Comment

06.03.17

Do we have credible costing methods for major projects?

Lord Berkeley, chairman of the Rail Freight Group and member of RTM’s editorial board, questions the methodology of estimating costs on major projects, including Great Western electrification.

For some time I have been strongly critical, not just of Network Rail’s ability to produce realistic costs for projects, but to justify them on the basis of past experience, and to deliver them on time and to budget

This Public Accounts Committee ‘Modernising the Great Western Railway’ report is a good start but I fear not the end for this project, since the outturn cost for Great Western electrification on a like-for-like basis could be over £4 bn. 

There are similar problems with HS2 Phase 1 where, using the Realistic Cost Estimates and data from other projects in a structured way with the Rail Method of Measurement (RMM) written by QS Michael Byng and commissioned by Network Rail, we gave evidence to the HS2 Lords Select Committee that the likely cost of their Euston to Old Oak Common section was over £8bn. This was not challenged by HS2 – as they did not appear to have any credible costs themselves.  

In January, during Committee Stage of the HS2 Bill, I quoted Michael Byng’s Calculation that, using the same RMM suite for the whole of the Phase 1, the cost would be £54bn rather than the £24bn quoted in a Written Answer to me on 21 December 2016. How can the first 8km from Euston, albeit with an expensive station, possibly be one third of the cost of the whole 200km of Phase 1, which also includes expensive tunnels, stations, junctions and viaducts?

So, I conclude that neither Network Rail nor HS2 have a credible methodology of estimating costs of projects; it is extraordinary that they can go ahead with HS2 Phase 1 without any justification or response, based on the RMM Suite and costs from other projects, that their costs will be double their quoted figure. 

Has the Treasury given the DfT a blank cheque for HS2 Phase 1? ‘Similarly, Network Rail must quickly get a grip of their costing methodology by fully and quickly implementing the RMM Suite that they have commissioned.

Lord Berkeley will be writing further on this topic in the April/March edition of RTM.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here

Comments

Lesf   06/03/2017 at 15:41

Clearly we do not have a reliable method of estimating, otherwise projects would not routinely finish up costing vastly more than the estimate. Where projects are completed to budget it's often because the budget was increased to meet the actual cost! The GWML electrification people complained that no-one told them about underground services in the way. On any new project, you find the u/g services and the cost of moving them BEFORE asking the government to commit to £1bn expenditure. Are we to go through it all again with HS2?

Lutz   06/03/2017 at 20:47

It is refresh to hear from someone whom is asking basic questions and coming up with the same doubts as myself. I hope Lord Berkeley pursues his questioning further, and I look forward to hearing more on his opinions.

Chris M   06/03/2017 at 23:38

So, Lord Berkeley continues to make out that all UK rail infrastructure projects are completed late and go over budget. GWML electrification is indeed a fiasco, for multiple reasons which have only started to become public. Lack of prior planning seems to have been a major factor. Yet recently I give you: 1) Reading station rebuilding, with a massive flyover, complete resignalling and several new chords. 2) The Norton Bridge relief scheme (6km of new electrified railway). 3) The Hitchin flyover (3km new electrified railway). All completed on time and on budget weren't they? HS1 wasn't a problem either was it? Crossrail is now 80% complete and appears to be on time and budget (using the same DFT costing methodology as HS2). So will Lord Berkeley prove to be a wise old sage, or a clueless buffoon? We will get an answer in just a few months, when the seven major construction contracts for HS2 phase 1 will be awarded. If Lord B is right about phase 1 costing a whopping £54 billion those contracts will attract no credible bidders - because the maximum value HS2 is willing to pay is based on the costs presented to Parliament with the hybrid bill. I will be watching closely....

Pessimism Bias   07/03/2017 at 13:33

The contracts would need to come in at or below the base estimate, not the one which includes optimism bias. Whether the optimism bias allowance will be reached depends on many things but I have a high expectation that it will be exceeded as the client and the design appears to be incompetent and the contractors will be doing their best to exploit the deficiencies.

Jerry Alderson   07/03/2017 at 16:13

To the list from Chris M, in East Anglia we can add the Ipswich Chord (Bacon Factory Curve), Cambridge island platforms, Peterborough platforms etc. Admittedly the last two were built down to a price: Peterborough's new island platform has no canopies. But...Cambridge North station has leaped from £25m to £50m as soon as Network Rail took charge of it, and very little of that overspend has gone to make it fit for passengers. Small waiting rooms on platforms. Tiny toilets. Only two of 12 carrianges will be next to a canopy. What Network Rail lacks (perhaps its suppliers as well) is consistency.

Peter   08/03/2017 at 12:48

For sure HS2 do not have a methodology, other than to throw everything in to justify the project, such as working time 'saved' by getting there quicker, as we cannot work on the train (??). Take away these spurious things and you begin to get nearer to the true costs.

Oliver   10/03/2017 at 10:30

HS2 clearly does not have a credible costing system as it continues to maintain that it only costs 9% more to build a 400kph line compared to a 200kph line. Heaven help us if it would cost over £50,000 million to build a classic line of a similar length to HS2 based on the current estimate which many commentators think will be far exceeded.

Bill S   04/04/2017 at 22:24

This is a pitch for the RMM and its Author which has some merit however their were many other contributors to the RMM in the entire NR estimating team and over 100 UK companies. The RMM is a good standard but others exist such as the SCC Codes in North America. The main reason for cost overuns are the funding methods. All to often sponsors would argue that the true cost of a project would destroy the business case therefore the low number is used. The second issue is expansion of scope after the original estimate GWML is an excellent example of this in no way does the original scope match the current scope. Estimating has improved and can go further the RMM is a good start however defined scope and change control are required throughout the process. Giving a project a name and value is meaniless without a clear scope definition. This why these projects inflate before taxpayers eyes. My end to this comment is dont blame the Estimator they know the business better than most people in the industry.

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

Alliancing: a step change in performance

26/09/2017Alliancing: a step change in performance

Alan Cox, director of pre-construction at BAM... more >
Investing in rail in the north

22/09/2017Investing in rail in the north

Rob Morris, director of operation at Siemens ... more >

editor's comment

04/09/2017A series of incredible events

There are a couple of announcements I’d like to make in this editor’s comment, which I believe could be very beneficial to many of our readers.  Firstly, the deadline is fast approaching to enter the UK Rail Industry Awards (UKRIA), which will take place on 22 March 2018 at Battersea Evolution in London.  Now in its fifth year, UKRIA continues to bring together the leaders and decision-makers running the rail industry for the sector’s biggest and most... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

'the sleepers' daily blog

Deadline for UKRIA 2018 entries extended by two weeks

26/09/2017Deadline for UKRIA 2018 entries extended by two weeks

UKIRA, the rail industry’s biggest and most prestigious awards event hosted by RTM, has officially extended the deadline for entries by an extra two weeks. Due to unprecedented high levels of demand, the cut-off has been moved from today to 9 October, giving entrants all the extra time they need to sign off on applications and get a... more >
read more blog posts from 'the sleeper' >

interviews

Pushing forward with East West Rail plans

21/09/2017Pushing forward with East West Rail plans

Andy Free, head of engineering assurance at East West Rail (EWR) Alliance, discusses the recent round two public consultation on the plans for th... more >
A game changer for Wales and Borders

17/07/2017A game changer for Wales and Borders

Andy Thomas, managing director for Network Rail’s Wales route, describes how the infrastructure owner will work more collaboratively than e... more >
‘In the rail business, we’re leading the way’

13/07/2017‘In the rail business, we’re leading the way’

Andy Milner, the chief executive of Amey, tells RTM about the transformation programme that has been taking place in the company since his takeov... more >
Expanding an unprecedented level of style and comfort

13/07/2017Expanding an unprecedented level of style and comfort

At the end of May, Eurostar introduced its new e320 train on the London-Brussels route. Rob Haycocks talks to RTM about what passengers can expec... more >