Farnworth Tunnel boring work ‘ahead of schedule’

Network Rail is confident that its major tunnel boring work at Farnworth – an important enabler of electrification between Manchester and Preston – will be complete on time. 

During a site visit on 11 August to the tunnel near Bolton, transport secretary Patrick McLoughlin was introduced to ‘Fillie’, the 9m diameter tunnel boring machine, which is being used to build the new 270m railway tunnel at Farnworth. 

IMG 0838

The work – which began in March – involves re-drilling the existing tunnel, using a machine bigger than those used on the Crossrail and Channel Tunnel projects, so that the rail line can be electrified. This will allow electric services to run from the end of 2016. 

Nick Spall, Network Rail’s LNW route delivery director, told us that he is confident the Farnworth work, which is due to be complete by 5 October, will be finished on time. 

He told RTM that there had been a few teething problems. But Fillie, which cost almost £2.5m from Oldham-based Tunnel Engineering Services (UK), is already ahead of schedule at the moment with 10m of tunnel bored, instead of the planned 9m. 

The works form part of Network Rail’s overall North of England programme, made up of various enhancements collectively costing more than £1bn. 

To prepare the tunnel ahead of Fillie’s work, more than 7,000 cubic metres of foam concrete have been pumped into the tunnel. Now that the machine has been launched it is tunnelling 24 hours a day, re-boring the tunnel, and installing 190 concrete sections which will form the tunnel lining. 

IMG 0827

After his site visit, McLoughlin said: “You can’t upgrade any rail infrastructure without causing a disruption — what I can say is that when this is completed, we will get a better service, a more resilient service and a brand new tunnel that takes two trains through it rather than one as currently happens.” 

IMG 0833

The transport secretary’s visit coincided with the government unveiling a blueprint for how £13bn of government investment in transport will help create the ‘Northern Powerhouse’. 

However, back in June, McLoughlin announced that one aspect of the ‘Powerhouse’ – TransPennine electrification between Leeds and Manchester – was ‘paused’ indefinitely. When asked about this, he said he was awaiting Sir Peter Hendy’s eagerly anticipated report in the autumn and that the work had not been cancelled, just ‘paused’. 

A full report on the site visit and the Farnworth Tunnel work will appear in the August/September edition of RTM.

Comments

John Gilbert   16/08/2015 at 21:16

I am a cynic where politicians are concerned. Given that they have every right to be furious at the total incompetence of Network Rail in its electrification schemes, and the waste of money on the apparently useless HOPS train, I shall nonetheless refuse to believe in any lifting of the "pause" on the two major schemes until it actually happens; politicians utter weasel words and it is their deeds by which we must judge them, even words from such a pleasant man as McLoughlin appears to be.

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

22/03/2019Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

A new £208m Belfast Transport Hub with major rail and bus connections has been granted planning permission by the Department of Infrastruct... more >
New to-the-minute measures for train punctuality introduced to tackle delays

22/03/2019New to-the-minute measures for train punctuality introduced to tackle delays

New measures of train punctuality are to be released by train operators and Network Rail next month in a bid to improve performance. The Rai... more >
FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

22/03/2019FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

FirstGroup has finalised a £100m order for Hitachi AT300 electric trainsets in a partnership between the two companies to create a new Lond... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >
Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

22/01/2019Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

In the jigsaw puzzle of regional transport decision-making, there must be collaboration and compromise. Midlands Connect media lead James Bovill ... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

The West Midlands 30-year strategy

19/03/2019The West Midlands 30-year strategy

Malcolm Holmes, executive director of West Midlands Rail Executive (WMRE), outlines the West Midlands Rail Investment Strategy 2018-2047. Th... more >
read more blog posts from 'the sleeper' >

comment

26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >
East West Rail: the next steps

19/03/2019East West Rail: the next steps

In January, five route options for the central section of East West Rail were published as part of a public consultation on the next phase of the... more >
Rail's role in transit-orientated developments

19/03/2019Rail's role in transit-orientated developments

Jonathan Bray, director at the Urban Transport Group (UTG), argues that transit-oriented developments are the future – and that rail has a ... more >