'Poor use’ of GWML midweek access bigger issue than buried signalling

Despite the known issues with buried signalling cables, the Office of Rail and Road (ORR) is “much more concerned” about Network Rail’s very poor use of midweek access as it tries to make progress on the troubled Great Western electrification programme.

ORR investigators have seen this for themselves on night-shift visits, according to its quarterly Network Rail Monitor for periods 1-7, published this week.

The ORR acknowledged the impact of the line’s unmapped and buried signal cabling on rising costs, but found that the company was not properly using overnight periods – which is when it should carry out most of its work to minimise disruption.

It also blasted Network Rail for the poor quality of information it supplied to the programme’s design contractors.

In October, Network Rail’s boss, Mark Carne, revealed that estimated costs tied to the Great Western electrification programme had nearly doubled since last year, now standing at up to £2.8bn.

Sir Peter Hendy’s long-awaited review of Network Rail’s CP5 programme, published last week, confirmed that buried cables have been a major productivity drain on GWML electrification. Cables were buried beneath the ballast in the 1970s, but not reliably mapped. Mechanical piling methods twice severed the cables – causing expensive disruption to passenger services. So workers are having to dig manual trenches to check for cable location, slowing down progress substantially.

But the ORR said the precise estimate of these extra costs remain uncertain until it can be independently verified. In its Monitor report, it said it is “yet to see the back up to this re-forecast” – but said it is particularly worried about the productivity assumptions the new estimate is based on.

It also cited a series of risks remaining even after the Hendy report, mostly because there have been developments since he started his work that have “materially changed the assumptions underpinning it”.

As well as the greater GWML electrification costs, risks included the government’s announcement of a firm date for the TransPennine electrification programme, “given that the scope is at such an early stage of development”.

The rail regulator also claimed that the “extent of capability weaknesses” that Network Rail must address – through the conclusion of its enhancements programme – has become more apparent, with systemic weaknesses left unresolved.

“These will inevitably introduce uncertainties around the accuracy of such a hurried and complex re-plan,” the ORR added.

Overall, the regulator has found that Network Rail is £58m over budget to date, mostly due to higher maintenance costs from difficulties in achieving targets, higher than expected renewal costs and an overspend in several projects in its portfolio.

It currently expects Network Rail to underperform by £810m in 2015-16, largely because of higher spending than originally budgeted.

RTM has contacted Network Rail for comment but has not yet received a reply.

Comments

Terry K   08/12/2015 at 07:39

There is absolutely no reason for the contractors to hit signalling cables, before any groundwork's can be carried out a CAT Scan MUST be undertaken, If they are hitting cables then they have NOT done their job correctly and therefore should bear the cost of any signalling disruptions caused. Poor excuse from Network Rail

Add your comment

rail technology magazine tv

more videos >

latest rail news

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Se... more >
Contract awarded by Network Rail to strengthen bridges

09/09/2020Contract awarded by Network Rail to strengthen bridges

Three contracts have been awarded by Network Rail to carry out strengthening work to three railway bridges across the We... more >
New electric train fleet revealed for Birmingham’s Cross-City Line

09/09/2020New electric train fleet revealed for Birmingham’s Cross-City Line

The electric train fleet set to transform travel on Birmingham’s Cross-City Line has been revealed to rail passeng... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >