Crossrail to open by March 2021 as bosses confirm new timetable

The Elizabeth Line will open by March 2021 at the latest as a new six-month delivery window for the Crossrail’s crisis-hit central section is revealed by the project’s bosses.

The announcement confirms that Crossrail, already heavily delayed and overbudget, will be completed at least two years behind schedule, with the midpoint of the delivery window at the end of 2020.

But the new plan does not include the opening of Bond Street, one of the 10 new stations for the new line, which has been delayed due to “design and delivery challenges.”

Crossrail said in its statement that “many risks and uncertainties remain in the development and testing of the train and signalling systems”, but that following a detailed audit of what has gone wrong so far, the new plan would put the project back on track.

Mark Wild, chief executive, said: “I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. But this plan allows Crossrail Ltd and its contractors to put the project back on track to deliver the Elizabeth Line.

“Crossrail is an immensely complex project and there will be challenges ahead, particularly with the testing of the train and signalling systems, but the Elizabeth Line is going to be incredible for London and really will be worth the wait.”

c610 line wide systems december 2018 315769

Originally due to open in late 2018, the earliest new opening date identified is October 2020, and its bosses say Crossrail’s central section will be delivered by March 2021 at the latest.

Crossrail expects the remaining fit-out and systems installation in the stations and tunnels to be completed in 2019 and for the central section works to be completed within the funding package agreed in December 2018.

London mayor Sadiq Khan described the new timetable as “realistic and deliverable.”

Crossrail said 100,000 interdependent tasks still need to be completed, with the four major tasks remaining, including the building and testing of software to integrate the train operating system with three different signalling systems.

Station systems need to be installed and tested, as well as complete installation of the equipment in the tunnels. When this is done, the trains need to be trialled over thousands of miles on the completed railway to “shake out any problems.”

The central section will open between Paddington and Abbey Wood and link the West End, the City of London, Canary Wharf and southeast London, with initially 12 trains per hour during peak times.

541 c610 line wide systems december 2018 315760

Crossrail Ltd said it was working closely with Costain Skanska Joint Venture to ensure Bond Street opens as early as possible, and full services across the Elizabeth Line from Reading and Heathrow in the west to Abbey Wood and Shenfield in the east will commence.

Tony Meggs, Crossrail chairman, said both the board and leadership team “recognise the seriousness of the challenges we face,” but was pleased with the progress made by the new team to get a grip on the project and pull together a new robust plan.

Caroline Pidgeon, chair of the London Assembly Transport Committee, welcomed the announcement with “cautionary relief,” but with the project pushed back twice already she questioned if the six-month window was just another “hedge-betting exercise.”

“It is also incredibly frustrating that no senior executives will accept any responsibility for the litany of failures that have led to this delay.”

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Government announces HS2 review, 'go or no-go' decision by year-end

21/08/2019Government announces HS2 review, 'go or no-go' decision by year-end

The government is set to launch a review into the HS2 project, transport secretary Grant Shapps has announced. The review into the high-spee... more >
New train station part of £218m Chelmsford regeneration

20/08/2019New train station part of £218m Chelmsford regeneration

As part of a major £218m regeneration of Chelmsford, a new train station is set to be constructed to improve transport infrastructure in th... more >
Mid-Cheshire Line speed increase after £800k rail upgrade

19/08/2019Mid-Cheshire Line speed increase after £800k rail upgrade

Following the completion of an £800,000 investment into new railway tracks, passenger trains operating on the Mid-Cheshire Line betwee... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Network Rail’s Anna-Jane Hunter on, NPR, TRU, HS2 and supply chain opportunities

12/08/2019Network Rail’s Anna-Jane Hunter on, NPR, TRU, HS2 and supply chain opportunities

Anna- Jane Hunter, is a ‘proud northerner’ and is passionate about continuing the investment and success story of rail across the North.  She plays a key role in working with government and northern leaders to enable the network to carry on thriving. We caught up with Anna... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Government announces HS2 review, 'go or no-go' decision by year-end

21/08/2019Government announces HS2 review, 'go or no-go' decision by year-end

The government is set to launch a review into the HS2 project, transport secretary Grant Shapps has announced. The review into the high-spee... more >