Major breakthrough as Farnworth Tunnel re-boring comes to an end

North west electrification works have hit a major milestone as Britain’s biggest active tunnel boring machine (TBM), the 9m-wide Fillie, broke through Farnworth Tunnel on Sunday (25 October).

Farnworth Tunnel features two single-line tunnels built in the 1800s that were not large enough to deliver the electrification project. As a result, the larger of the two tunnels had to be filled in with 7,500m³ of foam concrete and then re-bored, making it big enough for both sets of railway lines and the overhead equipment.

The adjacent down-tunnel, which runs south-east, was strengthened to allow some train services to continue to operate during the project.

Breakthrough and train

Contractors J Murphy & Sons celebrated the major breakthrough, with its project manager on the scheme, Mick Boyle, commenting: “Breaking through with the TBM yesterday is a big step to ensuring that the tunnel is secured for many decades of providing a more efficient railway for Network Rail and passengers.

“This has been an exciting project to work on and demonstrates the skills of our team who have worked very hard to ensure that we have reached this milestone.”

Fillie after completing Farnworth TunnelFillie after completing Farnworth Tunnel

Network Rail told RTM in a statement that full details of the reopening of the two-track railway near Bolton will be release as soon as possible.

And its route delivery director, Nick Spall, said: “Farnworth Tunnel is an extremely complex and challenging project in our railway upgrade plan. Breaking through to complete the tunnel is a key milestone for the project. There is still a lot of work to do, and our priority is to get passenger services returned to normal as soon as possible on this key passenger route.

“This will require a short closure of the railway and we are carefully planning this with the train operators to cause the least amount of disruption possible.”

IMG 9006

RTM had visited the tunnel in August where Spall discussed how the major work was helping deliver further electrification in the region, shortly after Fillie had started re-boring the 276m railway tunnel.

In September, Martin Frobisher, route managing director at Network Rail, told RTM that Farnworth Tunnel construction work would be delayed possibly until December after engineers hit an area of running sand on 14 August. This slowed down progress and created big voids, the largest of which needed filling with around 35 tonnes of grout.

Engineers were then tasked with pumping resin into the ground to firm it up before Fillie bored through it.

As a result of unexpected ground conditions, work could not be completed by the initial deadline of 5 October.

Comments

Robert Hill   29/10/2015 at 17:03

As readers of the RailUK Forums will know, the breakthrough was actually on October 25th, not the 28th as stated, but NR kept quiet about it until the 29th for some strange reason.

RTM   29/10/2015 at 17:19

Hi Robert, Thanks for the heads up - will look into it!

Andrew Gwilt   02/11/2015 at 00:55

Once the tunneling, electrification and tracks being laid are all completed. Trains will be running back to normal with the line electrified once the overhead wires goes live and Class 319's will be using the newly electrified line.

Add your comment

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

Most Read

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >