Glasgow Queen Street tunnel to open one day earlier than planned

Work at Glasgow Queen Street has been successfully completed, with the tunnel due to open one day ahead of schedule.

The high level station closed on 20 March in order to allow Network Rail engineers to reinstall more than 4,000m of new track.

Engineers finished laying the first line of track in June, and ScotRail announced yesterday that the tunnel will reopen on 7 August, not the eighth as was originally planned.

Phil Verster, managing director of the ScotRail Alliance, said: “I’m delighted to confirm that we will be able to reopen the Queen Street tunnel a day ahead of schedule.

“This has been an extraordinarily complex job. Our people have been working round the clock, often in really challenging circumstances, to get this job done. This has been one of the most significant pieces of work ever carried out on our railway. That we have managed to do it while still keeping people moving is testament to the hard work and dedication of our staff.

“I’m incredibly grateful to our customers for the patience and understanding that they have shown over the course of the last five months. The work that we have been doing at Queen Street will deliver amazing benefits for our customers in the future. Our new faster, longer greener trains will be arriving in just over a year’s time, meaning more seats, shorter journey times with less impact on our environment.”

The entire station is due to be redeveloped by 2019, subject to the relevant permissions.

The latest edition of RTM features an interview with Rodger Querns, programme director for the Edinburgh-Glasgow Improvement Programme (EGIP), on the work at Glasgow Queen Street.

The ORR’s recent assessment of Network Rail Scotland warned that EGIP is not on track to meet key dates in its electrification programme by the end of this year.

(Image c. Network Rail)

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

 

Comments

Nonsuchmike   29/07/2016 at 17:13

“ The work that we have been doing at Queen Street will deliver amazing benefits for our customers in the future. Our new faster, longer greener trains will be arriving in just over a year’s time, meaning more seats, shorter journey times with less impact on our environment.” The words "straining at a gnat and swallowing a camel" come to mind. They open Queen Street and tunnels one day early, but Scots have to wait a couple of years more for the full roll out of newer longer trains. I had to chuckle!

Add your comment

 

related

Rail industry Focus

  • 02/11/2019Monica Barbosa: Women In Rail

    Director of business development and communications at Xrail, Monica Barbosa, thinks women are missing out on exciting opportunities because the lack of gender diversity in the rail industry.
  • 01/11/2019The dangers of fatigues

    Working long hours, poor health, too little sleep, a demanding job and more can all make us tired and affect our mental and physical performance – and when we’re fatigued we make more...
View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

NPR, TRU & Fleetwood Mac

18/10/2019NPR, TRU & Fleetwood Mac

Switch up your playlist with the first #WeAreRTM podcast, gain exclusive insight into the leaders running the rail industry their opinions on recent headlines, visions for the future and meet the personalities behind the job titles. It's no... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

24/06/2019Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

Ahead of his appearance, Malcolm Holmes spoke with Rail Technology Magazine about what key leaders in the industry were doing to improve rail in the Midlands. He said: “It’s very... more >