Northern line extension: TfL warns of 5-month disruption to Bank branch services

TfL has cautioned passengers on the Northern Line about upgrade works which mean Bank branch services will go for a 5-month period without stopping at Kennington.

Starting on 26 May and finishing in mid-September, the work is part of the organisation’s plans to extend the Northern Line between Kennington and Battersea Power Station.

Engineers will construct four new passageways allowing passengers to change between branches more quickly and easily.

Stuart Harvey, TfL’s director of major projects, said the plans represented the “quickest and least disruptive” method of completing this section of the extension project.

While the upgrades are underway, officials have announced a temporary timetable from Morden on the Charing Cross branch, although Bank branch services will be reduced.

“We apologise to Northern Line customers and to local residents for the disruption this will cause to their journeys,” Harvey said.

“The Bank branch platforms at Kennington are simply too narrow to allow us to safely carry out this vital work behind hoardings while keeping the platforms open.

“Running Bank branch trains through Kennington without stopping will allow us to build the additional passageways we need in the quickest and least disruptive way possible, and are essential to enable customers to access the new Northern Line extension when it opens.”

In November, RTM reported on an important milestone in the extension programme when TfL announced that it had completed the tunnel boring process, connecting Kennington and Battersea via Nine Elms.

The extension will make the City and the West End accessible from Battersea in just 15 minutes, and it is anticipated that it will encourage the regeneration of the Vauxhall, Nine Elms and Battersea areas, with 25,000 new jobs and over 20,000 new homes.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Andrew Gwilt   15/02/2018 at 20:31

Shame that the Northern Line isn’t going to extend to Clapham Junction so that passengers can interchange between Underground, Overground and National Rail. But Battersea tube station once built and completed won’t be too far from Clapham Junction and/or Battersea Park via walking distance. Aswell Nine Elms station that isn’t too far from Vauxhall station and is only walking distance between the 2 stations. As us passengers and ToC’s refer to as Out-of-Station-Interchange.

Philip Stubington   15/02/2018 at 23:46

@Andrew. Besides the cost, as I understand it there were two reasons for not running through to CJ. Firstly that they couldn't handle the likely volume of passengers changing there (and it would be a mess since they'd need to link the Northern Line to something like 18 main line platforms). Secondly a real worry that trains from CJ would be full by the time the reached Battersea.

Steven Hayter   16/02/2018 at 14:49

I understand that the modelling indicates that Crossrail 2 will need to be operational through Clapham Junction before the Northern Line could be extended there from Battersea, owing to capacity concerns, as Philip says.

Sean Farrell   16/02/2018 at 20:44

I've read this article and a number of others. Would bank branch trains traveling from tooting bec to London Bridge still be running?

Melvyn   16/02/2018 at 21:51

It's a pity Kennington Station is not gaining a full upgrade including step free access to all platforms given plans to seperate branches of Northern Line thus making some journeys more difficult if they don't match cross platform interchange direction.

James Palma   21/02/2018 at 08:17

Why apologise to passengers on the northern line? Who really wants to go to keennington anyway? Haha. Joke! I am sure the charring cross branch will be providing an alternative?

Add your comment

 

rail technology magazine tv

more videos >

latest rail news

Five injured in Tube explosion

20/06/2018Five injured in Tube explosion

Five people have been injured in an explosion at a north London Underground station. A Metropolitan Police spokesperson confirmed that police we... more >
Strike news: guards row brings fresh strikes to Northern, South Western called off

19/06/2018Strike news: guards row brings fresh strikes to Northern, South Western called off

Members of the Rail, Maritime and Transport (RMT) union have walked out in a fresh dispute between the union and Northern Rail over a long-runnin... more >
TOC bosses appear before MPs, blame chaos on infrastructure failures

19/06/2018TOC bosses appear before MPs, blame chaos on infrastructure failures

Bosses from Govia Thameslink Railway (GTR) and Northern Rail cited failures in infrastructure being completed in time and last-minute change... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

How biometrics can help improve health and safety measures on railway construction projects

20/03/2018How biometrics can help improve health and safety measures on railway construction projects

ADVERTISEMENT FEATURE Biometric identity, time and attendance specialists Donseed looks at how biometric technology is already starting to enhance health and safety measures on railway construction projects. Advances in technology are starting to transform the way in which the rail network in the UK is managed, operated and maintained.... more >
read more blog posts from 'the sleeper' >

comment

Apprenticeship levy: the latest picture

05/06/2018Apprenticeship levy: the latest picture

Mark Holmes, head of membership and development at NSAR, describes the current resources available to the rail industry to ensure companies of al... more >
Moving in the right direction

05/06/2018Moving in the right direction

Alex Cropper, head of projects group at Transport for Greater Manchester (TfGM), reports on the exciting progress so far in building the Trafford... more >
Overcoming leaves on the line

05/06/2018Overcoming leaves on the line

Paul Gray, professional lead of engineering R&D at the RSSB, explains how latest research proves using double variable rate sanders on trains... more >
Rail: A woman’s world

18/05/2018Rail: A woman’s world

RTM’s Sacha Rowlands reports from a panel debate where six of the industry’s leading figures convened to discuss the fundamental issu... more >

rail industry focus

View all News

interviews

Transforming travel in the north west

06/02/2018Transforming travel in the north west

RTM’s Josh Mines talks to Robin Davis, head of new trains at TransPennine Express (TPE), about the huge rolling stock change journey the co... more >