Larger vessels can once again navigate through Reedham Swing Bridge after Network Rail successfully completed a significant programme of repairs to one of Norfolk's most iconic pieces of railway infrastructure.
The 123-year-old structure, which carries rail services across the River Yare while also providing passage for river traffic, had been unable to swing normally for much of the summer due to issues with its central bearing. The bearing forms a crucial part of the bridge's pivot mechanism, supporting the structure as it opens and closes.
Engineers undertook an extensive repair programme that involved removing the ageing bearing and installing a replacement. The work culminated during the August bank holiday weekend when the new component was fitted and tested.
Following a programme of testing and commissioning, Network Rail completed the work ahead of schedule, allowing the bridge to return to service earlier than the anticipated mid-September reopening date.
Despite the restrictions placed on navigation during the repair period, Network Rail and the Broads Authority worked together to facilitate three planned bridge openings between late July and early August. Around 30 boats were able to pass through during those carefully managed operations.
The temporary openings were only permitted after engineers carried out extensive inspections and testing to ensure the bridge could be operated safely without causing further damage. Smaller craft continued to pass beneath the bridge throughout the repairs.
Joe Kennedy, Infrastructure Director for Network Rail Anglia, said:
“This was a major, complex repair of a bridge that is both a critical piece of infrastructure and an important heritage landmark for the region. Our teams worked hard to get Reedham swinging again, but we’re so sorry for the disruption to boat users, passengers and neighbours while we got the job done.”

Rob Rogers, Director of Delivery for the Broads Authority, said:
“The Authority is pleased to learn that the repair of the bridge has been successfully completed ahead of schedule. The inconvenience caused to owners of larger boats unable to pass whilst it was out of action is regrettable. We extend our thanks to those affected for their patience and to Network Rail in dealing with the challenges of such a complex repair on an old, iconic structure.”
Network Rail has confirmed that the bridge will be closely monitored as it returns to regular operation. It is not uncommon for heritage swing bridges to experience minor reliability issues following major engineering interventions, particularly after being out of service for an extended period.

As with previous years, weather-related operating restrictions will remain in place. The bridge cannot be swung during periods of exceptionally high temperatures because thermal expansion affects both the rails and the bridge's structural components.
The completion of the project restores a vital transport and navigation link in the Norfolk Broads, balancing the needs of the railway network with those of the region's important boating community.