Rail Industry Focus

21.03.17

Bond Street: The importance of clear and consistent stakeholder communication

Source: RTM Feb/Mar 17

Chris Pateman, Crossrail’s Bond Street project manager, and Simon Bennett, head of Learning Legacy at Crossrail, discuss the value of strong stakeholder engagement while constructing a station in the heart of Mayfair.

When Crossrail’s Bond Street station opens in 2018 it will improve accessibility and capacity in one of the capital’s busiest shopping districts. It will also boast two new street-level ticket halls: one at Davies Street and the other at Hanover Square. 

Construction at the site, which sits in the heart of Mayfair, started back in 2010, and since then the team has led a programme of utility diversions works, as well as the demolition of buildings above each of the ticket hall sites, and construction work on the 250m-long platforms has taken place. 

Chris Pateman, Crossrail’s Bond Street project manager, who has worked on the scheme for the last seven years, said that while the engineering of the project came with its challenges, “the big issues, when we took control of the site, was we had to convey a message to local businesses and residents that a major infrastructure project was taking place on their doorstep without causing a detriment to their living standards or financial income”. 

One of the main successes on this major project, he added, has been how the team has managed the stakeholders and construction activities in a confined area. 

“The surroundings of each ticket hall, for example, are different,” said Pateman. “On the east, Hannover Square, we have a lot of business operations around our site – banks, nightclubs –  and on the western ticket hall it is more high-value residential properties. We also have a shopping centre.” 

Having a clear and common message has been key to the Bond Street works, with the team consistently holding three-monthly Community Forum meetings with local residents and businesses since the start of the scheme. 

“Initially, we used to get over 170 attending, but after 18 months this reduced to 20-25. This happened by virtue of the initial concerns being realised by the team,” explained Pateman. “In the forums, to keep and maintain the trust of our neighbours, we had to do what we said we would. We explain the works we have done in the last few months, and what will be done in the upcoming months.” 

An example of where good stakeholder engagement was crucial, Pateman told us, was in November 2015, when the team had to construct a large ventilation shaft on the western ticket hall. 

“The most efficient form of construction to build that was slip-form construction, so continuous moving shutters. We consulted with the residents and explained that this would be a 24-hour activity, and in this case we offered temporary rehousing. In total, 68 families took us up on that, works were completed in an 18-day period and regular communication was delivered to the families. Ultimately, the shaft got completed, and the residents deemed the rehousing a success.” 

The basic fundamental, he added, is building trust with your stakeholders, and “doing what you say you will do”. 

Simon Bennett, head of Legacy Learning at Crossrail, told us that while good stakeholder engagement is nothing new, Crossrail will be sharing how the local teams went about delivering this vital component of the works. 

“It can always improve as you go on,” he reflected. “I think what we are passing on is the lessons about ‘how’ you do it. Projects like Crossrail, which are authorised by Acts of Parliament, will go through that process and end up with something like our Environmental Minimum Requirements, one of which is the Crossrail Construction Code. This is something that was consulted with the local authorities while we were in Parliament, and indeed before, which is what mandates us to require our contractors to employ a specific community relations representative, i.e. to put resource into this.” 

Prior to the project’s completion next year, the Bond Street team is currently carrying out civil engineering activities, and it is also starting to install the first phase of electrical and mechanical works. 

A key date for the scheme this year, noted Bennett, is the handing over of the central section tunnels for dynamic testing in November. “But while dynamic testing is going on, we will be completing stations where there aren’t trains running,” he explained, adding that completion is due for August 2018, providing access for training before Crossrail services start using the new station.

The Learning Legacy work can be accessed at:

W: learninglegacy.crossrail.co.uk

Tell us what you think – have your say below or email opinion@railtechnologymagazine.com 

Comments

There are no comments. Why not be the first?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

View all News

rail industry focus

View all News

editor's comment

03/07/2017Rapid progress needed

As RTM went to press, the National Infrastructure Commission outlined a list of the ‘top 12’ immediate priorities on which ministers must make rapid progress in the next year. Unsurprisingly, major rail schemes, including HS2, Crossrail 2 and HS3, featured highly in the projects that needed speedy development.  Lord Adonis stated that all of these have been agreed in principle, “but require decisive action to get them moving in the new Parliament. They ought to... read more >

last word

How do tram and rail passengers compare?

How do tram and rail passengers compare?

David Sidebottom, director at Transport Focus, analyses the drivers in performance of passenger satisfaction in tram compared to rail. Results published in our recent Tram Passenger Survey (TPS) have seen remarkable levels of satisfaction by the six operators we covered in Blackpool, Birmingham, Edinburgh, Manchester, Nottingham and Sheff... more > more last word articles >

interviews

A game changer for Wales and Borders

17/07/2017A game changer for Wales and Borders

Andy Thomas, managing director for Network Rail’s Wales route, describes how the infrastr... more >

'the sleepers' daily blog

Was the HS2 route decision for Sheffield correct?

21/07/2017Was the HS2 route decision for Sheffield correct?

This week has been a busy one for HS2. A number of important announcements were made by Chris Grayling, who will surely be glad to head off on holiday for some rest and relaxation as Parliament heads into its summer recess. Major details of £6.6bn worth of construction contracts were announced, as well as a pair of shortlists for HS... more >
read more blog posts from 'the sleeper' >

comment

How can the new government support rail freight?

20/07/2017How can the new government support rail freight?

Following the recent general election, Maggie Simpson, executive director at the Rail Freight Group, considers what action the government can tak... more >
Building a sustainable future for rail services in Wales

20/07/2017Building a sustainable future for rail services in Wales

Geoff Ogden, interim managing director at Transport for Wales (TfW), talks to RTM about how the organisation is putting sustainable development a... more >
A potential benchmark for engineering quality and architectural design

20/07/2017A potential benchmark for engineering quality and architectural design

Victoria Hills, chief executive officer at the Old Oak and Park Royal Development Corporation (OPDC), gives RTM an update on the work to create a... more >
Simple changes for energy efficiency

20/07/2017Simple changes for energy efficiency

Michelle Papayannakos, rail sustainability specialist at the RSSB, argues that improving the way energy is managed should be a high priority for ... more >