

Tony Meggs, Crossrail chairman, said both the board and leadership team “recognise the seriousness of the challenges we face,” but was pleased with the progress made by the new team to get a grip on the project and pull together a new robust plan.

Caroline Pidgeon, chair of the London Assembly Transport Committee, welcomed the announcement with “cautionary relief,” but with the project pushed back twice already she questioned if the six-month window was just another “hedge-betting exercise.”

“It is also incredibly frustrating that no senior executives will accept any responsibility for the litany of failures that have led to this delay.”

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Record number of passenger journeys as UK rail revenue rises to four-year high

18/06/2019Record number of passenger journeys as UK rail revenue rises to four-year high

Record figures of rail passenger journeys have been recorded in England, Scotland and Wales, according to the most recent quarterly report by the... more >
Rail union Aslef launches 'On Track with Diversity' report at Houses of Parliament

18/06/2019Rail union Aslef launches 'On Track with Diversity' report at Houses of Parliament

Train drivers’ union Aslef launched its On Track with Diversity report at the Houses of Parliament on Monday, as it looks to increase ... more >
Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

13/06/2019Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

The storm-battered Dawlish rail line could be “moved out to sea” and away from the “hazard” of the cliffs under new plans... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey’s commercial account director, Anna Delvecchio, for her insight into what the Rail Sector Deal means for the rail industry and its supply chain. Anna started her career as an apprentice at the age o... more >
read more blog posts from 'the sleeper' >

comment

Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >
Malcolm Holmes on new stations for the Black Country

10/06/2019Malcolm Holmes on new stations for the Black Country

Malcolm Holmes, executive director of the West Midlands Rail Executive, described the new stations set to be built for the Black Country region o... more >
The skills bottleneck: Dealing with growing apprenticeship demand

10/06/2019The skills bottleneck: Dealing with growing apprenticeship demand

Richard Turner, head of apprenticeships at Network Rail, details the reasons for growing apprenticeship demand in the rail sector over the coming... more >
A train journey on the Midland Main Line 15 years from now…

10/06/2019A train journey on the Midland Main Line 15 years from now…

Chris Hobson, director of policy and external affairs at the East Midlands Chamber, talks in detail about what travelling through the region will... more >

rail industry focus

View all News

interviews

Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projec... more >