Crossrail to open by March 2021 as bosses confirm new timetable

The Elizabeth Line will open by March 2021 at the latest as a new six-month delivery window for the Crossrail’s crisis-hit central section is revealed by the project’s bosses.

The announcement confirms that Crossrail, already heavily delayed and overbudget, will be completed at least two years behind schedule, with the midpoint of the delivery window at the end of 2020.

But the new plan does not include the opening of Bond Street, one of the 10 new stations for the new line, which has been delayed due to “design and delivery challenges.”

Crossrail said in its statement that “many risks and uncertainties remain in the development and testing of the train and signalling systems”, but that following a detailed audit of what has gone wrong so far, the new plan would put the project back on track.

Mark Wild, chief executive, said: “I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. But this plan allows Crossrail Ltd and its contractors to put the project back on track to deliver the Elizabeth Line.

“Crossrail is an immensely complex project and there will be challenges ahead, particularly with the testing of the train and signalling systems, but the Elizabeth Line is going to be incredible for London and really will be worth the wait.”

c610 line wide systems december 2018 315769

Originally due to open in late 2018, the earliest new opening date identified is October 2020, and its bosses say Crossrail’s central section will be delivered by March 2021 at the latest.

Crossrail expects the remaining fit-out and systems installation in the stations and tunnels to be completed in 2019 and for the central section works to be completed within the funding package agreed in December 2018.

London mayor Sadiq Khan described the new timetable as “realistic and deliverable.”

Crossrail said 100,000 interdependent tasks still need to be completed, with the four major tasks remaining, including the building and testing of software to integrate the train operating system with three different signalling systems.

Station systems need to be installed and tested, as well as complete installation of the equipment in the tunnels. When this is done, the trains need to be trialled over thousands of miles on the completed railway to “shake out any problems.”

The central section will open between Paddington and Abbey Wood and link the West End, the City of London, Canary Wharf and southeast London, with initially 12 trains per hour during peak times.

541 c610 line wide systems december 2018 315760

Crossrail Ltd said it was working closely with Costain Skanska Joint Venture to ensure Bond Street opens as early as possible, and full services across the Elizabeth Line from Reading and Heathrow in the west to Abbey Wood and Shenfield in the east will commence.

Tony Meggs, Crossrail chairman, said both the board and leadership team “recognise the seriousness of the challenges we face,” but was pleased with the progress made by the new team to get a grip on the project and pull together a new robust plan.

Caroline Pidgeon, chair of the London Assembly Transport Committee, welcomed the announcement with “cautionary relief,” but with the project pushed back twice already she questioned if the six-month window was just another “hedge-betting exercise.”

“It is also incredibly frustrating that no senior executives will accept any responsibility for the litany of failures that have led to this delay.”

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Northern leaders warn Treasury against scrapping under-fire HS2

23/05/2019Northern leaders warn Treasury against scrapping under-fire HS2

Scrapping HS2 would be a “disaster” and would undermine Britain’s “national prosperity for decades to come,” more t... more >
Network Rail unveils new regional managing directors

23/05/2019Network Rail unveils new regional managing directors

Network Rail has announced five new regional managing directors as part of its “evolution” towards a more passenger-focused approach.... more >
£800m worth of rail haulage contracts awarded by Network Rail

22/05/2019£800m worth of rail haulage contracts awarded by Network Rail

Network Rail has awarded contracts for rail haulage and the operations of its engineering trains and seasonal treatment services for Control Peri... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Meeting clients, suppliers and stepping forward

23/05/2019Meeting clients, suppliers and stepping forward

The Midlands 30-year plan will deliver many economic benefits and will need a wide and diverse supply chain to deliver some of the key projects. We caught up with long running sponsors of TransCityRail, Bridgeway Consulting Limited, specialists in Site & Ground investigations, Geomatics and Infrastructure, to discuss why networking events ... more >
read more blog posts from 'the sleeper' >

comment

The railway franchising model is broken, and passengers are paying the price

13/05/2019The railway franchising model is broken, and passengers are paying the price

Meg Hillier, MP for Hackney South and Shoreditch and chair of the Public Accounts Committee (PAC), gives her view on the state of the UK’s ... more >
NSAR: Tackling the digital skills shortage

13/05/2019NSAR: Tackling the digital skills shortage

The National Skills Academy for Rail (NSAR) chief executive Neil Robertson returns to write for RTM, this time, to assess the digital skills shor... more >
Delivering cost-effective electrification

13/05/2019Delivering cost-effective electrification

David Clarke, technical director of the Railway Industry Association (RIA), sets out the findings of a new report on how rail electrification can... more >
5G: An opportunity to revolutionise on-train connectivity

13/05/20195G: An opportunity to revolutionise on-train connectivity

Simon Holmes, group head of digital (engineering) at FirstGroup, introduces us to the 5G solution being delivered for the rail sector.  ... more >

rail industry focus

View all News

interviews

Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projec... more >