Crossrail

07.03.18

Crossrail engineers hit key track, signalling and infrastructure milestones

A series of milestones have been reached as railway upgrades have been completed along the Crossrail route.

Network Rail has completed track work at Pudding Mill Lane, where the Elizabeth line tunnels emerge and meet with the national rail infrastructure, to allow trains to enter and exit the new tunnels from the existing above ground railway.

New overhead power lines and signalling equipment were also required, and the work has connected all the Elizabeth line portals - Plumstead, Westbourne Park and Pudding Mill Lane - to the existing railway.

Over the past 10 weeks work has also been completed on re-modelling the sidings at Gidea Park.

New overhead line equipment and signals have been installed, using 37 steel piles.

Over 3.2km of track have been renewed, with 8,000 tonnes of new ballast and 45,000 concrete sleepers with four new longer sidings, to enable the sidings to accommodate the 200 meter long Elizabeth line trains that will be stabled there.

Driver walkways have been built, and lighting and track drainage installed.

Further upgrade works will continue on the Great Eastern Main Line until April, replacing the overhead wires to improve reliability and continuing to install the systems which will power overhead line equipment.

Ben Wheeldon, Crossrail programme director at Network Rail, said: “Making the final connection between the national rail network and the Crossrail tunnels links east and west for the first time. 

“The completion of these huge pieces of work, including the final signalling commissioning on the eastern section of the Elizabeth Line route is a significant step towards ensuring that the railway infrastructure is ready for the introduction of the Elizabeth Line and is an important part of our Railway Upgrade Plan.”

While the works continue there will be track closures every weekend until Monday 2 April, including Easter weekend, between Liverpool Street and Shenfield, affecting TfL Rail and Greater Anglia services, and London Overground services between Romford and Upminster.

The Elizabeth Line is set to open in December 2018.

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

There are no comments. Why not be the first?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >