30.11.17

NR at fault for ‘potentially disastrous’ Liverpool Lime Street wall collapse

Investigators have found that Network Rail was partially at fault for a wall that collapsed onto open railway lines earlier this year.

Services at Liverpool Lime Street ground to a halt earlier this year when the wall collapsed over all four lines into the station, causing commuters five days of disruption while engineers worked to clear the debris.

Today, the Rail Accident Investigation Branch (RAIB) released its report into the incident, which found that Network Rail did not have a suitable risk prioritisation process in place for retaining walls, leaving a “high potential safety consequence in the event of a failure.”

The investigation also found that there had been developments on the leased property adjacent to the cutting, while a small portion of the land was owned by NR. This increase in ground level caused the wall to be subjected to heavy loading.

Heavy rainfall was also cited as another factor that could have played a part in the wall’s collapse.

The RAIB recommended that Network Rail be more aware of walls that have a potentially high safety consequence in the event of failure, as well as that the organisation review its assessment procedure for such walls, using open source data to monitor changes in land use.

“The collapse of the cutting wall on this busy line just outside Liverpool Lime Street occurred without warning, and about 170 tonnes of rubble fell on the railway,” said Simon French, chief inspector of rail accidents. “It had the potential to crush or derail a passing train, with disastrous consequences. However, the signs that a dangerous situation was developing had been there for a long time.

“Network Rail’s examination system did not pick up the significant changes that were taking place behind the wall due to earth moving activities undertaken by the occupier.

“Although I recognise that it can be challenging for the railway industry, it is vital that Network Rail carries out regular and effective checks for activities on its boundaries that may endanger the integrity of its structures.”

Comments

Andrew Gwilt   01/12/2017 at 10:11

Hope that Network Rail can sort it out over the Christmas & New Year period or when they do close the lines as part of the Liverpool Lime Street station upgrade next year.

Martin   01/12/2017 at 13:38

The wall collapse onto the lines approaching Liverpool Lime Street occurred last March and was repaired in five days. The report into the incident (which is the subject of this article) finds that Network Rail 'did not have a suitable risk prioritisation in place for retaining walls'. This is not something Network Rail will be 'sorting out' over Christmas and New Year

Walace58   01/12/2017 at 13:58

Why the misleading headline , corrected in the first line of the text, are your journalists from The Sun?

Peter Jarvis   01/12/2017 at 14:48

It is extraordinary what adjacent landholders will do without telling their neighbours and sometimes they do things which are obvious folly - 'ow, we didn't think of that' - or sometimes plain malevolent, such as heaping cowshed waste next to railway drains. It always helps if the manure goes into the water supply and may be involved in an outbreak of cryptosporidiosis. Railway civil engineers need eyes in the backs of their heads.

Jak Jaye   20/12/2017 at 12:31

Does that apply to the thousands of line side embankments that are devoid of trees i.e. guaranteeing line slides? not holding my breath on that one ,they should be re-named NotWork Fail!

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Rail industry launches new interactive accessibly map for UK rail stations

17/04/2019Rail industry launches new interactive accessibly map for UK rail stations

A new interactive map which lets passengers find out about accessibility at stations has been launched by the Rail Delivery Group (RDG) to help b... more >
Helium balloons causing ‘increasing number of train delays’ at cost of £1m

17/04/2019Helium balloons causing ‘increasing number of train delays’ at cost of £1m

Helium-filled balloons are causing hundreds of train delays at a cost of £1m in taxpayer money every year, Network Rail has revealed. ... more >
Dawlish sea wall gets council planning approval with construction to begin in May

17/04/2019Dawlish sea wall gets council planning approval with construction to begin in May

Plans for an £80m sea wall to protect the Dawlish coastal rail line from extreme weather have been by approved by Teignbridge District Coun... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >
Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

22/01/2019Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

In the jigsaw puzzle of regional transport decision-making, there must be collaboration and compromise. Midlands Connect media lead James Bovill ... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

08/04/2019West Midlands Rail Executive’s Malcolm Holmes on the 30 year Rail Investment Strategy and working with Midlands Connect

Malcolm Holmes, Chief Executive of the West Midlands Rail Executive, joins us to discuss the 30-year Rail Investment Strategy, and how he and his... more >
read more blog posts from 'the sleeper' >

comment

Changing the London skyline with HS2

26/03/2019Changing the London skyline with HS2

Lisa Hogben, HS2 programme delivery manager for area south enabling works, explains how the arrival of HS2’s first tower cranes shows chang... more >
Picking up the pace with high-speed track handovers

26/03/2019Picking up the pace with high-speed track handovers

In 2018 Steve Featherstone, programme director of track at Network Rail, set his team a challenge to secure 100 high-speed track handovers in a y... more >
26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >